Education:University degree in civil engineering ( M.S.), Bachelor degree in Economics
Languages: English, German, French, Dutch, Portuguese, Mandarin Chinese (Basic)
Areas of expertise:
Management of projects covering design, procurement, fabrication, construction, installation, hook up and commissioning involving:
FPSO's (refer to Bunga Kertas,, Espoir field development, Girassol and Rospo Mare projects), including topsides.
Jackets and decks (refer to SYMS, SHG and I-MNTW projects, total 7 jackets) SYMS platform
Pipelines (refer to SHG, I-MNTW,SHW field development projects, Upper Zakum Main Oil Line & Loading lines, IPC-Heera trunk line project)
CALM buoys and Offshore terminals (refer to Sungai Udang, Sirte Oil, Cilacap, Upper Zakum, Girassol(deep water buoy), Erha (deepwater buoy), Ash Shirh and Dung Quat projects)
Onshore pipelines and pump stations (refer to extension of Indian Oil terminal at Salaya, Sungai Udang and Dung Quat projects)
Hook up works (refer to SHG,I-MNTW,SHW, upgrading of BPB and wellhead platforms in Bombay high field)
In depth knowledge of contractual terms and conditions, design and construction methods and keen commercial negociator.
Computer skills: Extensive programming experience in C, FORTRAN, and Visual Basic languages.Enthusiastic PC user, fully conversant with the use of word processing, spreadsheet, scheduling and data base software. Fully conversant with drafting programs such as AutoCad 2007, Microstation, and Primavera planning package.
Contact details
E-mail: jvdh_2@hotmail.com (note the underscore "_" between 'h' and '2')
Mobile: (+)-60-12-499 36 63 or +(60)-12-503 82 87
Fax: (+)-60-4-826 9722 or (+)-1-770-818 5773
-----------
2006-2008
----------
Company: Bluewater China Offshore Equipment Production Co Ltd.
Position: Construction Manager/Site company representative
Responsibilities: Construction Management for fabrication of Jacket, topsides, covering all phases from shop drawing, procurement, fabrication, testing and pre-commissioning to load out.
Structure: Construction of Soft Yoke Mooring System (SYMS) platform for the Bohai field, client ConocoPhillips China Inc. the project involved the fabrication and load out of:: jacket (2000 tons), Piles (2000 tons), topsides (2,800 ton) and yoke arms (800 tons).
----------
2005-2006
----------
Company: Technip Malaysia Sdn Bhd
Position: Construction Manager
Responsibilities: Construction Management for fabrication, erection, offshore installation works, for onshore/offshore pipeline, tank, pumps and SPM
Projects: Construction of crude oil offloading terminal, water intake and outfall lines and associated basins.- Client: Dung Quat refinery, Vietnam
-------
2005
-------
Company: Canyon Offshore Ltd.
Position: Project Manager
Responsibilities:
Management of sub sea trenching, umbilical laying and survey projects, responsible for all aspect of the works including client liaison, procedure development, appointment and supervision of subcontractor, offshore works, QA and HSE aspects, financial close out. Outfitting of cable lay vessel for umbilical lay, trenching works.
Projects: several projects involving trench, umbilical and flexible pipeline installations, clients BP, Gaz de France.
------------
2004 -2005
------------
Company: Pegasus Inc.
Position: Client representative
Responsibilities:
Management/Supervision of offshore pipeline installation contract on Owner 's behalf
Projects
Installation of Ashdod to Hadera pipeline with related onshore tie in works, offshore Israel, client Israel Electric Corporation Ltd.
-----------
2003- 2004
-----------
Company: Stolt Offshore Services S.A.
Position: Project Manager offloading and mooring system
Responsibilies:
Management from engineering through field installation, including subcontract and vendor management of FPSO mooring and deep water offloading system.
Project: Erha FPSO
-----------
2002—2003
-----------
Company: Intec Engineering SEA Sdn Bhd
Position: Construction Manager
Responsibilities:
Management of all aspects of the works performed by shipyard, topside fabricator and bow turret designer and fabricator. Starting with contract negotiations with shipyard, coordination of day to day works, interface management with contractors and suppliers. Project schedule and cost control
Projects
Projects:
Conversion of MT "Bunga Kertas" to FPSO –Penara & North Lukut field, offshore Peninsular Malaysia- Malaysian International Shipping Corporation.
-----------
2001- 2002
-----------
Company:Canadian Nexen Inc.
Position: Project Manager
Responsibilities
Management of all works related to the installation of second buoy and associated pipeline at Nexen's Ash Shihr Export Terminal. Starting project definition, budgeting followed by preparation of tender document, evaluation and contract award.
Projects
Second loading buoy and associated pipelines at Ash Shihr Export Terminal –Offshore Yemen- Canadian Nexen Petroleum Inc.
-----------
2000- 2001
-----------
Company: Prosafe Production Pte Ltd (company formerly called Nortrans Offshore Pte Ltd. before take over early 2001)
Position: Project Manager
Responsibilities
Management of all activities related to a FPSO conversion project, covering the design, procurement & fabrication of all equipments, components for a floating production system. including its installation. Interface with client, supervision & coordination of design activities performed in house and by outside consultants, subcontractor and vendor supervision and inspection. Responsible for performance of all project activities within the budget, and in accordance with project schedule.
Projects:
FPSO for Espoir field development – Espoir field offshore Ivory Coast – Client Ranger oil Cote D'Ivoire SARL – Processing capacity 45,000 BCPD and 40 MMSCF of gas per day
-----------
1998-2000
-----------
Company: MPG – Mar Profundo Girasol – joint venture between Buoygues Offshore and Mc Dermott ETPM (Stolt Offshore)
Position: Project Manager loading buoy and FPSO mooring
Responsibilities
Management of all project activities related to the design, fabrication, transportation of an offloading system and installation of loading buoy & FPSO, both located in 1400 m water depth. Coordination and supervision of in house design work on loading lines and their interface with the loading buoy & FPSO. Contract negotiation, approval of design, site supervision and quality control of the works undertaken by the buoy manufacturer. Profit and loss responsibility for this part of the project. Emphasis was on the technically challenging aspects buoy project, the CALM buoy in the world's deepest waters, and the commercial complicated nature of this state of the art project. For the FPSO mooring system activities covered the design, procurement of the different components, and integration of these in the floater's hull. Development of detailed procedures for installation of both mooring buoy and FPSO on location.
Projects
Offloading and mooring system for MPG FPSO
----------
1997-1998
----------
Company: Intec Engineering, Houston, USA
Position: Construction Manager
Responsibilities
Overall management of Construction projects undertaken by Intec's regional office in Kuala Lumpur, Malaysia. Duties covered the overall coordination of the works design review & approval, contract negotiation, supervision and quality control of procurement activities and subcontracts, progress assessment, payment control, interfacing with client on a day to day basis and by formal presentation to client's board of directors. This position required a wide hands-on experience in contractual and technical matters. Training and education of local staff was part of the assigned responsibilities. Preparation of bid packages and pricing of new projects.
Projects
Installation of SPM system for 350'000 Dwt tankers at Sungai Udang (Melaka), client MRC, management of EPC contract
-----------
1995-1997
-----------
Company: GAL Offshore Services limited. Bombay, India
Position: General Manager/vice president Construction
Responsibilities
Set up from grass roots of offshore construction department Execution of all offshore works undertaken by the company.
Projects
My duties with this company started with setting up an offshore construction department to perform all activities from price preparation, commercial negotiations with client, project execution, till financial phase out of the project. Recently the company has merged with Great Eastern Shipping Company.
Installation of three replacement pipelines in the Dorood field, client Oceaneering, Owner, National Iranian Oil Company (NIOC),Location Kharg Island, Arabian Gulf
Upgrading of BPA-BPB platform's, subcontractor to Essar Oil Limited, Owner, Oil and Natural Gas Corporation, Location Bassein field, offshore India.
SHG remedial works, subcontractor to Daewooo shipbuilding and heavy Industries, Korea,, Owner, Oil and Natural Gas Corporation, Location Bombay High field, offshore India
Upgrading of wellhead platforms in Bombay High field. Subcontractor to Mazagon Docks,, Owner, Oil and Natural Gas Corporation, Location Bassein field, offshore India.
------------
1991 – 1995
------------
Company: National Petroleum Construction Company Abu Dhabi, United Arab Emirates
Position: Deputy Project Manager
Responsibilities
Overall project management responsibility for major Offshore Installation and Hook up Works for jackets and
Projects
SHG Process complex client Oil and Natural Gas Commission, location Bombay High Field offshore India l-MNTW infill platform project, subcontractor to Larsen and Toubro, Owner, Oil and Natural Gas commission, Location Bombay high field, offshore India
SHW project, Subcontractor to Daewoo Shipbuilding, Owner, Oil and Natural Gas Commission, location Bombay High Field offshore India.
IPC-Heera trunk line, Client Oil and Natural Gas Commission, Location Bombay High & Heera Field, offshore India.
-----------
1985– 1990
-----------
Company: Single Buoy Moorings, Monaco
Position: Manager Installation Department
Responsibilities:
Preparation of detailed procedures for installation Mooring Buoys, Floating Production Units, including loading lines and intra field pipelines. Development of Bid Packages for Installation Works, negotiation of contracts for execution of same. Monitoring of execution of offshore works, end of contract settlement and claim negotiation.
Projects
Installation of Mooring Buoy including Design, Procurement and Offshore pulling of 32 inch deballast line, Client Sumed, Location Sidi Kerir (Alexandria) Egypt
Design and construction of 8 and 6 inch lines. The concrete coated pipelines were simultaneously pulled from onshore make up site to sea., with PLEM attached. The spread mooring consisted of four buoys, tied to the seabed by anchors. The contract included the installation of land lines (10 km) connecting the terminal to the onshore facilities.
Repair of 1O inch oil line at Ekpe platform client Mobil Oil Nigeria, location offshore Nigeria
Repair of a 6 and 8 inch pipeline, client ELF, location offshore Gabon.
Installation SBM and 48 inch loading line at Sirte oil terminal, client Sirte oil Cy, Offshore the Libyan coast.
Installation of 3O kV electrical cable at Djeno terminal client Elf Congo, location offshore Congo
Project management for installation of 30 km long electrical cable between an offshore platform and the onshore oil terminal.
Fabrication and installation of SBM, with associated extension of 42 inch oil line at ADCO oil terminal, client ADCO oil Cy, location offshore Abu Dhabi
Project management for design and construction phase of pipeline extension at ADCO's Abu Dhabi oil terminal, including the re-use of existing pipe supports and combined pipe cum plem installation from a lay barge.
------------
1981 - 1985
------------
Company Bouygues Offshore, Paris, France
Position: Project Manager Offshore projects
Responsibilities:
covered all aspects related to offshore contracting such as preparation of bids, design engineering, development of installation methods, follow up during execution of the works. Technical aspects included for platforms: jacket launching, upending and pile driving ;for pipelines: design (hydraulic, stability, weight coating design), detailed procedures for pipe laying riser installation, specification for all materials and services required for the project. Client relations from bid till claim settlement stage.
Projects
Installation of jacket, topsides and associated flow lines for process platforms in the Kambala and Takula fields, Client Gulf Oil Co., location offshore Cabinda.(West Africa)
project management of the outfitting of lay ramp on the BOS 400 barge
------------
1978 - 1981
------------
Company: R.J. Brown and Associates Rijswijk, The Netherlands
Position: Project Engineer
Responsibilities:
design of pipeline systems and supervision of construction activities on sealine installation works
Projects
Development of the Upper Zakum field, Client ADNOC, location Arabian Gulf offshore Abu Dhabi
Design of the Main oil line and three loading lines, pipe sizes were 42 to 48 inches.48 inch pipeline across the Firth of Forth, client British Gas, location Scotland
24 inch gas line from North Rankin platform to Dampier client Woodside Petroleum Offshore Western Australia.