Misco Jobs
|
Go to Job Seeker's Center »»
|
«« previous resume
Resume #27757
next resume »»
CONTACT INFORMATION:
View contact information...
Objective
Seeking a challenging workplace where I will have the opportunity to utilize my interest in the field of corrosion and to help in achieving the company's long-term vision.
EDUCATION
Bachelors of Engineering Metallurgy & Material Science) Visvesvaraya Regional College of Engineering, India
First Division
July 2002 (REC Nagpur)
WORK EXPERIENCE
Amran Cathodic Protection Systems
Project Engineer
December 2004 - Present
Industry type: Corrosion Control
Functional Area: Cathodic Protecion
Muscat, Oman
Responsible for execution of cathodic protection projects based at Oman and at overseas.
Design and Engineering for cathodic protection systems.
Investigative assessment and trouble shooting of existing CP systems at oil & gas facilities.
Corrpro Companies Inc.
Field Engineer
January 2004 - December 2004
Industry type: Corrosion Control
Functional Area: Cathodic Protecion
Abu Dhabi, United Arab Emirates
ADCO well casing (1400wells) Cathodic Protection project.
Coordinating site activities, construction logistics, CP testing & commissioning
Material inventory, review of drawings & design, and supervision of contractors.
PeeKay Re-rolling Mills (P) Ltd. Metallurgical Engineer
Oct 2002 - Oct 2003
Industry type: Iron & Steel Functional Area: Quality Control
Nature of my job was ensuring the company's product (high strength deformed steel bars) to the specifications laid out by Bureau of Indian Standards (BIS).
I was part of the team responsible for the accreditation of TMT from CRM-Belgium.
I was part of the team that developed a unique high strength deformed steel bar with superior corrosion resistance for coastal environment.
KEY SKILLS:
Design and Engineering Practices of Cathodic Protection System for well casings, tanks & pipelines.
Detailed Investigation, Audit, Analysis and Trouble shooting of CP systems.
ICCP installation for well casings, tanks & pipelines.
Comprehensive CP Site survey including soil survey, groundbed positioning and AC mitigation studies.
TCP monitoring & trouble shooting for piplines.
CP Testing & Commissioning (Solar systems, T/R units, DC-DC converter).
Able to interpret drawings, forecast material requirements and understand QC specifications. Knowledge of various CP materials used.
Quality Control, Testing of Metals.
Excellent background in ferrous & non-ferrous metallurgy Familiarity with manufacturing techniques like casting and hot rolling.
Working knowledge with SEM, Interpreting Microstructures, Metallurgical Preparation, Hardness Testers (Brinell, Rockwell, Vickers, Micro-Hardness), Tensile Testing, Impact Testing, Fracture Analysis, Interpreting NDT, Wet Analysis and Spectroscopy(OES).
COMPUTER SKILLS:
Proficient: MS Excel, MS Word, MS PowerPoint, Windows 9x/2k/XP
Fair: MS Project, MS Access, AutoCAD
Others: BP Solar, Rohrback Cosasco Systems (Corrosion monitoring software)
MAJOR PROJECTS:
OGD-III Upstream Project
ADCO Well Casing Project ADCO, UAE
CP for AGT pipelines (Georgia Section) British Petroluem, Georgia
Integrity assessment and rehabilitation of CP system Occidental of Oman Inc
Investigation of Tank CP system at Shell terminal Shell, Oman
CP for 24" MAF Sohar Crude Oil Pipeline (270 Kms) Oman Gas Company
CP for Upstream Field Production Facilities PDOC, Sudan
CP for Saih Nihayda Gas Plant buried pipeline network Petroleum Development Oman
CP for 48" PDO LNG export capacity increase Petroleum Development Oman
CP for water tanks (Shuheiwat Water Transmission Scheme) CBI / ADWEA, UAE
ELECTIVES:
Failure Analysis of Engineering Materials
Advanced Processing of Materials
Electrical & Electromagnetic Materials
SEMINARS:
Cathodic Protection
Hard Magnetic Materials
Law of Diminishing Theory
DISSERTATION:
Study of High Temperature Properties of some Carbon Steels
For my senior year dissertation project, I worked under Dr. R. K. P. Singh on 'Study of High Temperature Properties of some Carbon Steels'. The aim of the project was to decide the most economic as well as apt material that could be used to meet the stress level and temperatures encountered in axles, bolts, fasteners, automatic transmission components, etc. For this purpose, data regarding various products and their end use were collected from few industries.
Following that, samples of interest were collected. These test samples were then subjected to tensile tests at elevated temperature using INSTRON. After compiling various test results, it was found out that a certain type of Cr-Mo Steels were the best suited for this purpose.
COURSES UNDERGONE:
Senior Year:
Structural Metallurgy, Corrosion And Surface Engineering, Alloy Steels and High Temperature Alloys, Steel Making Technology, Advanced Foundry Technology, Advanced Processing of Materials, Failure Analysis of Engineering Materials.
Junior Year:
Theory and Technology of Heat Treatment, Metal Joining and Powder Metallurgy, Elements of Foundry Technology, Characterization of Materials (Chemical and Structural), Principles of Non-Ferrous Metallurgy, Mechanical Processing of Materials, Ferrous Extraction Metallurgy, Engineering Economics, Electrical and Electromagnetic Materials
Sophomore Year:
Electronics and Instrumentation, Metallurgical Thermodynamics and Kinetics, Engineering Physical Metallurgy, Elements of Ceramic and Polymeric Materials,Heat Transfer and Furnaces, Testing of Materials, Numerical Methods and Computer Programming, Mineralogy and Mineral Dressing
EXTRA CURRICULAR ACTIVITIES:
Won many prizes in athletics, elocution and quiz at school level
Had been member of college soccer team during 1998-99
Had been member of college ball-badminton team during 1999-2000
Had won prizes for Dumb-Charade at university level
Was in charge of design of departmental T-Shirts during junior year (2000-01) and coordinated treasure hunt during annual departmental gathering in junior year
Was the Mess Secretary of my residence hall during my senior year
HOBBIES:
Guitar, Solving Crossword & Puzzles, Automobiles, Reading, Football, Badminton, Swimming
OTHER INFORMATION:
* Possess valid Oman & Indian driving license.
* Attended HSE Induction courses at all places worked.
* Helipcopter Underwater Escape Training (HUET).
* Offshore / Onshore H2S and Breathing Apparatus Training.
* Basic First Aid Training.
LANGUAGES
Proficient - English, Malayalam, Hindi
Fair - Arabic, Tamil
Basic - French
PROJECT OVERVIEW:
OGD-III UPSTREAM PROJECT
Owner: ABU DHABI COMPANY FOR ONSHORE OIL OPERATIONS (ADCO)
EPC Contractor: NATIONAL PETROLEUM CONSTRUCTION COMPANY (NPCC)
Role: Project Engineer
Period: Jan 06 to Present
* Scheduling of the Cathodic Protection works and fine tuning procurement plans & material take-off.
* Liaising with the client to finalize and integrate related specifications like borehole drilling etc.
* Designed the Cathodic Protection system for gas production / injection wellheads (42 nos.), and gas gathering / injection system (78 flow lines and 8 trunk lines).
* Inspection of integrity of existing wellheads (53 nos.) and trunk lines (8 nos.) associated with OGD.
* Coordinating for CP Construction activities.
INTEGRITY ASSESSMENT OF OXY TANKS AT HALUL ISLAND
Owner: OCCIDENTAL PETROLEUM OF QATAR LTD
Role: Lead Engineer
Period: Aug 06 to Present
* Investigation of ICCP system for two nos. produced water separator tanks.
* Evaluation of equipment status.
* Assessment of cathodic protection levels.
* Recommendations for future and planning of monitoring interval.
* Preparation of work Instructions for maintenance and testing.
* Stray current analysis and interference testing.
NEW TAWEELAH B EXTENSION WATER AND POWER PROJECT, UAE
Owner: TAWEELAH ASIA POWER COMPANY (TAPCO)
EPCC Contractor: FISIA ITALIMPIANTI
Role: Design Engineer
Period: Jul 06 to Present
* Designed for the ICCP system of tank internal for 8 nos. potable water tanks.
* Interfaced with EPC contractor for tank roof nozzle arrangement.
* Procurement of Cathodic Protection materials.
ENHANCEMENT OF STORAGE FACILITY PROJECT AT QATAR
Owner: QATAR FUEL COMPANY (WOQOOD)
PMC: ENGINEERS INDIA LTD (EIL, QATAR)
EPIC Contractor: PRASHANT PROJECTS LTD
Tank Contractor: CHICAGO BRIDGE & IRON (CBI)
Role: Inspection Engineer
Period: Aug 06
* Inspected Close Anode System for Tank Bottom
* Reviewed monitoring system for Tank Bottom during design phase.
* Interfaced CP System Design with Tank Structural Design.
* Prepared Quality Control Plan for Cathodic Protection Activities.
PDO 48" LNG EXPORT CAPACITY INCREASE
Owner: PETROLEUM DEVELOPMENT OMAN
Pipeline Contractor: PUNJ LLOYD
Role: Inspection Engineer
Period: Mar 06, Jul 05
* Liaised with PDO to integrate CP SCADA requirements of new 248 Km 48" LNG export line with existing 48" LNG export line (parallel lines), and devised cabling modification for existing 48" LNG line (from which CP current is derived to the new line) at BVS / CP Stations.
* Coordinated and inspected Solid State Polarization Cell installation for OHL AC mitigation.
* Resolved issues with PDO for high CP potentials (on installing magnesium anode), which was basically due to the near perfect insulation state of PPE coating.
* Analyzed Protection levels on the pipelines using CIPS.
INVESTIGATION OF TANK BOTTOM CORROSION AT RAS LAFFAN, Qatar
Owner: RAS LAFFAN POWER COMPANY (RLPC)
EPC Contractor: ENEL POWER
Tank Contractor: CHICAGO BRIDGE & IRON (CBI)
Role: Cathodic Protection Representative (Failure Analysis Team)
Period: Feb 06
* Cathodic Protection Representative for the Corrosion / Failure Analysis Team
EPIC OF NEW CONDENSATE DISPOSAL TANK (T-13) AT NGL PLANTS, MESAIEED, QATAR
Owner: QATAR PETROLEUM
EPC Contractor: GALFAR MISNAD
Role: Inspection Engineer
Period: Feb 06
* Inspected Close Anode System for Tank Bottom
* Interfaced CP System Design with Tank Structural Design.
* Prepared Quality Control Plan for Cathodic Protection Activities.
EPCC FOR ADAR / AGORDEED UPSTREAM FPF, MELUT BASIN OIL DEVELOPMENT
Owner: PETRODAR OPERATING COMPANY (PDOC), Sudan
PMC: OIL & GAS PETRONAS (OGP), Malaysia
EPCC Contractor: DODSAL – HIGLEIG CONSORTIUM
Role: Lead CP Engineer / Design Team Member
Period: Sep 05 – Dec 05
* Liaised with EPC contractor for equipment & manpower requirement for CP activities.
* Coordinated with other engineering disciplines for execution of the project.
* Was responsible for the actual status on the CP construction, and engineering vs. field modifications.
* Supervised Installation and Commissioned ICCP system for 15 nos. tank bottom, Galvanic System for 4 nos. tank internal, ICCP for 1907 tubular foundation pilings, ICCP for buried vessel and Galvanic System for buried plant piping network.
* Designed the Galvanic CP System for buried plant piping.
* Prepared QC Inspection check sheets for CP activities in scope of work.
* Imparted Cathodic Protection Training to Plant & Project Personnel.
* Formulated Operation & Maintenance schedule for Cathodic Protection.
INTEGRITY ASSESSMENT AND REHABILITATION OF CP SYSTEM AT OCCIDENTAL
Owner: OCCIDENTAL OMAN
Role: Lead CP Engineer / Design Engineer
Period: May 05 – Aug 05
* Evaluated existing CP system which included shipping line network, plant facilities, tanks and flow lines.
* Carried out DCVG survey and Current Drain Test for investigation of CP system of certain lines.
* Designed for up gradation of existing CP systems, wherever required.
* Formulated Multi-Phase Rehabilitation Plan for grossly under protected structures.
* Surveyed for and Designed new CP system for upcoming header lines / flow lines.
* Coordinated with client for the final ICCP aspects of steel reinforced concrete pipe support structures.
* Liaised with client for preparation of Tender Document for CP construction activities.
PDO SKIM TANKS AT YIBAL AND LEKHWAIR
Owner: PETROLEUM DEVELOPMENT OMAN
Tank Contractor: OMAN STEEL CO.
Role: Construction Engineer
Period: Jun 05
* Supervised Close Anode System Installation for 2 nos. external tank bottom at Yibal and Lekhwair.
* Developed Project Quality Plan, Inspection Test Plan and QC formats for CP activities.
SHUHEIWAT WATER TRANSMISSION SCHEME
Owner: ABU DHABI WATER & ELECTRICITY AUTHORITY (ADWEA)
EPC Contractor: MARUBENI – TAISEI CONSORTIUM
Tank Contractor: CHICAGO BRIDGE & IRON (CBI)
Role: Commissioning Team Member / Training Coordinator
Period: Dec 04, Jun 05
* Carried out Pre-Commissioning checks for external and internal ICCP for 10 nos. water tanks.
* Assisted the CP Project Engineer for client Training Program at Mirfa and Mussafah Lots.
* Imparted field training for cathodic protection to ADWEA Plant O&M Personnel.
AGT PIPELINE PROJECT (Georgia Section)
Owner: BTC PIPELINE COMPANY, SCP PIPELINE COMPANY
PMC: BRITISH PETROLEUM (BP)
EPC Contractor: SPIE - PETROFAC JV
Role: Field Engineer
Period: Apr 05
* PCP Installation Quality Checks for SCP (46" gas) and BTC (42" crude) lines – 248 Km.
* TCP Monitoring and Troubleshooting (ac & dc potentials) for SCP and BTC lines.
* Analysis of induced AC potential levels on the pipelines.
INVESTIGATION OF TANK CP SYSTEM AT SHELL TERMINAL
Owner: SHELL OMAN
Role: Co-Principal Engineer
Period: Mar 05
* Assisted CP Specialist Engineer for investigation of Tank ICCP system (angular drilled anode system).
* Analyzed useful anode life and CP protection level for the tank CP system.
* Assessed TRU condition and electrical isolation status for the tank CP system.
SAIH NIHAYDA GAS PLANT (SNGP)
Owner: PETROLEUM DEVELOPMENT OMAN
EPC Contractor: SNC LAVALIN – Al Hassan
Role: Commissioning Engineer
Period: Jan 05
* Commissioned ICCP system for buried flow line and trunk line network (Duplex Stainless Steel – pipe material) associated with SNGP main manifold and Remote Manifold Stations.
* Familiarized PDO Engineers with working of DC-DC Converter.
* Carried out interference test with foreign pipelines at crossing locations.
* Prepared Final Client Report.
MAF SOHAR CRUDE OIL PIPELINE PROJECT (MSCP)
Owner: OMAN GAS COMPANY / OMAN REFINERY COMPANY
PMC: MOTT MACDONALD
EPC Contractor: SAIPEM - CCC JV
Role: Lead Survey Engineer / Engineering Team Member
Period: Jan 05 – Mar 05
* Carried out CP site survey & soil resistance survey for 270 Km 24" Crude Oil Pipeline.
* Assessed foreign line crossings, parallelisms and OHL parallelism.
* Determined Ground bed locations considering AC power availability and soil resistivity (SYSCAL).
* Developed Inspection Test Plan and Quality Control Plan for Cathodic Protection activities.
* Prepared Method Statements for Temporary CP System Installation, Permanent CP System Installation and Commissioning of ICCP System.
* Liaised with EPC contractor and fed input to the drafting team to finalize CP drawings.
* Prepared Test Post Schedule and CP Material Schedule.
* Supervised TCP & PCP installation when on construction call.
ADCO WELL CASING PROJECT (1400 WELLS)
Owner: ABU DHABI COMPANY FOR ONSHORE OIL OPERATIONS (ADCO)
EPC Contractor: NATIONAL PETROLEUM CONSTRUCTION COMPANY (NPCC)
Role: Field Engineer
Period: Jan 04 – Dec 04
* Field Survey for determining the ground bed location and cable trench route.
* Soil Resistivity Measurement to decide the type of ground bed.
* Drill Stem Resistance Measurement to finalize depth for deep well ground beds.
* Installation supervision of deep well and horizontal surface ground beds.
* CP Testing & Anode Resistance Measurements.
* Energizing & Commissioning of Solar powered ICCP systems (BP-Solar).
* Monitoring of Solar ICCP systems using BP-Solar software.
* Energizing & Commissioning of Rectifier Energized ICCP systems.
* Installation of Rohrback Cosasco System (RCS) Data Logger software.
* Monitoring of T/R ICCP systems using RCS Data Logger software.
* Material Inventory & Verification of Mark-up Drawings.
View contact information...
«« previous resume
next resume »»
Search Results (Resumes 2001 to 2050 of 2282)
Go to Search Parameters...
Brief Description
hnician/manager with over 15 yrs experience in train scheduling and safety. Expertise in train circulation graphing, train scheduling, and statistical analysis of safety and performance. Strong mathematical, analytical and problem-solving skills; demonstrated leadership; sharp eye for detail.
Buyer/Purchasing Administrator, Planner/Scheduler, Sub Contract/Coordinator
Around five years of experience in the field of heavy fabrication, planning, estimation, procurement, execution, QA/QC activities, designs and production for EPC projects.
I am Mechanical Engineer with 7 years experiences in Engineering and Management
I have a cumulative of 5 years field work experience and my experience varies from manufacturing/processing environment to Information Technology and Oil & Gas.
I have over 27 yrs Elect/Inst experience on industrial and commercial projects throughout the US and Saudi Arabia.
Experienced construction project manager with heavy background in petrochemical production operations
I am a civil engineer designer with a multi - disciplinary consultancy. I am involved in all aspects of delivering flood alleviation schemes including design of flood defences. I have a BEng(hons) from an accredited university and am finishing my MSc part - time. I also have 2 years of site exp.
Graduate with Bachelor Degree in Science Surveying and Geomatics (Hons) from Universiti Teknologi Mara Shah Alam
Petroleum Technician
Accounts Professional having 5.8 years of an experience.
Experienced in Procurement, Supply & Engineering Management
Corrosion, Cathodic Protection, Quality Control, Metallurgy
HAZOP, Risk Assessment, EHS Training, Waste Management, EMS, OSHAS 18001
Industrial Projects Management / Engineering Design,Purchase / Supply Chain Management.,Installation, Erection and Commissioning of Machinery,Business Development,Material Management.
• Effective working alone and as a cooperative team leader/member. • Experienced in cash handling procedures and accounting. • Approximately 3 years of management experience in a food service setting. • Skilled in the planning and developing of catering activities.
Professional mechanical and project engineer, conduting the maintenance and projects within heavy industrial environment blingual, planning, ‎budget control, Reliability, RCM, PdM, PM‎
Professional bilingual Engineer with, mining, constuction, and maintenance experience
Cost Engineering / Schedule development and control, Estimating, perfect computer knowledge (programming level). AACEI member. English, Russian, Japanese languages knowledge. 7 years of working experience. Degree in international business administration.
A self-motivated with demonstrated strength skill rotating equipment analist and reliability engineering experience
Seeking Chemist or Laboratory Technician Position-will relocate
Engineer (Design & Vendor Development), (CAD/CAM) Engineer, 1)Planning and maintaining Our Section and the Customer regarding the Development 2) Visit Companies for our tools Development & make Reports on Current Status3)Responsible for the job planning and implementing with the schedules
B.E. Mechanical. Five plus years of experience in Project Management, Construction Management, Logistics, Budgeting, Cost Estimation, Materials Management, Resource Planning in Construction sector.
Terminating, Conduit Work, Cable Running; Tool Work, Managing & Training Personnel
Civil Engineer
Senior project planner schedule with 12 years heavy industry and construction projects experience ,professional in using MS Project,Primavera P3&P5,MS office,CMMS systema like SAP R/3 , Maximo. Strong technical background , project management and cost control, contract and claim adminstration
Planning, Scheduling, Primavera, Risk management, Pertmaster
Mechanical Engineer with wide experience in Manufacturing, Maintenance, Sales and Service, Application Engineering, Project Engineering and Administration. Total experience of 30 years. Can work in any field like Construction, Hospitality Industry and Process Industry.
Human Resources Generalist
I believe my experience in organization, projects and maintenance in the world largest methanol - petrochemical production site and other experience in foreign trade can help in implementation of your company's highest production, organisational and marketing standards.
Management , strategic management , marketing +EXPERIENCED PAINTER !!!
MA. research skills. people skills.
IT & Technical Facility Project Manager, Systems / Application Design, Development, Deployment, and Integration Manager - Data Centers, Contact/Call Centers, Hospitals, Renewable Energy Sources and Systems, "Green" Engineering/Construction, Clean Energy Technology, Energy Managment Systems / BAS
Project Manager, Plant Technical Manager, Interface Engineering Coordinator, Pre-commissioning Engineer, Commissioning Engineer, Start-up Engineer, Process Engineer, Chemical Engineer
GIS Analyst
Management Administration U S Veteran
B.E CHEMICAL with 2 yrs experience in Project
Seeking career prospects in metallurgical processing, mineral resources (ferrous metals, base metals, precious and rare metals), process improvement and optimization, research and development, project management, process-business analysis, technology policy and resources assessments
Project Manager
As an Engineer I have develop my skills in team motivation, public relation, Product Designing, Project & Product Management etc.I am known for meeting deadlines, following through commitments, being well organized etc.
Analytical skills to perform analysis of project costs and approaching problems, uses well thought out solutions. Prioritization of time management to ensure that project reports are timely compiled. Workload is managed effectively within deadlines. High level Excel user. Specializing in InControl
Sdw
BEng Hons., Naval Architecture & Ocean Engineering, University of Glasgow, Scotland
International Safety / Risk Professional available for fulltime or contract employment.
Occupational Health Safety & Environmental Practitioner, Post Gruate Cert. in OHS&E Management
A Dedicated Occupational Health & Safety Professional and Certified Safety Trainer
12 years experience in instrumentation mining processing plant.holder of a craft certifitecate in process control instrumentation.
Data Analyst
4.5-years experience - project management, construction economics, control, contractual compliance, AutoCAD, 4-D scheduling, cost estimation, risk analysis and probabilistic modeling, technology consulting, work breakdown structures, project financial analysis.
I would like to apply for a position where I can use my extensive experience in Managing, Coordinating, Supervising, Inspecting and Maintaining and my dedication to quality in Systems installation, Electrical engineering, Maintenance and Repair to help you obtain your company's mission.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
[ 41 ]
42
43
44
45
46
Seach Parameters
Change search parameters...
CATEGORIES:
Management;
INDUSTRIES:
Petroleum/Oil/Gas;
Change search parameters...
Keywords:
(e.g. mining engineer)
Find results with:
ANY of the words
ALL of the words
WITHOUT the words
Save this search parameters...
Post job with this search parameters...
Frequently Asked Questions
What's the most effective way to perform a search?
Go to
Advanced Search
1. Select 'Industries', 'Categories', 'Education', and 'Experience' fields. Click 'Search' and look through results.
2. Enter one or two of the most important keywords. Click 'Search' and look through results.
3. To search within results add more keywords.
How can I find resumes that contain specific exact phrase?
To search for an exact phrase, just put quotation marks around two or more words, for example "mining engineer". Use this feature to narrow your results or to find words that can be typed differently, for example AutoCAD "Auto CAD".
More Frequenly Asked Questions...
Employer's Center
»
Employers Home
»
Feedback
»
Help
»
Post Jobs
»
Edit/Delete Jobs
»
Search Resumes
»
Resumes By Email
»
My Account
»
Log In
»
Log Out
©1999-2008 Misco Jobs. All rights reserved. Contact:
support@miscojobs.com