Misco Jobs  |  Go to Job Seeker's Center »»   |  
 
«« previous resume Resume #4757 next resume »»
CONTACT INFORMATION:
View contact information...

B.E. Mechanical Engineering having graduated in the year 1990 in FIRST DIVISION from Osmania University, Hyderabad, Andhra Pradesh, INDIA.

IT Exposure

PRIMAVERA PROJECT PLANNER P3, MS PROJECTS, MS OFFICE including MS Access, MS Excel and MS Word. Can comprehend AUTOCAD drawings pertaining to Civil, Mechanical & Electrical areas.

CAREER HISTORY:

Present Employment

1. Organisation: QGM Energy LLC, Dubai (a BRITISH Company)
Period: From November 2003 till date
Position: Planning Engineer

Brief Job Profile

Presently working for a project viz. Conversion / Refurbishment of a Jack-Up Drilling Rig(In-House).

The nature of Job is as follows:

* Preparation of Preliminary & Detailed Project Schedule (at micro level) with Project Outline
* Preparation of Planned & Actual progress curve (S-Curve) indicating the Progress % on a Weekly & Monthly basis
* Preparation of Cost, Time, Resource (CTR) Analysis Reports
* Preparation of Material Status Report
* Liase with all Personnel viz. Construction Manager, Site Superintendent, Technical Design/ Engineering, Quality Control / Inspection etc.
* Preparation of Histograms
* Conduct periodic project status review meetings/discussions with Client as well as Civil & Electrical Sub-contractors to solve practical difficulties / problems at Site
* Frequent Site visits to monitor / control site activities

Brief Particulars of Previous Employment

1. Organisation: Belleli Energy S.r.l, Dubai (an ITALIAN Company)
Period: From August 2002 to September 2003
Position: Planner / Project Co-ordinator

Brief Job Profile

Worked for an EPC Project for Vopak ENOC (Phase-4 Expansion) at site (Vopak Oil Terminal) in Fujairah (one of the Emirates in UAE) in the Construction of Nine Petroleum Storage Tanks (55mtr Dia. - 2Nos., 45mtr Dia. - 2Nos., 39mtr Dia. - 2Nos., & 29mtr Dia. - 3Nos.).

The nature of Job is as follows:

* Preparation of Preliminary & Detailed Project Schedule (at micro level) with Project Outline
* Updation & Preparation of Contract Progress % on a Weekly basis
* Preparation of Planned & Actual progress curve (S-Curve) indicating the Progress % on a Weekly & Monthly basis
* Preparation of Weekly & Monthly Progress Reports
* Preparation of Drawing Transmittal Status Reports
* Preparation of Material Status Report
* Liase with all Personnel viz. Construction Manager, Site Superintendent, Technical Design/ Engineering, Quality Control / Inspection etc.
* Preparation of Two Week Look Ahead Schedules
* Preparation of Manpower Histograms
* Preparation of Database of Spools with regard to Piping works including status of fabrication in the Workshop
* Collection of Progress Photographs at Site on a Weekly basis
* Preparation of Invoices which is to be raised to Client
* Coordinate with Client as well as Suppliers / Vendors
* Conduct periodic project status review meetings/discussions with Client as well as Civil & Electrical Sub-contractors to solve practical difficulties / problems at Site
* Frequent Site visits to monitor / control site activities

2. Organisation: M.N.DASTUR & COMPANY (P) LIMITED, Chennai, INDIA
(Steel & Power Plant Consultants)
Period: From May 1998 to July 2003
Position: Senior Engineer (Mechanical)

Brief Job Profile

Role: Project Planner / Project Coordinator
Projects Associated with:

A. Captive Power Projects Capacity
* National Aluminium Company Limited - 120 MW
* Nova Petrochemicals Limited - 7 MW

B. Biomass based Power Projects Capacity
* Jocil Limited (India) - 6 MW
* Varam Power Projects Limited (India) - 6 MW
* Jocil Limited (India) - 6 MW
* Vandana Vidhyut Limited (India) - 6 MW
* Roshni Powertech Limited (India) - 6 MW
* KMS Power Private Limited(India) - 6 MW

C. Integrated Steel Plants Capacity
* Bellary Steels & Alloys Limited - 0.5 Million Ton

Brief Job Profile

The nature of Job in the project is as follows:

* Preparation of Preliminary & Overall Project Plan with Project Outline
* Preparation of Feasibility Report of the project. The various options of technology / process that could be adopted, would be analysed and reported clearly stating the viability of each.
* Preparation of Detailed Project Report.
* Coordinating in the preparation of overall plant layout.
* Providing all the input requirements to all the departments for the preparation of technical specifications
* Monitoring and Controlling the progress of the project as per the project plan prepared and any slippage foreseen in schedule would be immediately reported. This requires close coordination with all the internal departments, periodic project status review meetings, resolution of issues, coordinating with client etc.
* Holding technical / commercial discussions with vendors and preparation of appraisals
* Assisting the client in the order placement by participating in the final commercial discussions
* Holding kick-off meetings with vendors
* Coordinating with departments for the approval of Vendors¡¦ drawings
* Maintaining the updated overall project status at any point of time
* Preparation of quality documents required for project management
* Periodic Site visits of various clients to monitor / control the progress of site activities

Apart from the above, also involved in the following general activities that are not project specific

* Preparation of techno-commercial proposals for the engineering consultancy for various probable clients
* Meeting and discussing with vendors who would like to be included in the approved list of vendors of the company. Their facilities would be visited and assessed prior to approval.

Internal Auditor of Department, Responsible for the Implementation of ISO Quality systems and procedures

Additional Information

Was sent under deputation to M/S RAP ENGINEERS & CONSULTANTS PTE LIMITED, SINGAPORE for a period of one month to assist in Project Management.

3. Organisation: Kraft Engineering & Projects Ltd, Chennai, India
Period: From September 1994 to May 1998
Position: Design Engineer

Projects Associated with:

Bulk Material Handling Systems pertaining to Power Plants Capacity
* EID Parry, Nellikuppam (India) - 70 TPH
* TamilNadu Newsprints & Papers Limited - 40 TPH
* Indian Rayon and Industries Ltd. - 100 TPH
* Southern Iron & Steel Co. Ltd. - 100 TPH
* Hindalco Industries - 200 TPH

Brief Job Profile

The nature of Job in the project is as follows:

* Preparation of Preliminary & Overall Project Plan with Project Outline
* Preparation of Feasibility Report of the project. The various options of technology / process that could be adopted, would be analysed and reported clearly stating the viability of each.
* Preparation of Detailed Project Report.
* Coordinating in the preparation of overall plant layout.
* Providing all the input requirements to all the departments for the preparation of technical specifications
* Monitoring and Controlling the progress of the project as per the project plan prepared and any slippage foreseen in schedule would be immediately reported. This requires close coordination with all the internal departments, periodic project status review meetings, resolution of issues, coordinating with client etc.
* Holding technical / commercial discussions with sub-vendors and preparation of appraisals
* Coordinating with departments
* Maintaining the updated overall project status at any point of time
* Periodic Site visits of various clients to monitor / control the progress of site activities

4.Organisation: Aluminium Industries Ltd., Hyderabad, India
(Bulk Material Handling Division)
Position Held: Design Engineer
Duration: From July 1993 to August 1994
Job Responsibilities: As in Sl. No. 3 above

5.Organisation: Navabharat Ferro Alloys Ltd, Hyderabad, India
(Fabrication of Pressure Vessels & Auxiliaries)
Position Held: Shift Engineer In-Charge
Duration: From May 1991 to March 1993
Job Responsibilities: Reporting to Works Manager, updating log book on a daily basis,In-Charge of Fabrication Shop &
Machine Shop. Responsible for showing Productivity on a weekly basis

Personal Particulars

Date of Birth, Age: 15.02.1969,35 years
Marital Status: Married
Nationality: Indian

View contact information...
«« previous resume next resume »»
Search Results (Resumes 5751 to 5800 of 10917)Go to Search Parameters...
Brief Description
Well Testing Mobile unit Supervisor
Duties included design and drafting; instrument drawings and documentation such as instrument plans, installation details, creating databases and maintaining an instrument index, and numerous on-site surveys and field work for modification project.
Instrumentation Engg done the project in Hikal (Agro-Chemical company)
I am a young innovative technichian seeking a full-time position with your company.
Project Management / Construction Management / EPC / EPCM / PMC
Entry Level Petrol. Engineer
loaded chemical into varies transports for georgia gulf.
Fresh graduate of Petroleum , i did work with BP Pakistan as internee and also have command on Prosper software please give me a single chance so in this way i can show my skills and talent .
Construction Administration/Project Controls
I am looking job in instrumentation field as instrument SUPERVISOR/INSPECTOR/SR.TECH
Paramedic/Offshore medic with 19 years experience in Oil, Gas & Renewable Energy industries
seismic interpreter with a strong background in petroleum and structural geology, gained through working on a wide range of fields in different structural settings in the Syrian Euphrates Graben area. A skilled user of the Geoframe and OpenWorks software suite. Completed seismic interpretation
I am a Mechanical Engineer having Post graduation diploma in power plant ,working since Nov'02 in the field of power plant execution
5+ years production and design experience in refinery, PDS, PROCAD, Microstation, AUTOCAD,LDT
Process Engineer
My skills include the performing maintenance work and repairs on transmitters: SW, FM and AM. Maintenance work on Exchange Equipment: CDMA, trunk, lines. CCNA IN VIEW.
Ability to work as a team with little or no supervision. I read polymer and textile Engineering.
Abity to work with little supervision,counseling ,Bsc Industrial chemistry
Excellent communication skills -english:oral and written.Leadership skills :As a leader of the project team assisted the team in solving the problems that arose.Computer Proficiency:Ms Word,Excel,Powerpoint.Software:Intouch(SCADA).PrimaveraP3
Government Girls Comprehensive Secondary School 2008 – 2009
Mechanical Engineer with Piping Engineering Knowledge
I have a Bachelor of Science in Computer Science and in March '09; i will be getting my Microsoft Certified Professional and Microsoft Certified Technical Specialist - SharePoint papers. I have a managed a number of large software projects in Zambia, mostly in the capacity of project manager.
I am working in chicago Bridge & Iron (CBI) an EPC company, in Saudi Arabia as a Field Engineer.I have the ability to work both in field and office, also, ready for extensive travel.I am team player with good communication skills.
BA in Geoscience; 1 year experience cased hole wireline; intern for geology consultant in DJ Basin
Safety Specialist with OSHA 500 & 511 certifacations
With knowledge in SMAW 6G,TIG,GTAW,OAW. and Brazing welding. Plasma and Oxy Acetylene cutting, Lathe Machine operation, Pipe fitting Jobs and fabrication. Operate the forklift ,crane and wenches
Senior CMMS Engineer and Business Process Engineer with expertise in Oil & Gas plant Enterprise Asset Management with extensive experience in Maintenance, Material Management and Procurement; plant data collection and quality check.
EMPLOYMENT WITH Eni ,Bhit Gas Field Pakistan (Italian Oil & Gas Company)
Project leader and technical manager for heavy crude
I have 34 yrs Crane Operator experence, 4 yrs Crane, Rigging, & Mechanical Trainer experence. I have offshore crane operator exp. and onshore crane operator exp.
Senior Estimator Available to work in Indonesia, Malaysia, Nigeria, Kazakhastan, Thailand
More than 13 years of working experience with Major Oil & Gas Industries for their Documentation with responsibilities in Technical Documentation, Library system, Supervision, Administrative, Vendor, Procurement & Project Management etc.
Total 16 Years of diverse experience in Piping/Mechanical design of Refineries, Chemicals, Petrochemicals, Fertilisers Plants. 5 years experience in Operating Refinery of KNPC. 9 years of cosultancy (EPC) experience. 2 years of Piping design & construction experience.
Seven years of experience in oil and gas upstream industry as geophysicist. Currently involved in exploration & development of a deep-water lease in East Coast of India with multiple play/prospect (gas) discovery identified by 15 successful exploratory wells.
Over ten years of experience in the field of Electronics and Computer Engineering
Instrument design engineer in BHEL (Bharat Heavy Electricals Ltd), Hyderabad, India in Control & Instrumentation (C&I) department in Steam Turbine, Compressor & Gas turbine Engineering division. DNV certified HSE lead auditor
Since 1995, I have worked as a Planning Engineer / Maintenance Planner in Oil & Gas Industrial, both on offshore and onshore terminal, worked for ARCO, BP and CNOOC companies. Response for Opertioans and Maintenance work activities, good at CMMS-MAXIMO, MS Project, P3 Project Planner.
Completions/Production Engineering Experience
working in Malaysia ( far east) from 3 and 1/2 yrs. Looking for jobs in oil & gas fields . In field operators or panel operators position with better salary as a long term contract basis preferable in far east or middle east.
I am a degree holder in Mechanical Engineering, having more than 13 years of experience in various types of Refinery and Petrochemical project.
Cost Engineer with exposure to Planning. Russian-mother tongue. English - fluent. Arabic - working knowledge
13 Years Strong Experience & Exposure in The Arena Of I&C Systems Successfully handled numerous large scale projects Worked with SCADA, PLCs and DCS Strong at commissioning, testing, documentation and handling of O&M Effectively led teams to deliver positive and timely results
13 yrs Professional Exp.which include Project Management, Engineering and Estimation. Responsible for the Implementation of QMS(ISO9001-2000). Countries of Work Exp: India,Singapore,UAE Languages Known:English,Hindi,Kannada,Tamil & Telugu.
I try to get better conditions and get better live with my skills and competency
My Nine years and Six months of experience , I have exposure in Power & Utilities. I have hands on experience for Gas Turbines, Steam Turbines, D. M. Water Plant, Plant & Instrument Air Package comprises of Dryer and Compressors, Raw Water Treatment Plant, Cooling Tower, and OSBLs.
MATERIALS ENGINEER/CONTROLLER/SPECIALIST-CATALOGUING-INVENTORY-PREPARE PURCHASE DESCRIPTION-ERP-SAP MM-CMT-STRING-E-SPIR-MMS Etc.
I am a CWI, Level II in MT, UT, PT and RT film interpretation. I have US and overseas QA/QC project and manufacturing supervisory experience in the construction, petroleum, mining and aerospace industries. References and copies of certs. will be provided upon request.
Professional trainings and practices in Geological and Mining Institutes including well site practices, modeling of gas reservoirs and underground gas storage production, geological prospecting and drilling geophysics, control properties of mud-logging and cementation
-
Team Leader Shift Supervisor, Trainer: Operation at Refinery Processing Plants, Remote Oil & Gas Production Field and High Pressure Systems at NGL Processing Facilities LPG Plant including Petroleum & Petrochemical Utilities. Professional member MInstLM & MCMI UK, MBA Prod. Ops. Management, BSc, BA
First   Prev   101   102   103   104   105   106   107   108   109   110   111   112   113   114   115   [ 116 ]   117   118   119   120   121   122   123   124   125   126   127   128   129   130   131   132   133   134   135   136   137   138   139   140   141   142   143   144   145   146   147   148   149   150   Next   Last
Seach Parameters

Change search parameters...
INDUSTRIES: Petroleum/Oil/Gas;
Change search parameters...
Keywords: (e.g. mining engineer)Find results with:
Save this search parameters...
Post job with this search parameters...
Frequently Asked Questions
What's the most effective way to perform a search?
Go to Advanced Search
1. Select 'Industries', 'Categories', 'Education', and 'Experience' fields. Click 'Search' and look through results.
2. Enter one or two of the most important keywords. Click 'Search' and look through results.
3. To search within results add more keywords.

How can I find resumes that contain specific exact phrase?
To search for an exact phrase, just put quotation marks around two or more words, for example "mining engineer". Use this feature to narrow your results or to find words that can be typed differently, for example AutoCAD "Auto CAD".

More Frequenly Asked Questions...
Employer's Center


» Employers Home
» Feedback
» Help

» Post Jobs
» Edit/Delete Jobs
» Search Resumes
» Resumes By Email

» My Account
» Log In

» Log Out
 
©1999-2009 Misco Jobs. All rights reserved.  Contact: support@miscojobs.com