Misco Jobs  |  Go to Job Seeker's Center »»   |  
 
«« previous resume Resume #54175 next resume »»
CONTACT INFORMATION:
View contact information...

SUMMARY OF QUALIFICATIONS:
A. PERSONAL DETAIL

Name: Yani Handra
Place / Date of Birth: Duri, 4 February 1966
Sex: Male
Marital Status: Married (2 Children)
Healthy: Excellent

B. EDUCATION BACKGROUND

1. Primary School: SDN 2 Caltex Duri – Riau 1979
2. Secondary School: SMPN 1 Caltex Duri – Riau 1982
3. Senior High School: SMAN 1 Caltex Duri – Riau 1985
4. Engineer Certificate: University in Bandung – west Java
(Graduated Of Technical Division) 1993
Electrical Degree.

C. SKILLS

1. Knowledge about Electrical Principles.
2. Operating Personal Computer.
3. Speak and Write English.

D. WORK EXPERIENCES

Engineering Abilities: To manage the electrical installation project Electrical Industry; Refinary, Mining and Combine Cycle work on site, Field Design Electrical System pre-commissioning installation. Supervise Installation of High voltage equipment for Switchyard, Transmission line and, Substation. Medium and low voltage Switch gear, Circuit Breakers and MCC with controls and relays system.
QA/QC Abilities: QA/QC Documentation, Electrical Specification and Installation to commissioning Procedures. Inspection and testing all electrical equipment in accordance to assist in updating Operations Function codes, standards and procedure are ANSI (American National Standard Institute), NEC (National Electrical Code), NEMA (National Electrical Manufactures Association).
AMBITIOUS:
An ambitious and experienced electrical engineer with significant industry knowledge gained via management team, coordination with supervision of various projects Off-Shore, On-Shore and Construction. Pursue a career that that will provide a rule of:
- E & I Inspection
- Construction Manager
- QA/ QC manager

PROFESIONAL EXPERIENCES (1992 – 2007)
I have 15 (Fifteen) years of Experience as Electrical System, Maintenance Service and Construction – Plant for Petrochemical, Nickel/ gold Mining, Oil and Gas, On-Shore & Off- Shore.
D.14 British Petroleum Tangguh GPF Project
Designation: QA/QC E&I Construction Engineer
Job Location: Guna Nusa Fabricator Cilegon
Project name: BP Tangguh GPF Project (Construct & Installation Two Platforms)
Present: 2006 – 2007…

D.13 Tripatra/Fluor Chevron – Duri.
Designation: SLN Construction Superintendent
Job Location: Chevron Duri (Oil & Gas)
Project name: Flexible Project Management
Present: October. 2006 – Dec'26. 2006
D.12 Combine Cycle Gas Turbine Suban Pahse 2 Gas Plan Project
Designated: Pre-Commissioning & Commissioning And Facility Acceptance Coordinator.
Reason for leaving: Completion of Contract (4 Feb'2004 – Sept' 2006 ).

P.T Thiess Contractors Indonesia/ Conoco Phillips.
Expansion to an existing gas production facility.
DUTIES AND RESPONSIBILITY
Consist of review of quotations from the vendor and conduct T.B.E technical Bid Evaluations. Witness F.A.T and at the conclusion of site installation conduct S.A.T.
Source calibration equipment for site process instrumentation and personnel.
My team consists of one site Instrument Engineer and one site Electrical engineer along with a crew of 70 personnel to carry out site installation and site acceptance tests by means of a Quality Controlled hand over system to the client.
I then had the over all responsibility of supervising other Engineers in the Mechanical and Piping fields to full fill engineering interface between the client and the J.V partner Hyundai Engineering. Cleared all punch lists.
D. 11 Construction Service CHEVRON Project 2004
Thiess Contractors Indonesia

Designated: Estimator Engineer and Monitoring E/I Construction Activities
Job Location: Caltex Construction Service Duri Project, Oil and Gas
Present: February. 2004 – March. 2006

DUTIES AND RESPONSIBILITY
Handling some of electrical & instrumentation, civil work and mechanical work order incoming from Client ( Chevron Pacific Indonesia) to estimate / Calculate and negotiate. To conduct Kick of meeting Work Order Approved between Client and THIESS Contractor C/W Construction Teams. Witness F.A.T and at the conclusion of site installation conduct S.A.T. Organize and supervise Electrical & Instrument construction activities, quality, testing, documentation, Pre-commissioning, commissioning and start-up.
D. 10 Aberdeen Off-shore oil and Gas Industry in Europe (France) Shell
Power Generator System Installation' 2003
Designated: Operating Engineer - Electrical Inspector Eng. (QA/QC)
Job Location: North East of Aberdeen (Shell Oil Company – Aggreko).
Reason for leaving: completion of project (July 24' 02 – Jun' 03 ).

DUTIES AND RESPONSIBILITY
Full Inspected and monitoring Portable Power Plant Installation, Diesel Power Generator Systems (300 KW / 200 MW) Multi Voltage /50Hz/ 60Hz and Load Banks Precision testing for Both Resistive/ Reactive Loads (2.5 Mw – 100 Mw).
Perform routine inspection and document result in accordance with approved Project Owner procedures. Etc
D.09 PT. Caltex Pacific Indonesia Steam Flood project
Designated: QA/QC – Electrical Inspector/ Engineering
(Pre-commissioning and Commissioning) Owner Representative
Job Location: Central Gathering Station – 10. Duri Project.
Oil & Gas Facilities – Sumatra.
Reason for leaving: Completion of project. (September. 04' 00 – September. 2001

Combine Cycle & Gathering System Project: Coordinated construction activities 3 x 100 MW Siemens Westinghouse combustion turbines 501D.
Controlled daily activities of the sub-contractor PT. Siemens Indonesia on schedule requirement and engineering interface. Respond to (RFI) request for information and worked with engineering in Head Office.
In addition to my task of completing electrical system for hand over, I controlled the following: E & I, millwright, Building's, and Painting. Compiled all check sheets, involved with pre commissioning, commissioning and start up achieved contractual acceptance of plant hand over by the client.

DUTIES AND RESPONSIBILITY
1. QA/QC documentation and review Contractor construction electrical procedures.
2. Supervise and Monitor Installation of Cable, Cable tray, Lighting, Distribution control panel, all electrical equipment and Grounding system, etc.
3. Perform routine inspection and document result in accordance with approved CPI procedures.
4. Monitor activities of supervision contractor and construction Contractors.
5. Witness and verify Continuity, Merger, HI-POT and Component testing for Medium Voltage & Low Voltage equipment.
6. Monitor Quality control on construction progress activities.
7. Responsible from equipment installation and continue energizing of electrical equipment to pre-commissioning and commissioning.
8. Issued punch listing for out standing works.
9. Review Tested documentation, witness and accept all required Testing for CPI (Client).
10. Etc
D.8 Middle East UAE. Oil Refinery & Power Generation Plant
Designated: Electrical Maintenance Eng.
Job Location: Al – Mubaraz island – Abu Dhabi Oil & Gas Company (A D O C)
Abu Dhabi – GULF (UAE).
Reason for Leaving: Completion of Contract. (Augustus'04' 99 – April. 04' 00).
DUTIES AND RESPONSIBILITY
Maintenance and operational of plant facilities. Turbine generator power supply to Transformer, and than going to switch gear, from switch gear going to ALL WELL HEADS Platform / Central Platform, MCC, Distribution Panel, Motor Electric Over Hauls, Lighting and lighting Panels Distribution, all Electrical Equipment and Modification.
D.7 Newmont Gold Mining (COMBINE CYCLE) Project
Designated: Field Engineer Electrical and Quality Control Engineer
Job Location: PT. Flour Daniel – Sumbawa Batu Hijau Project (Power Plan &
Gold Mining) New-Mont Nusa Tenggara.
Reason for Leaving: Completion of Project. (October 1998 – July'30. 99)

Power Facility Portion of Batu of Batu Hijau Four (4) 28 MW Coal Unit and Nine (9) Diesel Generator Units, and a 150 KV Transmission Line. Project Cost US $ 1.8 Billion.
Combine Cycle Project ( Coal Power House & Diesel Generator)
DUKE FLOUR DANIEL INDONESIA
Coordinated all construction activities on a diesel powered power plant. (Associated Switch Yard 11 KV-150 KV).
Phase two of the contract, coal-fired power plant with four turbines. Responsible for electrical trades
With Electrical speciallist Commissioning bringing total to a round 25 personnel.
Controlled all QA/QC documentation. Involved with commissioning team for client hand over, and acceptance.
DUTIES AND RESPONSIBILTY
1. Manage the electrical Contractors daily construction activities, schedule and progress.
2. QA/QC documentation and specification and verify, contractor procedures.
3. Generate Field Change Request (FCR), Field Purchase Request (FPR) and Request for Information (RFI). Inspect and approve Electrical Installation on site.
4. Witness and verify Continuity, Merger, HI-POT and component testing for Medium voltage & Low voltage equipment.
5. Inspection of Connection and Installation switch gear and MCC panel.
6. Expedite materials for construction and issue field instruction to contractor.
7. Supervise and Inspect Subcontractor (SIEMENS) construction activities.
8. Witness Pre commissioning and commissioning testing.
9. Review all test packages; prepare QA/QC documentation for Turn over to client.

D.6 INCO Nickel Mining Project Daniel
Designated: QA/QC - E/I Engineer.
Job Location: PT. SNEF/ Fluor Daniel – Soroako, PT. Inco Expansion Project
(Soroako South Sulawesi) (Feb 1998 – Oct 1998).
Reason for Leaving: Completion of Project 1998 – Certificate.

DUTIES AND RESPONSIBILITY
1. Responsible for project operational safety requirement
2. QA/QC documentation and review contractor installation procedures.
3. Implement & enforce all company policies, procedures and practices.
4. Planing construction electrical and Instrumentation schedule.
5. Monitor construction activities and progress.
6. Witness and monitor electrical and Instrumentation equipment testing.
7. Responsible for test packages documentation from pre-commissioning to final hand over to client.
D. 5 UNOCAL' 76 Combine Cycle Project Unit # 4. 5. 6
Designated: Electrical Engineer for Start-up to Commissioning/ Owner Represent.
Job location: Unocal Salak Geothermal Project Unit # 4,5,6 (West Java)
Reason for Leaving: Completion of project (1998) / Certificate.

DUTIES AND RESPONSIBILITY
1. Perform evaluation and recommendation for power generation project electrical operation system start-up to commissioning acceptance.
2. Assigned as Commissioning Electrical Engineer. Trouble shooting, maintenance for power plant and distribution during shut-down Unit # 4,5,6 and MCC panel and local panel for lighting Power Generation Facility Area and-Resource Production Facility Area.
3. Responsibility too for cleaning ISO-phase Bus Duck and prepared, termination element Space heater and confirmation main transformer. Install and link grounding clutiss on generator out put for Turbine Generator Unit # 4, 5, 6.
4. Inspected and Cleaned Unit # 400, 500, 600 Lube oil Clarifier Heaters.
5. Verify Drawing & specification of Electrical Equipment.
6. QA/QC Electrical Documentation.
7. Verify Punch listing for all Electrical works prior to final acceptance.
8. Planed schedule for electrical start-up, cables modification, installation and other construction activities.
D.4 AMOCO Petrochemical Project
Designated: QA/QC. Electrical Engineer
Job Location: Merak – PTA 1 AMOCO Petrochemical Plant Project
Cilegon – West – Java / PT. IKPT – CHIYODA – J/O
Reason for Leaving: Project Completion (1997) – Certificate.
DUTIES AND RESPONSIBILITY
1. Supervise and Monitor Installation of Cable, cable tray, Lighting, Distribution control panel, electrical equipment and Grounding system, etc
2. Prepare and Verify construction Drawing, Specification and installation procedures of Electrical Equipment.
3. Supervise & Inspection of electrical equipment Installation, testing to - commissioning.
4. Witness cable termination for Medium and Low voltage Power to Switch Gear, MCC, MV/LV electrical Motor.
5. Responsible to QA/QC and Construction Managers.

D.3 Unocal'76 Geothermal power Generator Project Unit # 4, 5, 6.
Designated: Field Engineer / Engineering Dept.
Job Location: Salak Geothermal Project (West Java)
Fluor Daniel JO IKPT.
Reason for Leaving: Contract Completion (1996 – 1997) – Certificate.
Combine Cycle Geothermal Power Generation
Directed construction activities on caterpillar generators series 3512.
Controlled all QA/CC documentation pre commissioning, commissioning and start up.
I controlled a very small and dedicated local craft force to achieve start up in a very isolated and troubled province.
We achieved start up on schedule and I trained local staff to switch over to maintenance duties.
DUTIES AND RESPONSIBILITY
1. Verify all Drawings and Specification of Electrical and Instrument.
2. Support the project program for verifying construction quality.
3. Supervision and Inspection to Subcontractor in construction Activity Installation and Hook-Up some Instrument Equipment and Planning Installation Electrical Motor Connection, Power Supply and Compressor.
4. Handling RFI from Subcontractor and Connected all Paper Work
5. Reporting to Engineering Manager.

D.2 Mivan Apartment Project.
Designated: QA/QC – Electrical Engineer.
Job location: Dukuh Golf Apartment Project, Kemayoran,
Jakarta Utara
Leaving for Job: Completion Project (1995 – 1996) - Certificate.

DUTIES AND RESPONBILITY
1. Verify Drawing, Specification and Equipment.
2. Inspection of connection pooller and control cables.
3. Supervisor of Installation cable Tray, Lighting and Light distribution panels.
4. Direct Medium Voltage & Low Voltage Equipment testing (continuity, Megger test and HI-pot test. (Feeder, pncc & swgr panels).
5. Prepare document & record or documentation for turn over package)

D.1 Unocal Power Generation Project Unit # 123.
Designated: Unocal Electrical and Instrument Supervision.
Job Location: Gunung Salak Geothermal Plant Project Unit – 1,2,3, (West –
Java) UNOCAL' 76.
Reason for Leaving: Complete Project (1993) – Certificate.

DUTIES AND RESPOSIBILITY
1. Supervise to Subcontractor in Construction Activity Installation in Hook up all Instruments on general Electric (Gas Turbine) Ingersoll (Condensate Pump) and Installation such (Installation Cable Tray). CCS (Compressor Anti Surge Control), PLC.
2. Control all Drawing & Specification of electrical and Instrument.
3. Supervises of Connection all Electrical Motor, Blacke Dur (welding Procedure Specification) Bailey Controls (West Pump Station) Pneumatic Products (Installation Operation & Maintenance).
4. Inspection & Check for Pre Commissioning & Commissioning.
5. Report to Construction Manager

THIS CERTIFY, IS TRULY AND CORRECT.

YANI HANDRA
Electrical Engineer

Please enter brief description of your skills and qualifications.
Eletrical & Instrument Inspector

1. Knowledge about Electrical Principles.
2. Operating Personal Computer.
3. Speak and Write English.

Please describe in your own words, what you are expecting from the job and/or the company.
AMBITIOUS:
An ambitious and experienced electrical engineer with significant industry knowledge gained via management team, coordination with supervision of various projects Off-Shore, On-Shore and Construction. Pursue a career that that will provide a rule of:
- E & I Inspection
- Construction Manager
- QA/ QC manager

WORK EXPERIENCE:

D. WORK EXPERIENCES

Engineering Abilities: To manage the electrical installation project Electrical Industry; Refinary, Mining and Combine Cycle work on site, Field Design Electrical System pre-commissioning installation. Supervise Installation of High voltage equipment for Switchyard, Transmission line and, Substation. Medium and low voltage Switch gear, Circuit Breakers and MCC with controls and relays system.
QA/QC Abilities: QA/QC Documentation, Electrical Specification and Installation to commissioning Procedures. Inspection and testing all electrical equipment in accordance to assist in updating Operations Function codes, standards and procedure are ANSI (American National Standard Institute), NEC (National Electrical Code), NEMA (National Electrical Manufactures Association).

Please detail your work history including past employers, employment dates, position held, responsibilities, and major achievements.

Present,
British Petroleum Tangguh GPF Project
Designation: QA/QC E&I Construction Engineer
Job Location: Guna Nusa Fabricator Cilegon
Project name: BP Tangguh GPF Project (Construct & Installation Two Platforms)
Present: 2006 – 2007…

EDUCATION & CERTIFICATION:
Electrical Degree

List any formal education including schools, degrees attained, and performance. Also include professional affiliations or associations, certifications you have earned, special licenses, etc.
B. EDUCATION BACKGROUND

1. Primary School: SDN 2 Caltex Duri – Riau 1979
2. Secondary School: SMPN 1 Caltex Duri – Riau 1982
3. Senior High School: SMAN 1 Caltex Duri – Riau 1985
4. Engineer Certificate: University in Bandung – west Java
(Graduated Of Technical Division) 1993
Electrical Degree.

ADDITIONAL INFORMATION:
I am Indonesian
Provide any additional information including your personality, hobbies, references, citizenship, etc.
SPORT

View contact information...
«« previous resume next resume »»
Search Results (Resumes 1851 to 1900 of 9871)Go to Search Parameters...
Brief Description
Industrial Control & Automation Systems PLC programmer (Siemens, Schneider Electric) Repair and maintenance - electrical devices
Process Control design, analysis, and tuning, ESD logic design and analysis, Systems experience: Honeywell DCS, Triconex, Wonderware MMI, PI, and Mitsubishi Diasys Netamtion
Experienced Rig Safety Officer capable of performing Audits to verify compliance to company’s Policies and Procedures. Conduct SMS audits on Rigs to. Conducted Training sessions to rig personnel in Safety and Emergency Procedures. Cooperate with all disciplines to improve effectivness of the SMS.
DCS OPERATOR
After completing my Diploma in Mechanical engineering from India I joined Shipping as Engine Cadet on a Product Tanker. After completing one year cadet ship I went to UK in March 2000 for National Vocational Qualification course In Marine Engineering and down all advance survival courses from there.
Maintenance Engineer (rolling mills)
INSTRUMENT ENGINEER / SUPERVISOR
Free! M.Tech with 7 years of work experience in managing functional aspects of Static Equipments Design & Engineering. Expertise in planning, executing and spearheading projects involving Design Engineering and Resource Planning with a flair for adopting modern construction methodologies in compliance to
Mechanical supervisor / Technician with experience in permit coordination
Petroleum Engineer with expertise in pipeline inspection, MFL technology, corrosion diagnostics, pipeline integrity management and assessments, large-scale petroleum relational database design and interpretation, financial analysis, budget analysis, and project management.
Process / Systems / Operations
Drilling Superintendent - Senior Drilling Supervisor, International Positions Only
Electrical / Instrument Inspector
Objective: To share knowledge on Best Practices on Health, Safety and Environment (HSE) in the development and implementation of HSE Management System and promote a culture of Continuous Improvement.
I am a senior instruments engineer. I have 15 years experience in the design and specification of instrumentation for petrochemical plants. I was involved in developing P&IDs, specifications, data sheets, logic narratives, instrument indexes, systems diagrams and alarm summaries.
Bioinformatician and clinician
To obtain a challenging engineering position in an internationally active oil/service company. Education The University of Texas at Austin May 1993 Master of Science in Petroleum Engineering. Overall GPA 3.83/4.00
I have extensive experience in Production Operations in the oil and gas industry.
Experience in Exploration and Development Geology, having involved in exploration of new areas and Enhancing of Oil Recovery in the fields of Northern Potwar Deform Zone and Middle Indus Basin of Pakistan. Day to day duties include studying the current reservoir properties via interpretation of geop
Stage 3 crane operator 25 years experience oil / gas / subsea / construction
Experienced Engineer working as Test Engineer for latest released versions of DeltaV software applications. Flexible knowledge in hardware technologies like Fiedlbus and SIS.
Engineer- electrician. Electrical installation testingand setup electrician.
Oil and gas Utilities Senior Operator, start up, power plant shift enginner
diesel mechanic&fitter turner machinist with technical management skills. 28yrs exp. expat . job locatio no problem. brief off shore exp.
Hands of experience with good knowledge of engineering (standards) & trouble shootings working with one of the major such as SABIC projects (Yanbu national petrochemical company) with Technip JV Irem sPa, and other than working with Steel plant in one of the major company JINDAL group.
My name is Garry Jennings and I would like to introduce myself as a possible candidate for the fulltime Operations Technicians positions.
Sales, marketing & Applications Eng. for all ESP applications
I am an experienced Fire Protection personnel. My experience not only in hands-on fire protection activities but also in fire risk assessment, fire protection training and supervising of down line personnel, fire protection system auditing, safety at work issues auditing.
Metallurgical & Welding Engineer with experience in failure analysis, materials characterization, welding Technology, Microstructure-Property correlation, Research and Development, QA/QC, NDT, WPS, PQR Certification Project Quality Management System, Internal Quality Audit. Expert in engineering eva
I am experient with AutoCAD by new released and CAD worx to made 3D model of piping
Drilling Engineer
Calculated volumes, Maintained well, equipment and compressors, participated in well reviews, intered volumes in computer.
TECHNICAL QUALIFICATIONS:
Have worked and travelled all over the Pacific region, NZ and Australia. I have interacted and worked with a wide diversity of cultures. I am a very hard worker, I learn new skills quickly and am able to implement them accordingly. I wish to continue utilizing my skills as a Diesel Fitter,
Master Degree Of Science Major In (( Synthesis of cascaded refrigeration systems)), *PUBLICATION:F. Rabea, S. aly and M. awad," Fuzzy approach for cascade Refrigeration Synthesis ", HYDROCARBON PROCESSING March 2008.VOL.87 NO.3,** HYSYS PROCESS SIMULATOR , Word – Excel – Power pointInternet,windows*
My backgroung is in Mechanical Engineering but I have been working in Utilities Plant Operation since past 11++ years. My expertise in Steam Boiler and Steam System, Water Technology, and others related to utility plant.
Oil wells,oil process,gas dehydration,control room DCS,storage & dispatching etc
Rotating Equipment Engineer
Principal Process Engineer (B Eng - Chem), (M Eng - currently enrolled), 12 years design experience worked in RSA, USA, UK
I have graduated from the University of Khartoum and got my M.Sc. there among my carrers since then is working as a mud logger and a wellsite geological supervisor
Senior mechanical draftsman
Seeking middle level managerial assignments in the domain of Procurement / Materials Management to excel with organization of repute.
i am chemical engineer and have 11 years experience
Qualification:DIPLOMA IN MECHANICAL ENGINEERING;Iam having 18 years experience (10 years in Gulf + 8 years in India) in the field of Oil & Gas, Refinery, crude oil gathering station, Gas recovery flash gas compressor, Heavy industry, Gas utilization.
Landmark Drilling Consultant seeking international position with 28 and 28 rotation.
Over 14 years of experience covering industries of Engineering, Oil & Gas , Chemical industry, Offshore and Space Industry in the fields of Quality Surveillance, Project site Inspection & Management, Product certification (ATEX, MD, PED, RoHs, WEEE), Type approvals, WPS/PQR & WPQR approvals, Coatin
16 yrs. plus Instrument & Control Maintenance & Engineering experience in Gas & Petrochemical Industries, Copper Smelter & Refinery, Aviation Air Defence & Telecommunication systems.
IT with expertise in systems business analysis, database management, ERP implementation & support
Business and Customer focused team player, qualified engineer and lead auditor specializing in Quality solutions for project and corporate applications
Planning Engineer
First   1   2   3   4   5   6   7   8   9   10   11   12   13   14   15   16   17   18   19   20   21   22   23   24   25   26   27   28   29   30   31   32   33   34   35   36   37   [ 38 ]   39   40   41   42   43   44   45   46   47   48   49   50   Next   Last
Seach Parameters

Change search parameters...
INDUSTRIES: Petroleum/Oil/Gas;
Change search parameters...
Keywords: (e.g. mining engineer)Find results with:
Save this search parameters...
Post job with this search parameters...
Frequently Asked Questions
What's the most effective way to perform a search?
Go to Advanced Search
1. Select 'Industries', 'Categories', 'Education', and 'Experience' fields. Click 'Search' and look through results.
2. Enter one or two of the most important keywords. Click 'Search' and look through results.
3. To search within results add more keywords.

How can I find resumes that contain specific exact phrase?
To search for an exact phrase, just put quotation marks around two or more words, for example "mining engineer". Use this feature to narrow your results or to find words that can be typed differently, for example AutoCAD "Auto CAD".

More Frequenly Asked Questions...
Employer's Center


» Employers Home
» Feedback
» Help

» Post Jobs
» Edit/Delete Jobs
» Search Resumes
» Resumes By Email

» My Account
» Log In

» Log Out
 
©1999-2008 Misco Jobs. All rights reserved.  Contact: support@miscojobs.com