Senior Project Manager (Power) Kvaerner, (CA,USA)
Based in San Ramon, CA: project engineering and management of 500+ MW Gas Combined Cylce CTG project for the CA Region, Bakersfield and Redding (CA),.
Also responsible for Conceptual / Preliminary Engineering/ Estimating/Scheduling for other active EPC projects and proposals for new CCCTG /Coal projects.
Senior Project /Construction Manager (Houston, USA) MAN B&W AG
Covering Western Hemishere, focused on the sale of capital equipment for EPC diesel power projects from the enquiry stage thru contract and complete construction (Nicaragua 70 MW,Dominican Republic 70 MW ). Produced EPC project proposals and engineered and negotiated contracts with clients for projects in Dominican Republic, El Salvador Panama, Nicaragua, Mexico.
.
Project Manager (Latin/South America), Coastal Power Corp, based in Houston, focused on Latin /South American Market. Successful asset rehabilitation and consolidation of Itabo Group of generation assets in Dominican Republic. Spec/ Contract/Construct projects involving Coal fired and conversion of SCCTG to CCCTG new and existing
Bidding involvement on Greenfield Development, Capitalization and Acquisition projects in Peru, Salvador, Panama, Bolivia, Caribbean. Development of overall scope and schedule for O&M takeover, Rehabilitation to Coal firing and future Coal Expansion Project, and Combined Cycle at Itabo, in the Dominican Republic.
Joint Project & Construction Manager (Brazil), for the "Fast Track¡½ Barge mounted 90MW Aeroderivitive gas turbine (simple cycle), for El Paso Energy International, Houston under a short term PPA (5 yr.), with Electronorte, Manaus, Amazonas, Brazil. This project created a new construction record (5 mths) for the fast track placement and
Commissioning of power generation capacity. The bulk of the work force were Brazilian in Portuguese with a core group of qualified (US) discipline leaders and the Owner Representatives.
Project Development Manager (Honduras) from the Feasibility Study through to Financial Closure for three (3) x15MW (Net) Renewable (Biomass) Projects with
International Applied Engineering (IAE) and Nations Energy Inc. (NEI),
(Guaimaca, San Pedro Sula, La Cieba, Honduras) Financial Close: August
1998. Retained minority equity position in all Projects. Negotiated
PPA, EPC, and O&M Agreements, in conjunction with Honduran partner (all in Spanish).
Project /Construction Manager ( Argentina) for Dominion Energy ( Richmond, Va) in the Acquisition of Existing Power Plant Infrastructure in Argentina. Asset due diligence, consolidation technical/commercial studies and cost estimates. Led Project Team and Construction Management of the rehabilitation/relocation and upgrade to Combined Cycle of several CTGùþs from various sites to consolidate at gas wellhead plant site.
Developed specifications, evaluated bids and negotiated EPC contracts for all power generation asset rehabilitation and combined cycle (All in Spanish). Acted as Owners Engineer to supervise all construction ( based in Argentina)
Project Development/Engineering Manager (Oklahoma), for Smith Cogeneration Inc.,
Responsible for all project engineering and commercial analysis during development for:
* Successful Proposal to Bangladesh Power Development Board (BPDB) for fast track HaripurBarge mounted 100 MW capacity. EPC Contract with Raytheon. Acted as Owners Engineer throughout Project Implementation.
* Project Implementation of its 170 MW Combined Cycle Barge Mounted PowerProject, Mangalore, Karnataka, India. Contracted as Owners Engineer; EPC, O&M, FSA, EIA, at State Level. Acted as supervisor for PM an CM activities during implementation
Project /Construction Manager (U.S Virgin Islands), for Stowe Engineering Corp, Boston,
* Removal of old existing FT8 and installation of GE Frame 5/25 MW Simple Cycle CTG, for WAPDA, St. Croix, US Virgin Islands. Direct hire non union workforce with P/L responsibility. This project utilized a Construction Crew from Puerto Rico and was run completely in Spanish on site.
* Contract Manager for the upgrade project for GE Fr7 to Combined Cycle operation for WAPDA at St Thomas. Developed specifications, evaluated bids and negotiated contract for the HRSG and all auxilaries.
Project Development Engineer, (Canada), for Sithe Energies USA, In the Initial Economic and Technical evaluations of IPPs in Eastern Canada.
Supported Sithe in all Conceptual Engineering and Contract negotiations on several developments of IPPs in Eastern Canada. Assisted in PPA /EPC/O&M FS Agreements.
Development of Renewable based IPP
1984-1986: Babcock and Wilcox International, (Cambridge,Ontario)
Regional Sales Manger, Latin / South America
Set up and Managed the Network of agreements with all Regional Distributors and
Clients throughout Latin /South America for the complete range of products and services.
Expanded Industrial Regional Markets (Mexico, Venezuela, Argentina, Chile, Brazil). Managed all sales team(s), as active, "in country representatives/distributors¡½.
Increased power plant retrofit business revenues of from the US$ 8.00MM to 37.00MM/1985, /1986.
Supported all new boiler sales efforts in all Industrial/Utility Markets (Food, Chemical, Paper, Mining, Petroleum, Power).
1982-1984: Walsh Power Systems, (Minas Gerais, Brazil)
Project Manager
Steam and Power Plant: Engineering and Site Construction through to
Operation of HFO fired 22 MW STG based Industrial Power/ Steam Installation for
Petrobras, Minas Gerais, Brazil.
Contracted Bracep Engineering, Brazil, Rio de Janeiro, for all detailed engineering and construction services and took lead in Project and Construction Management.
1974-1982 ;Combustion Engineering Inc., (Montreal, Canada).
Senior Power Island Engineer
* Site Commissioning Engineer.( Spain, Mexico, Canada, Iran, Africa)
* Construction Engineer ( Mexico )
* Proposal/Sales Engineer.
* Project Manager.
1970-1974: Central Electricity Generating Board, England.
Senior Commissioning Engineer (1970-1974)
Station Fiddlers Ferry (4x500 MW, PF Coal Steam +4x17.5MW CTG).
1968-1970: Senior Efficency and performance Engineer.
Ironbridge A&B Power Stations (2x 500 MW + 4x22 MW, Coal PF)
1966-1968 Assistant Project Design Engineer
Midlands Generation Services Headquarters
1961-1966: Undergraduate Training/Apprenticeship Sponsorship
University of Birmingham Degree
University/Departmental rotation of 6mths, for Advanced Training
Central Electricity Generating Board.(CEGB), eg, Operations, Design,
Planning, Construction, Maintenace.
Formalized Apprenticeship (Major Trades), Experience: Operations, R&D,
Projects, Planning, Transmission, Maintenance, as part of the" Sandwich
Course "of the CEGB.
Interests:
* Computer Literacy in all Applications: (Technical, Remote Office, Economic Analysis).
* Cabinet Making and Woodwork in General as a form of productive relaxation.
* Sports: Fitness Routine, Golf, Ratchet Ball, Fishing, Bicycle Trekking.
* Reading: History, Financial News, IPP Project Activity, Technology Development..
* Improvement of my communication and management skills.
* Family and Friends
Education:
1950-1960: Public Grade and Grammar School Education Birmingham
1960-1965: B. SC, ( Hons ) Mechanical Engineering: Birmingham University.
1960-1965: Student Apprenticeship, C.E.G.B., England.
1965-1967: H.N.C. Electrical, Advanced College of Technology, Birmingham,
1980-1984: MBA. McGill University, Montreal, Quebec, Canada.
Additional Assets:
Languages
Fluent in Technical and Contractual English, ( Written / Oral/ Read).
Fluent in Technical and Contractual Spanish, ( Written / Oral /Read).
Fluent inTechnical and Contractual French, (Oral / Read).
Fluent in Technical and Contractual Portuguese, (Oral/ Read )
Experience Specialties:
* Systems Design (conceptual/prelimin/detailed) for wide range of Fuels and Power GenerationTechnologies.
* Project and Construction Management on Fossil fired STG/SC/CCCTG/Diesel Projects.
* Sucessful International IPP Greenfield to Commercial Operation Project Development.
* Experienced in /RFPùþs/EPC/FSAùþs/O&M/EIAùþs/FCùþs/ Agreement drafting/negotiating
* Multilingual/Multicultural Understanding for Power Generation Proposals /Contract Negotiations
* Experience in all Technical and Spreadsheet Programs to support Engineering and Financial Issues
* Good Negotiating and Contracting Ability from Owner and Suppliers side of Power Generation Projects.
* Inter- Personal and Inter¡ÔPersonnel Skill
Mobility: Mobility given Time and Right Opportunity.
References will be provided on request.
View contact information... |