CONTACT INFORMATION:
View contact information...
Date of Birth: 08-31-1971
Sex: Female
Marital Status: Married
Nationality: Indian
Visa Status: H4
________________________________________________________________
Educational qualification:
M.E. [Design & Production of Thermal Power Equipment – Mech. Engg.] from
Regional Engineering College From Tiruchirappally, Bharathidasan university, India with 69 % - First Class During 1994-1996.
B.Tech. Mechanical from R.V.R & JCOP College of Engineering, Nagarjuna university, Guntur,
India with 71 % - First Class During 1989 - 1993.
Additional Qualifications:
Post Graduate diploma in Piping Design from MIT College - Pune, India
With 71 % First Class.
Certificate Course in Pro-E and Ideas from Neha Engineering Solutions, Pune, India.
Computer Skills:
Used Extensively: Word, Excel, Access, and Power Point
Stress Analysis software: CAESAR-II [for Piping Stress Analysis], CADISON, PDMS
STAAD-III [for Structural Analysis and Design]
CAD software: AutoCad-14.0, 2000
CFD software: CFX-4 [used for single-phase flow study]
Modelling Software: Pro-E, Ideas
ERP: BaaN and PDM
Languages: C++, Java
Profile:
* I have total seven years experience in EPC of Water Tube Boilers and industrial power plants.
* Worked at Thermax Babcock & Wilcox Ltd, India (A joint Venture of Thermax, India & Babcock and Wilcox – USA), a well-known boiler manufacturer company.
* I have handled number of projects and have excellent functional knowledge of Engineering of Projects and possess very good knowledge of Manufacturing, Procurement and Construction functions of Engineer to Order industry.
* I was Key User during implementation of PDM and was responsible for pre and post implementation activities.
* I am well conversant with all modern management tools like, TQM, BPR, etc.
* I posses good communication and inter personnel skills.
Experience Summary:
April 1996 To March 2003:
Company: Thermax Babcock and Wilcox Ltd, India
Engineering of Water Tube Boilers –
For seven years I was looking after engineering of various types of water tube boilers, and was responsible for following activities.
1. Issue of long lead bill of materials for pressure parts. Boiler and pressure vessel design as per ASME,
IBR and BS codes. Stress and stability analysis and design of pressure parts, pressure vessels and boiler house structures. Piping engineering including design of Plant & Equipment Layout, Piping Layout,
Stress & Piping Flexibility Analysis etc. Preparation of specifications for bought out equipment like fans, feed water pumps etc.
Self is well conversant with international codes like ASME Sec.I,II,VIII, ASME B31.1 & 31.3,
BS1113, UBC, IBR, IS800 etc. used in Pressure Vessel and Design of Steel Structures.
2. Preparation of detailed equipment and pressure vessel drawings, P&IDs, Piping GA and Isometrics, preparation of engineering specifications and getting approval from third parties and statutory bodies.
3. Control of Project schedules and cost, co-ordination between different functions likes Projects, Materials,
Manufacturing and Engineering.
4. Standardization and parameterization of design, drawings and product components, standardization of procedures and practices, Auditing of internal business processes and functions as per requirement of ISO9000-2000.
During my tenure I had worked on the following projects.
1. Bajaj Hindustan Ltd: 1 x 100 TPH, 42/32 Bar (g), 425/400 deg.c. Pinhole Grate Boiler with auxiliaries for sugar plant at Golagokharnath, KHERI, UP, India.
2. SRIRAM EPC: 1 x 35 TPH, 66 Bar (g), 485 deg.c. travelling Grate Boiler with auxiliaries for
6 MW bio –mass based power plant at tekulapalli village, Khammam Dist., AP, India.
3. Indian Oil Corporation Ltd:- 2x 50 TPH, 45 Bar(g), 480 Superheated, Naphtha Fired boiler & accessories in Guwahati, India.
4. KAJARIA IRON CASTINGS LTD: - 1x 22 TPH, 42 Bar(g), 480 Superheated, BFG / LDO, site
Assembled boiler & accessories in UP, India.
5. ONGC, Hazira: 1 x 37.4 TPH, 20 Bar(g) saturated gas fired boiler, UP, India.
6. ETA – Emirates Trading Agency (DUBAI), 1 x 38 TPH, 30 bar (g),450 Gas & oil fired boiler, DUBAI.
7. JGC CORPORATION, Turkmenistan: 2x 80 TPH, 14 Bar(g) 250 deg.c oil & gas fired boiler.
8. HYUNDAI engg. & construction ltd., Madras 2 x 12.5 TPH / 14Bar(g), saturated oil fired boiler.
9. MITSUBHISHI HEAVY INDUSTRIES LTD., Haldia 1x 71.2 TPH, 13Bar(g) saturated oil fired boiler.
10. VARDHMAN ACRYLIC LTD, Bhruh: 1x 42 TPH,45 Bar(g), superheated coal fired AFBC boiler.
11. RELIANCE, Jamnagar: 1 x 39 TPH 39 Bar(g) superheated oil fired radiant boiler