JOB DESCRIPTION:
* Review and approve Subcontractors Work Method Statements, Quality Procedures and Inspection and Test Plans.
* Lead the team of QC inspectors to ensure that project work meets the required specifications. Supervised the team to make sure that proper inspections are carried out, and required PMC representative are notified for witness/hold point inspections at site and relevant Request For Inspections (RFI) are completed as per the ITP. Raising punchlist if any deficiency is observed.
* Issues Non-Conformance Reports (NCR) on works that deviates standards, quality procedures and design specifications.
* Coordinate with client (PMC) and vendor representative for all technical related issues of project clearing all doubts/bottleneck by raising Technical Queries and expediting issuance of site instruction to close the issue and smooth flow of RFI without loss of time.
* Coordinate, monitor and control site QC activities including stage wise inspections of systems/sub-systems.
* Maintain all inspection records, check lists, data sheets for final handover of the system to Client.
* Ensure that construction activities meet the HSE requirements applicable at site.
* Ensure that Flawless Start-up Initiatives are carried-out from initial stage up to precommissioning stage.
NAME OF COMPANY: UTS KENT CO. LTD (KENTZ GROUP, Ireland)
Address: Abu Dhabi, U.A.E.
Inclusive Date: February 25, 2006 – June 6, 2008
POSITION: QA/QC ENGINEER (E & I)
PROJECT INVOLVEMENT:
I&CS Upgrade and Integration of Pneumatic Control Loops to DCS (OGD-0)
Client: Abu Dhabi Gas Industries Ltd. (GASCO)
Habshan, Abu Dhabi, U.A.E.
January 2008 – June 2008
Onshore Gas Development Phase III (OGD III) Construction Project
Main Contractor: Eastern Bechtel Co. Ltd.
Client: Abu Dhabi Gas Industries Ltd. (GASCO)
Habshan, Abu Dhabi, U.A.E.
May 2007 – December 2007
Control System Upgrade of GE Turbine-Compressors (Shutdown Works)
Client: Abu Dhabi Gas Industries Ltd. (GASCO)
Asab, Abu Dhabi, U.A.E.
January 2007 – April 2007
Excitation System Upgrade of GE Turbine-Generators (Shutdown Works)
Client: Takreer Ruwais Refinery
Ruwais, U.A.E.
November 2006 – January 2007
Taweelah Gas Receiving Facility Construction Project
Main Contractor: Al Jaber-Technip Consortium
Client: Dolphin Energy Ltd.
Taweelah, U.A.E.
May 2006 – November 2006
Boil Of Gas and Sulfur Recovery Unit Construction Project
Main Contractor: Chiyoda/Costain
Client: Abu Dhabi Gas Liquefaction Co. Ltd (ADGAS)
Das Island, U.A.E.
February 2006 – May 2006
JOB DESCRIPTION:
* Conducts inspection, surveillance, and monitoring of installation activities as per issued for construction (IFC) drawings, clients specifications and standards, and other internationally recognized standards.
* Prepares and submits Request For Inspection (RFI) on completed works to clients for their approval.
* Inspects installation of process instruments, impulse tubings, instrument air lines, JBs, DCS, RTU panels, power, control, and instrument cables, cable glanding and terminations, motors, transformers, variable speed drives, capacitor banks, HV & LV swicthgears, lighting systems, earthing systems, cathodic protection systems, etc.
* Witness standard tests conducted on new equipment such as transformers, switchgears, MCCs, grounding systems, motors, cable IR and Hipot tests, etc.
* Witness calibration activities for instruments such as PTs, FTs, PDTs, MOVs, TTs, etc.
* Maintains calibration records of instruments (such as transmitters, transducers, etc.)
* Issues Non-Conformance Reports (NCR) on works that deviates standards and design specifications.
* Prepares and maintains inspection and test reports, quality records and documents.
* Prepares redlined drawings.
* Facilitate clean-up of exception items/punchlist items.
NAME OF COMPANY: M.R. AL-KHATHLAN EST. FOR CONTRACTING
Address: Dammam, K.S.A.
Inclusive Date: August 10, 2002 – August 21, 2005
POSITION: PROJECT QA/QC Manager (Aug. 2004 – Aug. 2005)
QA/QC Electrical Inspector (Aug. 2002 – Aug. 2004)
PROJECT INVOLVEMENT:
Process Area Emergency Shutdown System and Marine Control System Replacement (BI-3038), Yanbu Refinery
PMC: SNC Lavalin
Client: Saudi Aramco
Yanbu, K.S.A.
Designation: Project QA/QC Manager
Saudi Aramco SAP No.: 70003595
August 2004 – August 2005
Control System Replacement (BI-3535), NGL Plant (Yanbu Gas Plant)
PMC: SNC Lavalin
Client: Saudi Aramco
Yanbu, K.S.A.
Designation: QA/QC Electrical Inspector
Saudi Aramco SAP No.: 70002842
November 2003 – August 2004
Control System Replacement (BI-3536), Yanbu Crude Oil Terminal (YCOT)
PMC: SNC Lavalin
Client: Saudi Aramco
Yanbu, K.S.A.
Designation: QA/QC Electrical Inspector
September 2003 – November 2003
Control System Replacement (BI-3536), Saudi Aramco East/West Pipeline
PMC: SNC Lavalin
Client: Saudi Aramco
Abquiq-Riyadh-Yanbu, K.S.A.
Designation: QA/QC Electrical Inspector
August 2002 – September 2003
JOB DESCRIPTION:
As Project QA/QC Manager
* Prepares Quality Plan, Work Instructions, Special Work Procedures, Inspection and Test Plans, monthly and weekly quality reports.
* Implements Quality Management System in the project as per Saudi Aramco Quality Schedule (Sched. Q) and ISO 9000 series.
* Monitors the quality activities of the project.
* Coordinates with the client representatives on matters involving quality assurance and control activities.
* Initiates and prepares site technical queries.
* Review the quality of materials in quotations prior to submission to client for approval.
* Review materials Inspection Assignment Packages (IAP).
* Maintains calibration records of instruments (such as transmitters, transducers, etc.)
* Maintains records of test results conducted on cables and equipment.
* Review and sign-off Instrument Installation Inspection Records.
* Review Instrument Loop Folders.
* Initiates and conducts quality process improvement activities.
* Maintains database of audit, corrective actions and matters relating to quality measures.
* Prepares Photostat and Inspection Record books after project's completion as per contract requirements.
As QA/QC Electrical Inspector
* Prepares Inspection and Test Plan (ITP), Work Instructions, and Special Work Procedures.
* Prepares 2-Week Inspection Look Ahead Schedules.
* Conduct site inspections and implements the approved Project Quality Plan, ITP, Work Instructions, Special Work Procedures, Saudi Aramco Standards, and other recognized international standards (e.g. NEC, NEMA, etc.).
* Conducts material receiving inspections.
* Prepares and submits Request For Inspection (RFI) on completed works to clients for their approval.
* Issues Non-Conformance Reports (NCR) on works that deviates standards and design specifications.
* Prepares daily quality reports, quality records and document.
* Witness standard tests conducted on electrical equipment such as Insulation Resistance, Contact Resistance, Over Current Trip Test for Circuit Breakers and Ground Fault Protection, low voltage Transformers winding Turns Ratio, Impedance, Polarization Index, etc.
* Inspects calibration of intruments such as transmitters, transducers, gauges, etc.
* Inspects installation of field instruments (e.g. Pressure Transmitters, Pressure Differential Transmitters, Flow Transmitters, Level Transmitters, etc.)
* Prepares Instrument Installation Inspection Records.
* Assists in preparation of Loop Folders.
* Witness instrument loop checks and function tests.
* Witness pre-commissioning works for UPS and Stationary Battery System, Battery Monitoring System, Equipment Smoke Detection System, DCS, ESD, and SCADA System.
* Prepares redlined drawings.
* Facilitate clean-up of exception items/punchlist items.
* Prepares partial/final Mechanical Completion Packages.
NAME OF COMPANY: AL-SAIGH TRADING AND CONTRACTING
Address: Buraidah, Al-Qassim, K.S.A.
Inclusive Date: June 28, 2000 – April 15, 2002
POSITION: PLANT ELECTRICAL ENGINEER
PROJECT INVOLVEMENT:
Operation and Maintenance of
Water Treatment Plant and Tower
Ministry of Water
Buraidah, Al-Qassim, K.S.A.
June 2000 – April 2002
JOB DESCRIPTION:
* Prepares Plant Electrical Maintenance Schedules.
* Identifies actual potential problems and deficiency situations and provide prompt solutions.
* Conduct electrical inspections on sub-contractors activities as per their approved Contract's Scope of Works and Specifications.
* Review materials quotations.
* Prepares maintenance report and the likes.
NAME OF COMPANY: FORMOSA PETROCHEMICAL CORPORATION (FPCC)
Address: Mailiao, Yunlin, Taiwan, R.O.C.
Inclusive Date: May 7, 1999 – May 6, 2000
POSITION: ELECTRICAL INSPECTOR
PROJECT INVOLVEMENT:
* Crude Oil Refinery Construction
Formosa Petrochemical Corporation
Mailiao, Yunlin, Taiwan, R.O.C.
May 1999 – May 2000
JOB DESCRIPTION:
* Performs 'Hold', 'Witness' and 'Surveillance' inspections and tests on contractors' construction activities.
* Inspect materials and equipment as applicable to ensure compliance with FPCC specification requirements for proper handling, storage and protection at warehouses and/or construction sites.
* Monitor Contractors' Quality System, records and Quality Personnel for compliance with requirements.
* Review and evaluate Contractor's Quality document submittals.
* Witness on-site and offsite material, equipment, and installation test for compliance with standards and approved procedures.
* Record legibly and accurately all controversial and non-complying construction practices, materials and equipment and report to supervisor detailed potential problems for early resolution.
* Write inspection reports and initiates Non Conformance Reports (NCRs), Worksheets, and Equipment Deficiency Reports (EDRs) as needed.
* Assist in the training of Maintenance Personnel for operation of electrical equipment to be handed-over.
NAME OF COMPANY: GLOBAL TECHNOLOGY SYSTEMS PHILS., INC.
Address: Pasig City, Metro Manila, Philippines
Inclusive Date: September 7, 1997 – May 6, 1999
POSITION: PROJECT ENGINEER
COMPANY DESCRIPTION:
Global Technology Systems Phils., Inc (GTSPI) is a construction company which handles mechanical & electrical projects ranging from Building construction to Industrial plants. GTSPI is also supplier of Groupe Schneider products such as Circuit Breakers, Contactors, Variable Speed Drives, etc.
PROJECT INVOLVEMENT:
* Construction of
Sulfuric Acid Plant with Co-generated 16MW Power Plant
Main Contractor: Monsanto Environchem Co.
Client: Philippine Phosphate Fertilizer Corporation
Leyte, Philippines
September 1997 – May 1999
JOB DESCRIPTION:
* Responsible for examining bid documents, plan specifications and procedures to be performed on the project.
* Perform job costing, planning, documentation, and evaluates change orders and billings.
* Supervise electrical installation works as per Project's scope of work and specifications.
* Review redlined and as-built drawings.
* Prepares progress reports.
NAME OF COMPANY: HI-ELES INDUSTRIAL CORPORATION
(HITACHI Elevators and Escalators)
Address: 1351 Angono St., Makati City, Philippines
Inclusive Date: August 7, 1995 – July 21, 1997
POSITION: INSTALLER
PROJECT INVOLVEMENT:
Installation of Elevators and Escalators for the following projects:
EDSA Shangri-La Hotel (Makati, Phils.)
South Center Tower (Alabang, Phils.)
Asian Plaza 2 (Makati, Phils.)
Prince David Condominium (Manila, Phils.)
Vernida 1 Bldg, (Makati, Phils.)
Maintenance of Elevators and Escalators at the following areas:
Makati City Area (189 Elevators, 20 Escalators, and 2 Moving walks)
Manila City Area (86 Elevators and 13 Escalators)
JOB DESCRIPTION:
* Responsible for proper installation of power and control system of elevators and escalators.
* Conducts testing and commissioning of elevators and escalators.
* Adjusting and setting elevator and escalator parts and devices for normal operation.
* Conduct repairs and replacements of defective and damaged parts and devices.
* Prepares installation and maintenance reports.
NAME OF COMPANY WIREWAYS Engineering
Address 1125 Metrica St., Sampaloc, Manila, Philippines
Inclusive Date June 1, 1993 – July 31, 1995
Position ELECTRICAL ENGINEER
PROJECT INVOLVEMENT:
Construction of Sulfuric Acid Plant
Client: Chemphil LMG
Pasig City, Philippines
April 1994 – July 1995
Construction of Flour Mill
Client: Philippine Foremost Corporation
Iloilo City, Philippines
June 1993 – April 1994
JOB DESCRIPTION:
* Responsible for examining bid documents, plan specifications and procedures to be performed on the project.
* Perform job costing, planning, documentation, and evaluates change orders and billings.
* Supervise electrical installation works as per Project's scope of work.
* Prepares daily activity report.
* Prepares redlined and as-built drawings.
TRAININGS AND SEMINARS
1. Internal Quality Management System (QMS) Auditor Training Course
SGS Inspection Services
Dammam, K.S.A.
Certificate #: SGS/SSCE/IQMSA/505830/P/12489
January 4-5, 2005
2. ISO 9000:2000 Series Foundation Training Course
SGS Inspection Services
Dammam, K.S.A.
Certificate #: SGS/SSCE/QMSFTC/505829/P/1802
January 3, 2005
3. Computer Aided Construction Project Management (CPM)
CADVision Engineering Technologies
Manila, Philippines
May 21, 2000 – June 25, 2000
4. Computer Aided Drafting and Design (CADD)
CADVision Engineering Technologies
Manila, Phils.
Nov. 1998 – Jan. 1999
5. Safety of Life At Sea (SOLAS)
* Survival Craft Handling
* Personal Survival Technique
* Fire Fighting and Fire Prevention
* First Aid at Sea
Philippine Seafarers Training Center
Manila, Philippines
Feb. 6-20, 1995
COMPUTER APPLICATIONS
1. MS Office
2. AutoCAD
3. Microstation
4. Primavera Project Planner
EDUCATIONAL ATTAINMENT
COLLEGE: CENTRAL PHILIPPINE UNIVERSITY
Bachelor of Science in Electrical Engineering
Jaro, Iloilo City, Philippines
1993
LICENSES:
1. Board Passer: Philippine Registered Electrical Engineering Licensure Exam., April 1994
License No. 0017647, Feb. 1995
2. Board Passer: Philippine Registered Master Electrician Licensure Exam., October 1993
License No. 0016327, Nov. 1994
View contact information... |