QUALIFICATIONS: High school, Punjab School Education Board, Chandigarh in 1980
Trade Certificate in DM Mech. from Industrial Training Institute, Patiala in 1985
Training on MICROSTATION Ver.3.0 by Rolta India Ltd in September 1990
Learned French language & passed 1st. semester examination of French Studies from Alliance Franchise, New Delhi in 1991
Completed Bachelor of Science in Mechanical Engineering from Rochville University, MD, USA in 2008
LANGUAGES: English, Hindi, Punjabi
COMPUTER LITERACY: AutoCAD, MicroStation, PDS, 3DM & MS Office
CAREER SUMMERY: 23 Years plus experience in plant engineering, piping study drawings, equipment layouts, nozzle orientation, general arrangement piping drawings & piping supports.
- Plot Plan
- Equipment Layout
- Preparation & Review of Piping GA drawings
- Nozzle orientation of vessels
- Preparation & checking of piping isometrics
- Bill of Materials
- Piping supports
FIELDS OF EXPERIENCE: Oil & Gas, Power Plant, Petrochemical, Effluent Treatment & Fire Fighting
EXPERIENCE: Working with Worley Parsons, Atyrau, Kazakhstan LLP
As PDS Lead Piping Designer in Plant Design Team on GUP U-800 Revamp Project For TANGIZCHEVOROIL (TCO), Tangiz, Kazakhstan Visited the jobsite for the survey of the Different Areas,
Assignment Duration: August 2008 - Till Date
Worked as Checker / Piping Lead Designer in Plant Design Team on GAS UTILAZATION Revamp Project For TANGIZCHEVOROIL (TCO), Tangiz, Kazakhstan, Visited the jobsite for the survey of the Coalescer Filter Area,
Assignment Duration: April 2008 – August 2008
PREVIOUS WORK HISTORY: Worked with First Egyptian Engineering Co.– Cairo, Egypt
As Checker/Technical Lead Designer in Plant Design Team and assisting to Engineering Group Supervisor on EL-TEBBIN THERMAL POWER STATION, EGYPT.
Assignment Duration: August, 2007- April, 2008
Worked with Crestville Engineering & Technology Co. Ltd. – Lagos, Nigeria as Lead Piping Designer/PDS/PDMS Designer on Oil & Gas jobs for Shell Fuel Oil Depot, Nigeria.
Assignment Duration: April, 2007- June, 2007
Worked with FLUOR DANIEL INDIA PVT. LTD.
Gurgaon as Principal Designer (Piping) /Deputy Lead Supervisor/Area Lead Designer, Responsible for VAM / AA Tankage Area Modeling & checking of others work on Smart Plant Review and PDS (3D Modeling) Assignment/Visit to Fluor Daniel - Greenville (U.S.A.) from 5th February 2007 to 22nd February 2007 for 33% Model Review with client & Greenville office For Sipchem Project, Saudi Arabia
Assignment Duration: June, 2006- March, 2007
BECHTEL INDIA PRIVATE LIMITED, New Delhi on various projects and visited other countries per the detail as mentioned below
Deputy Lead Supervisor / Lead Designer / Senior Designer (Piping)
Assignment Duration: April, 1996 – June, 2006
Worked as Lead Designer/Deputy Lead Supervisor & was responsible for Vendor document Review & Checking Piping Isometrics generated by other designers on 3DM (3D Modeling). For
Elm Road Generating Station, Michigan,USA
Assignment Duration: March, 2006 – June, 2006
Worked as Lead Checker, Checking Equipment parametric/Nozzle Reports and Isometrics on Smart Plant Review and PDS (3D Modeling). For
Sonahess G C R Facilities, Algeria
Assignment Duration: January, 2006- March, 2006
Worked as Area Lead Designer & responsible for Pipe Rack, Day Tank Area, Cooling Tower Area & co-ordination with other leads Piping Design, Equipment Modeling & Pipe Modeling on PDS (3D Modeling). For
Borger Refinery, Borger at Texas, U.S.A.
Assignment Duration: April, 2005- December, 2005
Worked on Piping Study Drawings, Equipment Modeling & Pipe Modeling on
PDS (3D Modeling). Assigned to Bechtel - Houston (U.S.A.) from August 2003 to January 2004 for Revamp Project of Ultra Low Sulfur Diesel Projects, at Motiva Convent Refinery, & Norco Refinery, U.S.A.
& visited the Job site for no of times during the stay in Houston
Assignment Duration: August, 2003- February, 2005
Worked on Equipment Layouts, Piping Studies & M T O,
Assigned to Bechtel-London (U.K.) from April 2003 to May 2003
for Gasco OGD - III / AGD – II Feed Project for ADNOC, Abu Dhabi.
Assignment Duration: April, 2003- May, 2003
Worked on Piping Design, Equipment Modeling, Isometric Ext., for Area C & G Equipment's Parametric Report / Isometric Checking on PDS (3D Modeling). Assigned to Bechtel - Houston (U.S.A.) from July 2002 to October 2002 for Equiva Low Sulfur Gasoline Projects, at Motiva Convent Refinery, & Deer Park Refinery, U.S.A.
Assignment Duration: July, 2002- March, 2003
Worked on Pipe, Equipment Modeling & Designing of of Different System of U/G & A/G piping, Isometric Ext.
on 3DM (3D Modeling). Assigned to Bechtel - Frederick (U.S.A.) since December '2000 to March '2001 for Intergen North America LP's, Power Plants (Cottonwood, Magnolia, Redbud ) U.S.A.
Assignment Duration: December, 2000 – July, 2002
Worked on Pipe, Equipment Modeling & Designing of Different System of U/G & A/G piping, Isometric extraction on 3DM (3D Modeling). for Sabine River Works LP, Cogeneration Plant, Orange, Texas, U.S.A.
Assignment Duration: July, 2000-September, 2000
Worked on Pipe, Equipment Modeling & Designing of Different System of U/G & A/G piping, Isometric Extraction on 3DM (3D Modeling). Assigned to Bechtel - Frederick (U.S.A.) from February '99 to November '99 for Coryton Energy Project, Stanford-Le-Hope, England, U.K.
Assignment Duration: February, 99 – June, 2000
Worked on Checking of Isometric, Making & checking of Sleeper Location & Stringing Drawings of Refinery Tank Farm & O & U Additional Areas in PDS (Plant Design System) Ver. 6.1 for Reliance Petroleum Ltd., Jamnagar Refinery Project. Jamnagar, India
Assignment Duration: January, 98 - November, 98
Worked on Piping Design & Equipment Modeling, for Fire Water Pump House & Fuel Gas Compressor House, Extraction of Isometrics & Bill Of material in 3DM
Ver. 5. for Spalding Energy Project, Spalding, U.K.
Assignment Duration: August, 97 - December, 97
Worked on Modeling / designing of pipe supports, Selection of Supports, Extraction of hanger sketch using HGRSKET software on 3DM (3D Modeling)
for different Systems for Samalayuca-II Combined Cycle Project, Mexico, U.S.A.
Assignment Duration: January, 97 - August, 97
Worked on Pipe, Eqpt., & Hanger Modeling, Interference Report & Iso Ext.on 3DM (3D Modeling) on Different systems for Rocksavage Power Project, Runcorn, U.K.
Assignment Duration: May, 96 - January, 97
ENGINEERS INDIA LTD., New Delhi on deputation thru Dalal Consultants & Engineers Private Limited
Senior Draughtsman (Piping)
Preparation of piping GA drawing on AutoCAD Release-11. Review of Piping GA, Isometrics & Supports drawing.
LPG Plant, Lakwa
LPG-Recovery Unit, Usar
Ethylene Plant, Auraiya
Assignment Duration: July, 93 - April, 96
DEGREMONT INDIA LTD, New Delhi
Senior Draughtsman (Piping)
Preparation of piping GA drawing, Plot Plans, Equipment Layouts, P&ID's, Isometrics, Piping Supports & BOM.
E.T.P. Gola Distillery, Gola Gokarnath
E.T.P. Synthetics & Chemicals, Bareilly
E.T.P. Kedia leathers & liquors,Indore
E.T.P. Khoday Distillery,Banglore
Assignment Duration: January, 89 - July, 93
TECHNOFAB ENGINEERING LTD., New Delhi.
Draughtsman (Piping)
Preparation of Isometrics & Bill of Material of fire fighting system for Super Thermal Power Station, Korba
Assignment Duration: April, 88 - January, 89
CHEMICAL & METALLURGICAL DESIGN CO.
LTD., New Delhi
Draughtsman (Mech.)
Preparation of vessel data sheets, GA & Isometrics drawing.
Indian Calcium Carbide Ltd.,
Madhya Pardesh Calcium Carbide Ltd.,
Assignment Duration: October 85 - April 88