SUMMARY OF WORK EXPERIENCE:
More than 21 years of combine technical work experience in fabrication, construction, erection & installation on both offshore and onshore. Inclusive are mechanical equipment, piping / pipeline, structural steel, civil & architectural. Work related such as construction coordinator, project management, consultant, engineering & supervision work project related to oil & gas, offshore facilities, petrochemical plant, refineries, power plant, pulp & paper mill, industrial building & major facilities. Organization and balancing of contractor manpower, equipment, material resources in liaison with the client or owner. Plan, execute and control work activities in accordance with approved drawings, work procedure & specification required by the project. Such as: API, ANSI / ASME, BS, JS & AWS.
EXPERIENCES:
15 November 2003 – 11 July 2005
EMC Construction
Sta. Rita / San Lorenzo 1, 500MW CCGT Maintenance
Philippines
Construction Manager
By having multi-discipline skill I have experienced to lead construction team.
Controlling of construction progress to be ahead of the project schedule and prepared constructions procedures.
Overhead management for staff assignment to various project, and for hiring & firing of construction staff.
Attending managers meeting & coordinating to each department and client regarding construction, maintenance including QHSE for our people.
01 December 2002 – 31 October 2003
Tripatra-Gulf Consortium
PGN Gas Transmission and Distribution Project
28" dia. Pipeline from Indonesia to Singapore
Offshore – 276 km & Onshore – 207 km
Indonesia to Singapore
Construction Coordinator
Project Management and Consultant for the Panaran and Pemping Station.
Responsible for ensuring all of the construction activities are in accordance with the approved procedures and project standard.
Ensuring that various department are fully briefed for each daily activities.
Do & prepare punch list, site memo & give verbal instruction for piping, mechanical, structural and civil works to be coordinated & to expedite to be finished by Contractors such as: HYUNDAI, NACAP / THIESS, NPCC, BOSKALIS & PUNJLLOYD as per given schedule by PGN / PMC.
15 August 2001 – 30 October 2002
Halliburton (Kellog Brown & Root)
ESSO, Exxon Mobil, Petronas & Chevron
Chad – Cameroon Development Project 30"
& 18" dia. 1, 070 km. or 663 miles pipeline from
Chad to Cameroon, Central Africa.
Kome, Chad, Central Africa
Construction Manager (TCN/FILIPINO)
Construct facilities, fabrication & installation of process piping, pipelines, wellhead flow lines, piping hook up & dress up connections.
Meeting with Esso & Exxon Mobil for various reports and project schedule for the additional work to be given to KBR Halliburton.
The project is to develop the oil fields in Chad (US$ 1.5 billion) & construct a 1,070 km. pipeline to offshore oil loading facilities going to Cameroon Atlantic coast (US$ 2.2 billion) and World Bank is the financier.
23 January 2001 – 31 July 2001
Ballast Nedam International
First Gas Philippines
San Lorenzo 500 MW Power Plant
CCGT Project
Philippines
Structural Superintendent
Establish with subcontractors and maintain effective work teams to complete their assigned tasks on time meeting defined budget of quality requirements.
Review of the specification, drawings, technical instruction, TO, Quality System document (Work Methods) during work preparation stages.
11 April 2000 – 07 January 2001
EMC Construction
First Gas Philippines
San Lorenzo 1, 000 MW Power Plant, CCGT Project, Philippines
Construction Manager
Implementing & formalized project plan schedule which includes site monitoring.
Check and monitor the progress & maintain against plan.
Conduct the daily coordination meeting considering the work priority in terms of overall project schedule & look for the security of my people that takes priority.
16 March 1998 – 28 March 2000
Klockner / ROH Joint Operation
PT. Tanjung Enim Listari
Musi Pulp & Paper Mill Project
(Pipeline and Processing Plant)
Sumatra Selatan, Indonesia
General Superintendent (Consultant / Advisor)
In charge for the monitoring of the daily distribution of our people and responsible for the acceptance of the CWSI (Civil Work Site Instructions) follow up & expedite the erection of structural steel.
Structural steel support for mechanical & piping erection or installation.
Prepare as built drawing for piping field run (small & large bore).
Attending meeting with PT. TEL Client (weekly & monthly)
Drawing to be issued to our sub contractors (John Holland, Ballast Nedam, Thiess Engineering and Truba Jurong).
20 May 1997 - 27 February 1998
Kiewit Holt International
California Energy & Halliburton
Pipeline 750 km – 28" dia. pipeline
80 MW Geothermal Power Plant
(Deing, Patuha & Bali)
Central Java, Indonesia
General Superintendent
Night shift general superintendent of wellhead pad & pipeline works for gathering system.
Supervised 200 Indonesian crafts of multi-discipline in all areas separated about more than 10 km each.
The work consisted of activities such as civil, structural and pipelines construction, modification and installation of equipment tanks, pressure vessels etc. expedite the works in all areas to meet with deadlines, and to achieve high work output so that all areas were carried out satisfactory.
21 November 1996 – 30 April 1997
Commonwealth Asia Pacific Ltd. Pte.
Pt.Kiani Kertas
Bleached Kraft Pulp & Paper Mill Project
(Pipeline and Processing Plant)
Kalimantan Timur, Indonesia
Chief Piping Engineer & Inspector
Site checking, to identify the problem that causes the low productivity ratio deficiency on piping installation.
Prepare memo FWO, EWO, or site instruction to be closely coordinated to Beloit Corporation for site adjustment, modification, revision, deletion, or as built drawings.
Involved in inspection, line checking, punch listing and testing of pipe spools.
Responsible for progress update report, pump alignment release notice and documentation.
05 January 1995 – 13 October 1996
Japanese Gas Corporation
Bakrie Kasei Corporation (PTA & CTA Project)
Bakrie Diafoil I-F Project (Plastic)
PT. ASC Project (Asahimas Subentara Chemicals)
Merak & Anyer Indonesia
General Superintendent
Chief of Steel Structures & Civil works on CTA & PTA Projects.
General Superintendent for Industrial Building in Indonesian Film Project.
14 October 1993 – 30 November 1994
PT. NISCONI/TOYO ENGINEERING
PT. Chandra Asri Petrochemical Complex Project
(Biggest ethylene plant in the World)
Cilegon – Indonesia
Piping Design Engineer
In charge of coordination closely with TOYO Engineering Designers for the changes of the drawings based from revision made by TEC.
Site modification etc.
Responsible for the computation of dia – inch cutting length of pipe and material take off.
Site checking to identify the problem that causes the low productivity ratio deficiency on piping installation.
Do the daily and monthly progress report to forecast the anticipated problems for smooth execution.
Lead the daily schedule meeting with the attendance of all concerned contractors for area wise.
Schedule the coordination and discussion of piping prefabrication and material verification etc.
04 March 1991 – 30 September 1993
Euro Mechanical & Electrical Contractors Co.
LNG Plant, Sulphur Plant, ADMA OPCO, D & D Plant Project
ADGAS Pipeline
Das Island, Abu-Dhabi
United Arab Emirates
Project Engineer
Supervision and check the dimensional control items and if fabricated within the contract specification tolerances.
Supervision on welded joint numbers if in accordance with the standard specification and that if satisfies the stipulated requirements.
Inspection and check of D & D project. (Dehydration/Desalting Plant).
Demothballing and re-commissioning works which consists of heat exchangers, valves, pipelines works, fire heaters plus the installation and hydro testing.
Support shall conform to the codes and standard, such as ASME, API, ASTM & AWS collect data from P & I D drawing etc. Involved in data captured and inputting via terminal to the teroman computerized maintenance system.
27 February 1990 – 02 March 1991
JAC Construction
Batangas, Philippines
Caltex Refinery, LMG Chemicals, & Industrial Buildings
Philippines
Construction Manager
Coordinating and attend meeting with the client which regards to the daily progress report & status of structural, piping electrical, civil and mechanical projects as a construction manager.
Presiding the daily coordination meeting, weekly, and monthly.
Conduct actual field monitoring and prepared working drawings for Caltex Refinery and LMG Chemicals.
Prepare inspection report, estimating and others.
Attend the weekly Managers meeting etc.
22 February 1989 – 23 February 1990
Mohammad Al-Mojil Est. & EEI
Riyadh Petromin Refinery
Yanbu Petrochemical Plant
Glycol & Ethylene Plant
Riyadh, Yanbu, Dammam, Abquik, etc.
Kingdom of Saudi Arabia
Structural & Piping Engineer
Expose in process and utility line.
Being familiar with the use of codes and standards.
Do the daily accomplishment report, documentation, crane utilization report, estimating & material take off.
Supervision of maintenance work such as dismantling and cleaning of heat exchanger's construction of pipe supports such as dummy leg support, vessel pipe guide, floor support, anchor support, etc.
05 January 1988 – 24 December 1988
A.G. & P. Co. (Atlantic Gulf & Pacific Co.)
ONGC Project of India
(Oil & Natural Gas Commission Complex Project)
Philippines
Piping / Pipeline Inspector & Engineer
One year experienced on site and fabrication yard as Piping Engineer.
Conform to the drawings and standard, specifications the prefabrication, Inspection, installation & erection of pipe spools.
Being familiarized with drawings and different specification to be coordinated with supervisors and fitter foreman for some difficulties in structural and piping works
Preparing drawings for offshore facilities, piping for the as built, revision and tie-installation. Assures that the fit up of structural members, pipe supports and pipe spools shall conform to the approve drawings by the A.G.& P. standards.
02 October 1985 – 28 December 1987
EEI & Braun Transworld Corporation
Kuwait National Petroleum Company
Refinery Modernization Project
(Up grading Pipeline and Processing Plant)
Mina Ahmadi & Mina Abdulla
Shuaiba, Kuwait
Piping & Structural Engineer
Supervised 142 to 172 people as a Piping and Structural Engineer.
I do the S.E.R. (Site Engineering Request) daily crane utilization report for 45 to 150 tons cranes, inspection for acceptance.
Tracking and expediting of pipe spools and structural steel materials.
Materials take off from the drawing's including pipe field support for process line and utility line.
At site I do the S.E.R., sketch and draft' the structural obstruction which are commonly causes the problem for the completion of the installation of piping at unit 148 C-utility 148 process from area A, B, C,D,E,F & G other unit and area, In-charge for Level 1 up to Level 4 (Both for Piping & Structural).
25 May 1984 – 20 September 1985
JAC Construction
Caltex Batangas Refinery, LMG Chemicals
Philippines
Project Engineer
Coordinates with superintendent and fitter supervisor or foreman for some rectification to be followed before welding and fitting.
Prepares inspection for Caltex Refinery and LMG Chemicals Expansion.
Conduct actual field visual inspection survey for the preparation of working drawing for Caltex Modification and LMG Expansion.
I visit the job site to see the progress of the project and assist in tracking and expediting of materials, necessary for the said project.
Study and identify problems that causes the low productivity ratio deficiency of steel erected and familiar to interpret blue print of isometric, orthographic drawings, basic rigging, spool computation, material take off, estimating etc. which is necessary for the said project.
TRAINING AND SEMINARS ATTENDED:
1.Health Awareness Training Program
Kellog Brown & Root / N'Djamena, T'Chad Africa
2.Project Development Management
Philippine International Multi – Purpose Cooperative of Overseas Workers / Riyadh, Kingdom of Saudi Arabia
3.Countryside Entrepreneurship Development Program
Department of Trade and Industry / Lipa City, Batangas Branch, Philippines
4.ADMA – OPCO LNG & Desalination Project (Dehydration & Desalting Plant)
Das Island, Abu – Dhabi, United Arab Emirates
Safety Training, Operating of Breathing Apparatus & First Aid Course, Sponsored by Abu Dhabi Marine Operating Company
JOB SKILLS: OTHER SKILLS:
Construction Manager Computer Literate:
Project Engineer MS-Word
Construction Engineer E-mailing
Construction Coordinator
Piping / Pipeline Engineer or Superintendent Driving
Structural or Civil Engineer
Inspector (Piping, Structural & Civil)
Quantity Survey Engineer (Estimator)
General Superintendent
Project Coordinator
EDUCATIONAL ATTAINMENT:
University: University of Batangas (Philippines)
(Formerly Western Philippine College)
1979 -1984 (GRADUATED)
B.S. Civil Engineering
College: P.B.M.I.T.
1977 – 1979
Technical Electricity
High School: Saint Theresa's Academy
1973 – 1977 (Graduated)
Elementary: Bauan West Elementary School
1967 – 1973 (Graduated)
PERSONAL DATA:
Upon request
Language Spoken & Written: English / Tagalog / Malay / Bahasa Indonesia
CERTIFICATES & REFERENCE: (Upon Request)
View contact information...
«« previous resume
next resume »»
Search Results (Resumes 351 to 400 of 723)
Go to Search Parameters...
Brief Description
International Trade such as Import & Export Business, Offers, Sales Promotion, Market Research, Different Business Reports / Information's, Estimations and Future Business Plans beside some Administrative Work etc
A Senior Financial, Systems and Accounting Manager with significant experience in the development, creation and management of accounting and reporting systems gained both internationally and domestically. Have worked in the United States and the United Kingdom for Citibank, Xerox, Yale, Louis Dreyf
Field Service Engineer
During my university and professional work, I acquired a solid experience in the field of the program coordination, the logistics and the financial management.
Highly qualified in security, safety and rescue work, a lot of experience in helicopter rescue, work and training camp experiences, military education, calm, reliableand flexible
Geologist with a very good computer literacy
Qualified, results-producing Emergency Management Professional with experience steering and directing all aspects of operations, administration, budgeting, and equipment maintenance. Successful in managing multiple projects with compelling priorities involving program development.
By having multi-discipline skill; I have 21years of combine technical work experience in Project Management/ Consultant/ Coordinator/ Advisor/ Engineering/ Fabrication/ Construction/ Erection/ Installation & Maintenance work on both offshore & onshore.
BSc Applied Geology, with experience in near surface gold exploration as well as geological modeling of various ore bodies at a consultant level. Knowledge of mine design software such as Datamine and also GIS software. Competent traveller.
20 + Years Experience / Supervisor / Heavy Equipment / Haul Trucks / Will Relocate
Having 16 years experience in pumping and assescories of Pipe line, Motors, Engines, System study, Trouble shooting etc. Having abroad experince. Visited Lao PDR, Thailand, Srilanka. Handled Project works at varoius sites in India and in Abroad.
I am a graduate metallurgical engineer with experience in melting of steel and cast iron. I have also worked as a corrosion engineer.
Dedicated hard worker with 10 years mining experience.
Licensed professional civil engineer. Have worked mostly in construction as either an owner or an owner's representative. Enjoy doing field work and would like to work in a foreign country.
HR, Payroll, Operations
Experienced electrical sales, buyer, customer service,contract negotiations,job bidder
Land surveyor with over 30 years experience
Extensice technical skills incorporating computer literacy & engineering discipline. Highly regarded for a proactive attitude and an ability to thinl literally, providing idead & solutions. A dedicated individual, achieving reputation for consistently going beyond what is required.
Environmental Health Safety and Emergency Management Specialist / Safety Trainer in Oil and Gas, Petrochemical and Marine Industries with 15 years experience.
Heavy Equipment Operator/Upend Labourer
I have completed Masters in Commerce( MCOM) and i have more than 7 years expereis in Accounts/Audit.I have strong knowledge in Tally and SAP- Sales & Distribution model
Long experience, professional skills, mastered business sectors: Oil - Petrochemical plants, Banks, Government organizations, Multinational organizations, Hotels & Commercial companies all with its different type of applications, working environments and unique needs.
International HR Manager
Procurement Purchasing Logistics Inventory Control Contracts Negotiations
Security Executive with massive corporate and international exposure. Expert in Afrcan matters and have massive and extensive security network in Africa.
HSE Remote Safety Medic, Offshore Medic, Emergency Medical Technician, Safety Officer
Industrial Electrician 20 yrs. experience in automated industries. PLC, instrumentation, construction, commissioning and maintenance / troubleshooting
Over 20 years Quality Management and Supervision experience in Heavy Engineering Construction Industry
Talented HR professional with a generalist background. Experienced working in a professional services environment with complex hierarchies and matrix management. Ability to operate at both a strategic and operational level, within a geographically diverse team and in an international role.
I Mohammed Yaseen Kajee hereby wish to apply for employment through your company in the capacity of Client Projects Quality Manager, Senior Client Quality Assurance Engineer / Inspector and Client Safety Representative. I have had extensive experience in Quality Management Systems , Pressure Vesse
I have 28 years experience in maintenance, the experience gained in the instrumentation trade up to the management level. I have gained vast experience in technical faultfinding and technical and staff related problem solving, mostly in the shortest time due to process requirements.
Since April 2004: Aeronautic Source Inspector “hardware” in Bourges and Méru (only 1 to 2 missions of 4 hours/month) for a diversified technology and manufacturing leader, serving customers worldwide with aerospace products and services (40% of sales); control technologies for buildings, etc
Experienced in deep excavations for 20 years, specializing in sewer and water and installation of large diameter pipe, as well as Mass excavation and Heavy Highway work.
CA, CIA, CPA
Innovative thinker with broad-based expertise in human resources, and business development.
Financial Manager (expat)
20+ years of experience with the environmental aspects of major energy projects - power plants, pipelines, transmission lines, refineries.
Oracle Functional Consultant with over 10 years of experience in the Finance domain
Piping and Welding Supervisor QA
Engineer with 15 years of experience in Supply Chain, Operation, Project & Construction management
I¡¦m a Canadian/ Syrian citizen with Business, Engineering, Water/Wastewater and (HSE) Health Safety Environment Background I have been working in the field of HSE (Health Safety Environment) management for past 10 years/ 5 yr Management HR BUS PR Project GS ADM OPS
Safety Officer, Process Supervisor and Marine Engine Driver and experienced in Petrochemicals, Power Plant and Marine Industry
Temporary Cards for Surface and Underground Mining
Senior Process Engineer with 14 years of Experience in Oil and Gas and Petrochemical
MSc Mining geology student graduating this summer. Looking for a summer project in association with a company, preferrably in exploration, hopefully leading to employment. Interests are in Gold and Ni-Cu-PGE exploration. Extensive field experience in remote areas.
In addition to academic work, my experience also includes working voluntarily, part-time and full time with both local and international organizations, as you will see in my CV. My work in these organizations hinges on working at community levels in various projects and researches.
Wide knowledge in the field of geology and very good command of the English language. capability to develop different activities in the geology area and to achieve goals in fixed periods of time; ability to work co-operatively, across cultures and organisational boundaries to achieve shared goals.
35 + year mechanic
Vast experience in Engineering, Construction, Mining and Design:
Logistics, Technology, Transport and Management Professional
1
2
3
4
5
6
7
[ 8 ]
9
10
11
12
13
14
15
Seach Parameters
Change search parameters...
CATEGORIES:
Other;
INDUSTRIES:
Mining;
Change search parameters...
Keywords:
(e.g. mining engineer)
Find results with:
ANY of the words
ALL of the words
WITHOUT the words
Save this search parameters...
Post job with this search parameters...
Frequently Asked Questions
What's the most effective way to perform a search?
Go to
Advanced Search
1. Select 'Industries', 'Categories', 'Education', and 'Experience' fields. Click 'Search' and look through results.
2. Enter one or two of the most important keywords. Click 'Search' and look through results.
3. To search within results add more keywords.
How can I find resumes that contain specific exact phrase?
To search for an exact phrase, just put quotation marks around two or more words, for example "mining engineer". Use this feature to narrow your results or to find words that can be typed differently, for example AutoCAD "Auto CAD".
More Frequenly Asked Questions...
Employer's Center
»
Employers Home
»
Feedback
»
Help
»
Post Jobs
»
Edit/Delete Jobs
»
Search Resumes
»
Resumes By Email
»
My Account
»
Log In
»
Log Out
©1999-2009 Misco Jobs. All rights reserved. Contact:
support@miscojobs.com