Misco Jobs  |  Go to Job Seeker's Center »»   |  
 
«« previous resume Resume #29327 next resume »»
CONTACT INFORMATION:
View contact information...

1995 – 2005 FT. MCDOWELL INDIAN COMMUNITY - Fountain Hills, AZ
Construction Engineer - Managed construction of 1500 acre pecan farm. Items included, clearing, main line piping, distribution piping, pump station(s), backup well field, tree layout and fencing. Total cost $6 Mil. Also managed construction of 50 new home additions, $3 mil water, electric and phone upgrades along with new subdivisions and roads. Recently competed a new 10.7 Million dollar wastewater treatment plant and have started a 4.4 Million water upgrade and a 5 Million sewer upgrade.

1993 – 1994 STATE OF ARIZONA, DEPT. OF ADMINISTRATION Phoenix, AZ
Project Manager - Temporary position assisting in building projects. Duties included negotiating and contracting for professional services, preparing bid documents and construction administration.

1984 – 1993 KS ENGINEERING & CONSTRUCTION Tempe, AZ
Partner/ Owner/ Public Works Contractor - Specialized in school work and industrial projects. Design/ Built custom homes. Performed all phases of work including the bidding, project management, supervision, accounting and all items necessary to run a successful business.

1979 - 1984 ARIZONA PUBLIC SERVICE, NUCLEAR CONSTRUCTION Phoenix, AZ
Senior Civil Engineer/ Owners Representative - Reviewed all plans/equipment/procurement/costs of a civil or architectural nature. Gained specific knowledge in nuclear design and construction as well as quality assurance and licensing.

1979 DAMES AND MOORE, Phoenix, AZ
Geotechnical Engineer - Earth dam design

1977 MACHINERY ERECTION Ajo, AZ
Boilermaker - Trade labor for Local 627

1976 M. W. KELLOGG Donaldsonville, LA
Field Engineer - Field work on new Ammonia Plant

1973 - 1976 M. W. KELLOGG New Orleans, LA
Field Engineer - Performed plant layout and coordinated subs. Prepared schedules, purchased materials, performed testing at new Shell Oil Refinery.

EDUCATION:
Arizona State University M.S. Civil Engineering 1979
Arizona State University B.S. Construction 1973

PROFESSIONAL ASSOCIATIONS:
Registered Civil Engineer, Arizona, No. 15280
Registered Land Surveyor, Arizona No. 16154
Member, Panel of Arbitrators, American Arbitration

DETAILED BACKGROUND:
I began my career working in industrial construction after graduation from Arizona State University in 1973.

I was first assignment was in New Orleans, LA, at the Shell Oil Refinery working on-site as a field engineer for M.W. Kellogg. At Shell, I performed foundation layout and coordinated subcontractors. I later prepared schedules, made minor design modifications, purchased materials, and conducted hydro tests.

In 1976, I returned to Arizona for graduate studies in Civil Engineering. During my term at ASU, I worked part-time throughout the year. Positions included additional field work for Kellogg, analysis and design for Dames and Moore, and as a trade labor boilermaker for Phelps Dodge.

Upon graduation in 1979, I joined the Nuclear Project Management Staff of Arizona Public Service. My responsibilities included review of all engineering, design, equipment, costs and procurement of all items of a civil or architectural nature and coordination of any additional review which was necessary.

During my term with the Project, I gained specific knowledge and experience in contract administration, procurement methods, nuclear power plant design, construction and engineering standards, cost estimating, quality assurance, and nuclear power plant licensing.

In 1984, I began as Owner and Project Manager at KS Engineering and Construction. Since that time, KS performed public works contracting with most of the major municipalities and school districts in the Phoenix area. All projects have covered the broad spectrum of commercial and industrial construction. The diverse nature of these projects include; stadium renovations, waste water dechlorination facilities, an emergency chlorine scrubber, water well modifications, computer and remote telemetry units, and hazardous waste storage facilities. KS also built school modifications, additions, and sports facilities.

In January, 1993, KS ceased operations and I accepted a temporary position with the State of Arizona, Department of Administration to assist in a 15 million dollar build out of newly purchased buildings and to augment the needs of the prison construction program. Duties included negotiating and contracting for professional services, preparing and competitively bidding for construction services and administering construction contracts. Project responsibility included office space renovation, gas line replacement, installation of plate and frame heat exchangers, purchase of HCFC chiller units, fire safety systems, and voice\data systems.

After completing projects for the State, I accepted the position of Construction Engineer with the Ft. McDowell Indian Community in 1995. In this position, I have managed construction and helped design a Bureau of Reclamation funded 1500 acre mist irrigated pecan farm. Activities included clearing, fencing, construction of roads and drainage structures, overseeing testing, building two VFD electric turbine pumping plants, a 5 plant backup well field, over 15 miles of mainline piping and over 150 miles of distribution piping. Approximate cost - $6Mil. During and after project construction, I have also managed bidding and construction of 50 new homes, a $3Mil Community water, electric and telephone upgrades, along with new subdivisions and roads.

In January, 2002, Ft. McDowell constructed an $11Mil SBR Wastewater Treatment Plant using a modified Design/build contract. I had the full responsibility for overseeing the design and construction of the facility. The plant completed, on time with no change orders and has functioned excellent. After the completion of the facility, I oversaw completion of design and bidding for $4.5Mil domestic water upgrade. This upgrade consisted of refurbishing two existing wells, installing 4 storage tanks with about 1Million gallons of storage, 7 miles of new waterline and an automated booster pump station. This project completed in October, 2004. Currently, I have started construction on a $5.3 million sewer system and lift structures.

Completed Projects 1995 - 2005

PROJECT NAME DATE COST CONTRACTOR

RV Park 9/1/2004 $5,000,000 W.E. O'Neil
Dry Conduit for Fiber Optic and Cable 8/1/2004 $188,000 Hunter Contracting
Sewer Design CM at Risk - design portion 3/3/2004 $57,000 Hunter Contracting
Driveway and Road Improvements 3/3/2004 $1,100,000 LTC
Golf Course Irrigation Line 1/11/2004 $100,000 LTC
Sewer Construction - CM at Risk 1/10/2004 $5,300,000 Hunter Contracting
Out of Africa Reclamation 1/6/2004 $100,000 Ft. McDowell S&G
Water Delivery System Design and CA 10/10/2003 $450,000 Stantec
Water Delivery System Construction 10/10/2003 $4,600,000 MGC
Recreation Center Ramp and Drainage 5/19/2003 $25,000 C&W Restoration
Sewer Design Casino to Grande Wash 4/12/2003 $506,000 Stantec
Utility Rate Study 4/6/2003 $50,000 L. Gold and Assc.
Waste Water Operations 4/1/2003 $240,000 Severn Trent
City of Phx - Wellfield Turn Over 1/27/2003 City of Phoenix
Casino Remodel 12/12/2002 $2,300,000 Kitchell
Adventures Roof Study 10/13/2002 $1,000 Landa & Assc.
Foundation Underpinning 3/14/2002 $18,000 AZ Helical Piers
Natural Gas Line 3/12/2002 $175,000 Southwest Gas
New Orchard Development - BOR 2/2/2002 $2,500,000
Clubhouse Booster Pump Station 10/22/2001 $35,000 Stantec
Clubhouse Booster Pump Station 10/22/2001 $150,000 Wespac
Waste Water Plant Design Build 5/12/2001 $10,800,000 Hunter/ Wilson
Recreation Center Remodel and Painting 5/3/2001 $82,500 JAR Construction
Shipping and Receiving remodel 2/15/2001 $130,000 Agate, Inc.
Scoreboard 12/20/2000 $20,000 Agate, Inc.
Adventures remodel and water supply 12/1/2000 $175,000 JAR Construction
Golf Course Sewer and dry conduits 12/1/2000 $200,000 LTC
Golf Course Irrigation Well and Infrastructure 10/10/2000 $250,000 LTC
Earl Stratton House 8/8/2000 $50,000
Waste Water Treatment Plant Design 8/1/2000 $900,000 Malcolm Pirnie
Water Needs Study 6/7/2000 $52,200 Stantec
Hotel Feasibility studies 3/3/2000 $500,000 Bergman Walls
Temporary Fire Station 2/28/2000 $100,000 Agate, Inc.
City of Phx - Wellfield Evaluation 1/7/2000 $18,000 Stantec
School Building Site Plan 7/21/1999 $25,000 CMX
Javalina Water Lines 3/1/1999 $40,000 LTC
Dodgers Spring Training Site Planning 2/18/1999 $50,000 Speedie/ CMX
Waterline/tank fire protection Phase II 12/8/1998 $1,400,000 T&T Construction
New Well Rodeo Grounds 10/10/1998 $20,000 SW Water and Min.
New Water Services 7/14/1998 $104,291 Ft. McDowell S&G
Community Well Improvements 4/28/1998 $40,000 Yost and Gardner
Community Well Improvements 4/28/1998 $250,000 T&T Construction
Jomax Quarry Investigation 3/14/1998 $30,000 SW Water and Min.
Boundary Pond Study 2/2/1998
Yavapai Hills phII Road and Infrastructure 1/9/1998 $302,000 Monks
South Farm Road 9/20/1997 $595,000 Banicki Construction
Yavapai Rd. Dry Conduits 8/19/1997 $161,915 Ft. McDowell S&G
Surama Dry Utilities 8/19/1997 $162,000 Ft. McDowell S&G
Acid Injector 8/4/1997 $25,000 Ag Acid Inc.
Yavapai Rd. Dry Utiltites 6/24/1997 $140,000 Hard Rock Const.
South Area Orchard Irrigation System 4/28/1997 $729,000 Rain for Rent
South Area Pipeline Delivery System 4/16/1997 $2,600,000 T&T Construction
Tribal Farm Well Pumps and pipelines 1/20/1997 $300,000 T&T Construction
Weir Modification 12/17/1996 $11,000 Cactus Con.
Land Smoothing and Ripping 12/12/1996 $100,000 Ft. McDowell S&G
Well Design for Farm 9/20/1996 $35,000 SW Water and Min.
Well 3 Pump, motor, and piping 9/10/1996 $57,000 Watt-Irr
Farm Road Surveying 7/22/1996 $10,000 Ansco
35 New Homes 7/17/1996 $3,700,000 ABR
Casino water tie in 4/16/1996 $20,000 Cactus Con.
Fire Protection Phase 1 4/4/1996 $578,000 Lee's Backhoe
South Area Farm Irrigation Line 2/14/1996 $353,000 Watt-Irr
North Area Pipeline Delivery System 1/19/1996 $845,000 T&T Construction
South Area Farm Fencing 1/16/1996 $139,000 Associated Fence
Well Drilling 1/4/1996 $289,000 Weber Pump
North Area Farm Fencing 12/15/1995 $48,000 Acme Fence
Community Health Center 12/1/1995 $2,200,000 Summit Builders
Electric Line to Rodeo Grounds 10/10/1995 $144,000 SRP
New Baja Gas Station 9/15/1995 $1,700,000 B.L. Weber Group
Baja Gas Remediation 9/14/1995 $611,000 Groundwater Tech.
Rodeo Ground Development 9/9/1995 $101,000 Gladstone
Daycare Center 6/28/1995 $400,000 BCS
Landfill Closure 4/1/1995 $365,000 Kajima
Main Farm Road 4/1/1995 $729,000 Hunter Contracting
Orchard Development Planning 3/1/1995 Ecoplan

$55,581,906

View contact information...
«« previous resume next resume »»
Search Results (Resumes 2001 to 2050 of 2726)Go to Search Parameters...
Brief Description
By having multi-discipline skill; I have 21years of combine technical work experience in Project Management/ Consultant/ Coordinator/ Advisor/ Engineering/ Fabrication/ Construction/ Erection/ Installation & Maintenance work on both offshore & onshore.
Excellent PC knowledge and technical assistant experience
I have worked in management positions for over 15 years in both the construction and manufacturing industries. I have had up to 120 employees under my supervision at any given time. HR, production, purchasing, documentation and inventory all under my supervision. Workflow and quality #1 priority.
Construction / mining / environmental
Diploma in Chemical engineering. Now working in leading Engineering Institute of India as a Sr. Tecnical Assistant.
8 yrs of exp as mechanical engineer
To work with the state-of-the-art machines with utmost aims of achieving result and proactive in competing with the challenges in oil and gas sector.
Electrical & Instrument Engineer (2006-Now), MIGAS Certified Welding Inspector (2007), Process Quality/Internal ISO Auditor (2004-2007), Product Failure Analysis (2004-2007), Electrical & Instrument Design Engineer (2002-2004), Lecturer Assistant/Junior Lecturer (2000-2002)
Rotational Equipment, Power Infrastructure E&I, O&M, & International ISO Quality and Safety Systems
I have implemented and maintained 7 ISO 9000:2000 Quality Management Systems for several leading companies.
Certified civil engineer with a strong background in oil & gas, industrial, building projects
I am an experienced Wireline Supervisor with cased/open hole experience.
I am an Environmental and Chemical Engineer, working in an oil and gas sector as an EIA specialist at Kuwait
I am a Canadian, "Hands-on", Project Manager/Superintendent interested in International work again. My extensive experience is in Heavy/Civil and Oil & Gas Pipeline Construction. I have a reputation for completing on-time, safe and cost-effective projects in various climates and nationalities.
Over 14 yr experience in Instrumentation/Control/Electrical of Oil&GAS OFFSHORE & ONSHORE.
HSE Manager, Advisor for International Oil/Gas Company, Led Assets to top quartile performance. Graduate engineer and Certified Safety Professional
Providing technical review and recommendation for peers. Knowledge in Project Managemant, HYSYS. Training in ISO 9001:2000, OHSAS, ISO 14001:2004
If you are looking for a dedicated, hardworking, honest, dependable employee who can think “Out Side the Box”, see further into the future than the end of his nose and is a dedicated team player - your search may be over.
Hands-on engineering and construction individual with extensive experience in all stages of the industry, project & site support, field & maintenance engineering, technical expertise and interpersonal skills in order to function within a multi-discipline team or operate within a stand-alone environm
Experieced in reliability improvement by implement RCA, RCM and Condition Monitoring technologies. Certified as Vibration Analyst Category III.
I have had experience in most forms of drilling, workovers and stimulation. I have limited coil tubing experience, but have a good working knowledge. I am used to working overeseas with people whose first language is not english.
Licensed professional civil engineer. Have worked mostly in construction as either an owner or an owner's representative. Enjoy doing field work and would like to work in a foreign country.
HR, Payroll, Operations
Extensive experience in supervision and inspection of structural and architectural works for high rise buildings, residential, commercial, industrial, roads and bridges and large infrastructure with an over all responsibility for successful and timely project delivery
Water treatment chemist
Professional Qualification: Bachelor of Engineering (Mechanical); Gulbarga University, Gulbarga. Year of passing Oct. 2000 With the aggregate of 78%, First Class with Distinction. Worked as Junior Erection Engineer for Power Engineers Under 2x25mw Wadi Power Plant
Experienced Senior Technician in Marine/Railway/Mechanical Engineering to obtain a greater opportunity in a challenging and professional environment in which be able to perfect my skills and to learn new things in order to reach the top of my profession and for company's benefits and productivity.
I am Diploma Engineer with total 6+ Years of experience in various engineering field, particularly 5+ years of experience in piping/pipeline Design Engineering for Onshore projects. Presently working as a Pipeline Designer for M/s. Worley Parson Engineering LLC., Oman
A position where I can use and enhance my Linux/Unix, POS, PKI, Smartcards and network security skills in a company where I can contribute with many years of hands-on experience
Computer software as: Office - AutoCAD- mechanical desktop - working model + fluent in speaking, reading, writing English & Turkish + Farsi is my native language+ Azeri is my mother tongue
I am a Chemical Engineer with Masters in petrochemicals and polymers. Problem analysing and solving capabilities supported by strong technical background and enhanced by effective communication skills are my major competencies.
Diploma in Chemical Engineering and 11 yrs. of experience of refinery and petrochemical plant operation as a field/panel operator.
I HAVE ALOT OF EXPERIENCE IN THE ENVIRONMENTAL INDUSTRY
Extensive experience in Civil Engineering CAD Designer/Drafter field, in positions requiring supervisory, administrative, analytical and IT skills
Long term experienced : wanted , Painting Inspector , Paint Superintendent or Technical Sales
I have been trained and have experience integrating the spectrum of the logistics processes within the operational, acquisition, and wholesale environments. The major logistics processes include distribution, materiel management and contingency operations. Duties included directing and managing dis
Design and Construction, Engineering, Calculations, Quality control, Installation and Start Up of new Equipment, Electrical and Electronics Repair and Maintenance
Over 20 Years Experience Process Operator,Commissioning and Start Up Heavy Oil ,Oil and Gas Production
Trucking experience 20 plus years, good on tools, excellent mechanical understanding
15-years of experience as Document Controller for vendor & design documentation in gas and oil industry.
Experienced electrical sales, buyer, customer service,contract negotiations,job bidder
I am Aldrin Entac, male, single and 26 years old. My Present work Exposed me in Construction Site, working on ELV system Company as a Site supervisor for BMS (Building Management System) Structured cabling System,Security System, Audio Video System, Broadcasting System, GSM System, TETRA System etc
Excellent team working skills, Excellent negotiation skills, capable of working under pressure and meeting deadlines, high quality customer service skills, and high quality communications skills
Environmental Health Safety and Emergency Management Specialist / Safety Trainer in Oil and Gas, Petrochemical and Marine Industries with 15 years experience.
Health safety and environment officer
Geothecnic, environmental, hydrogeologic, operation
Experienced Administration analyst with areas of expertise in Strategic management, Finance, Logistics and supply chain, Contracts Administration, Business Administration along with latest british MBM degree in Business Management
Experienced and innovative operation & maintenance engineer with technical leadership in commissioning & operation and maintenance activities, quality achievement, reliability, efficiency, customer service and cost reduction goals. High level of management skills with outstanding leadership and
I am part of the team Responsible for the routine, preventive & Predictive Maintenance of all the Static & Rotary equipments of LPG, NGL, Dehydration unit & Sulphur Recovery Unit.
Site Manager, Supervisor, Commissioning, Start up, Troubleshoot,
First   1   2   3   4   5   6   7   8   9   10   11   12   13   14   15   16   17   18   19   20   21   22   23   24   25   26   27   28   29   30   31   32   33   34   35   36   37   38   39   40   [ 41 ]   42   43   44   45   46   47   48   49   50   Next   Last
Seach Parameters

Change search parameters...
CATEGORIES: Operations;
INDUSTRIES: Petroleum/Oil/Gas;
Change search parameters...
Keywords: (e.g. mining engineer)Find results with:
Save this search parameters...
Post job with this search parameters...
Frequently Asked Questions
What's the most effective way to perform a search?
Go to Advanced Search
1. Select 'Industries', 'Categories', 'Education', and 'Experience' fields. Click 'Search' and look through results.
2. Enter one or two of the most important keywords. Click 'Search' and look through results.
3. To search within results add more keywords.

How can I find resumes that contain specific exact phrase?
To search for an exact phrase, just put quotation marks around two or more words, for example "mining engineer". Use this feature to narrow your results or to find words that can be typed differently, for example AutoCAD "Auto CAD".

More Frequenly Asked Questions...
Employer's Center


» Employers Home
» Feedback
» Help

» Post Jobs
» Edit/Delete Jobs
» Search Resumes
» Resumes By Email

» My Account
» Log In

» Log Out
 
©1999-2009 Misco Jobs. All rights reserved.  Contact: support@miscojobs.com