1995 – 2005 FT. MCDOWELL INDIAN COMMUNITY - Fountain Hills, AZ
Construction Engineer - Managed construction of 1500 acre pecan farm. Items included, clearing, main line piping, distribution piping, pump station(s), backup well field, tree layout and fencing. Total cost $6 Mil. Also managed construction of 50 new home additions, $3 mil water, electric and phone upgrades along with new subdivisions and roads. Recently competed a new 10.7 Million dollar wastewater treatment plant and have started a 4.4 Million water upgrade and a 5 Million sewer upgrade.
1993 – 1994 STATE OF ARIZONA, DEPT. OF ADMINISTRATION Phoenix, AZ
Project Manager - Temporary position assisting in building projects. Duties included negotiating and contracting for professional services, preparing bid documents and construction administration.
1984 – 1993 KS ENGINEERING & CONSTRUCTION Tempe, AZ
Partner/ Owner/ Public Works Contractor - Specialized in school work and industrial projects. Design/ Built custom homes. Performed all phases of work including the bidding, project management, supervision, accounting and all items necessary to run a successful business.
1979 - 1984 ARIZONA PUBLIC SERVICE, NUCLEAR CONSTRUCTION Phoenix, AZ
Senior Civil Engineer/ Owners Representative - Reviewed all plans/equipment/procurement/costs of a civil or architectural nature. Gained specific knowledge in nuclear design and construction as well as quality assurance and licensing.
1979 DAMES AND MOORE, Phoenix, AZ
Geotechnical Engineer - Earth dam design
1977 MACHINERY ERECTION Ajo, AZ
Boilermaker - Trade labor for Local 627
1976 M. W. KELLOGG Donaldsonville, LA
Field Engineer - Field work on new Ammonia Plant
1973 - 1976 M. W. KELLOGG New Orleans, LA
Field Engineer - Performed plant layout and coordinated subs. Prepared schedules, purchased materials, performed testing at new Shell Oil Refinery.
EDUCATION:
Arizona State University M.S. Civil Engineering 1979
Arizona State University B.S. Construction 1973
PROFESSIONAL ASSOCIATIONS:
Registered Civil Engineer, Arizona, No. 15280
Registered Land Surveyor, Arizona No. 16154
Member, Panel of Arbitrators, American Arbitration
DETAILED BACKGROUND:
I began my career working in industrial construction after graduation from Arizona State University in 1973.
I was first assignment was in New Orleans, LA, at the Shell Oil Refinery working on-site as a field engineer for M.W. Kellogg. At Shell, I performed foundation layout and coordinated subcontractors. I later prepared schedules, made minor design modifications, purchased materials, and conducted hydro tests.
In 1976, I returned to Arizona for graduate studies in Civil Engineering. During my term at ASU, I worked part-time throughout the year. Positions included additional field work for Kellogg, analysis and design for Dames and Moore, and as a trade labor boilermaker for Phelps Dodge.
Upon graduation in 1979, I joined the Nuclear Project Management Staff of Arizona Public Service. My responsibilities included review of all engineering, design, equipment, costs and procurement of all items of a civil or architectural nature and coordination of any additional review which was necessary.
During my term with the Project, I gained specific knowledge and experience in contract administration, procurement methods, nuclear power plant design, construction and engineering standards, cost estimating, quality assurance, and nuclear power plant licensing.
In 1984, I began as Owner and Project Manager at KS Engineering and Construction. Since that time, KS performed public works contracting with most of the major municipalities and school districts in the Phoenix area. All projects have covered the broad spectrum of commercial and industrial construction. The diverse nature of these projects include; stadium renovations, waste water dechlorination facilities, an emergency chlorine scrubber, water well modifications, computer and remote telemetry units, and hazardous waste storage facilities. KS also built school modifications, additions, and sports facilities.
In January, 1993, KS ceased operations and I accepted a temporary position with the State of Arizona, Department of Administration to assist in a 15 million dollar build out of newly purchased buildings and to augment the needs of the prison construction program. Duties included negotiating and contracting for professional services, preparing and competitively bidding for construction services and administering construction contracts. Project responsibility included office space renovation, gas line replacement, installation of plate and frame heat exchangers, purchase of HCFC chiller units, fire safety systems, and voice\data systems.
After completing projects for the State, I accepted the position of Construction Engineer with the Ft. McDowell Indian Community in 1995. In this position, I have managed construction and helped design a Bureau of Reclamation funded 1500 acre mist irrigated pecan farm. Activities included clearing, fencing, construction of roads and drainage structures, overseeing testing, building two VFD electric turbine pumping plants, a 5 plant backup well field, over 15 miles of mainline piping and over 150 miles of distribution piping. Approximate cost - $6Mil. During and after project construction, I have also managed bidding and construction of 50 new homes, a $3Mil Community water, electric and telephone upgrades, along with new subdivisions and roads.
In January, 2002, Ft. McDowell constructed an $11Mil SBR Wastewater Treatment Plant using a modified Design/build contract. I had the full responsibility for overseeing the design and construction of the facility. The plant completed, on time with no change orders and has functioned excellent. After the completion of the facility, I oversaw completion of design and bidding for $4.5Mil domestic water upgrade. This upgrade consisted of refurbishing two existing wells, installing 4 storage tanks with about 1Million gallons of storage, 7 miles of new waterline and an automated booster pump station. This project completed in October, 2004. Currently, I have started construction on a $5.3 million sewer system and lift structures.
Completed Projects 1995 - 2005
PROJECT NAME DATE COST CONTRACTOR
RV Park 9/1/2004 $5,000,000 W.E. O'Neil
Dry Conduit for Fiber Optic and Cable 8/1/2004 $188,000 Hunter Contracting
Sewer Design CM at Risk - design portion 3/3/2004 $57,000 Hunter Contracting
Driveway and Road Improvements 3/3/2004 $1,100,000 LTC
Golf Course Irrigation Line 1/11/2004 $100,000 LTC
Sewer Construction - CM at Risk 1/10/2004 $5,300,000 Hunter Contracting
Out of Africa Reclamation 1/6/2004 $100,000 Ft. McDowell S&G
Water Delivery System Design and CA 10/10/2003 $450,000 Stantec
Water Delivery System Construction 10/10/2003 $4,600,000 MGC
Recreation Center Ramp and Drainage 5/19/2003 $25,000 C&W Restoration
Sewer Design Casino to Grande Wash 4/12/2003 $506,000 Stantec
Utility Rate Study 4/6/2003 $50,000 L. Gold and Assc.
Waste Water Operations 4/1/2003 $240,000 Severn Trent
City of Phx - Wellfield Turn Over 1/27/2003 City of Phoenix
Casino Remodel 12/12/2002 $2,300,000 Kitchell
Adventures Roof Study 10/13/2002 $1,000 Landa & Assc.
Foundation Underpinning 3/14/2002 $18,000 AZ Helical Piers
Natural Gas Line 3/12/2002 $175,000 Southwest Gas
New Orchard Development - BOR 2/2/2002 $2,500,000
Clubhouse Booster Pump Station 10/22/2001 $35,000 Stantec
Clubhouse Booster Pump Station 10/22/2001 $150,000 Wespac
Waste Water Plant Design Build 5/12/2001 $10,800,000 Hunter/ Wilson
Recreation Center Remodel and Painting 5/3/2001 $82,500 JAR Construction
Shipping and Receiving remodel 2/15/2001 $130,000 Agate, Inc.
Scoreboard 12/20/2000 $20,000 Agate, Inc.
Adventures remodel and water supply 12/1/2000 $175,000 JAR Construction
Golf Course Sewer and dry conduits 12/1/2000 $200,000 LTC
Golf Course Irrigation Well and Infrastructure 10/10/2000 $250,000 LTC
Earl Stratton House 8/8/2000 $50,000
Waste Water Treatment Plant Design 8/1/2000 $900,000 Malcolm Pirnie
Water Needs Study 6/7/2000 $52,200 Stantec
Hotel Feasibility studies 3/3/2000 $500,000 Bergman Walls
Temporary Fire Station 2/28/2000 $100,000 Agate, Inc.
City of Phx - Wellfield Evaluation 1/7/2000 $18,000 Stantec
School Building Site Plan 7/21/1999 $25,000 CMX
Javalina Water Lines 3/1/1999 $40,000 LTC
Dodgers Spring Training Site Planning 2/18/1999 $50,000 Speedie/ CMX
Waterline/tank fire protection Phase II 12/8/1998 $1,400,000 T&T Construction
New Well Rodeo Grounds 10/10/1998 $20,000 SW Water and Min.
New Water Services 7/14/1998 $104,291 Ft. McDowell S&G
Community Well Improvements 4/28/1998 $40,000 Yost and Gardner
Community Well Improvements 4/28/1998 $250,000 T&T Construction
Jomax Quarry Investigation 3/14/1998 $30,000 SW Water and Min.
Boundary Pond Study 2/2/1998
Yavapai Hills phII Road and Infrastructure 1/9/1998 $302,000 Monks
South Farm Road 9/20/1997 $595,000 Banicki Construction
Yavapai Rd. Dry Conduits 8/19/1997 $161,915 Ft. McDowell S&G
Surama Dry Utilities 8/19/1997 $162,000 Ft. McDowell S&G
Acid Injector 8/4/1997 $25,000 Ag Acid Inc.
Yavapai Rd. Dry Utiltites 6/24/1997 $140,000 Hard Rock Const.
South Area Orchard Irrigation System 4/28/1997 $729,000 Rain for Rent
South Area Pipeline Delivery System 4/16/1997 $2,600,000 T&T Construction
Tribal Farm Well Pumps and pipelines 1/20/1997 $300,000 T&T Construction
Weir Modification 12/17/1996 $11,000 Cactus Con.
Land Smoothing and Ripping 12/12/1996 $100,000 Ft. McDowell S&G
Well Design for Farm 9/20/1996 $35,000 SW Water and Min.
Well 3 Pump, motor, and piping 9/10/1996 $57,000 Watt-Irr
Farm Road Surveying 7/22/1996 $10,000 Ansco
35 New Homes 7/17/1996 $3,700,000 ABR
Casino water tie in 4/16/1996 $20,000 Cactus Con.
Fire Protection Phase 1 4/4/1996 $578,000 Lee's Backhoe
South Area Farm Irrigation Line 2/14/1996 $353,000 Watt-Irr
North Area Pipeline Delivery System 1/19/1996 $845,000 T&T Construction
South Area Farm Fencing 1/16/1996 $139,000 Associated Fence
Well Drilling 1/4/1996 $289,000 Weber Pump
North Area Farm Fencing 12/15/1995 $48,000 Acme Fence
Community Health Center 12/1/1995 $2,200,000 Summit Builders
Electric Line to Rodeo Grounds 10/10/1995 $144,000 SRP
New Baja Gas Station 9/15/1995 $1,700,000 B.L. Weber Group
Baja Gas Remediation 9/14/1995 $611,000 Groundwater Tech.
Rodeo Ground Development 9/9/1995 $101,000 Gladstone
Daycare Center 6/28/1995 $400,000 BCS
Landfill Closure 4/1/1995 $365,000 Kajima
Main Farm Road 4/1/1995 $729,000 Hunter Contracting
Orchard Development Planning 3/1/1995 Ecoplan
$55,581,906
View contact information...
«« previous resume
next resume »»
Search Results (Resumes 251 to 300 of 638)
Go to Search Parameters...
Brief Description
DOCUMENT CONTROL MANAGEMENT, PROJECT SUPPORT, TECHNICAL & DESIGN COORDINATION, EDMS..ETC
Legal & Regulatory Affairs Executive/Advisor
Camp Manager / Logistics
Totally, more than 18 .6 years of experience in Diversified Fields, of which 15 years in Retail Trade in a Service-Related industry & 3.6 years in Wholesale Trade.
Over 25 years of design and engineering experience; providing design, engineering and management services for a variety of projects and fields. Expertise includes estimating, conceptual and finalized layouts, piping design, instrumentation, process, P&ID development, sizing/specifying/requisitioning
I have over 4 years experience in Inside Business Development field / Recruiting. Am most interested to work in Gulf like Oman, Kuwait, Qatar etc...Throughout my Inbound Business Development career / Tele sales. I believe I would good in Market Researching, Market Analysts.
Exceptional Facility and Construction Management Executive
Professional experience in QC Document Control, Project Cost Reporting, Materials Control, Logistics, Administration, NDT Supervision, NDT reporting, QA/QC etc. with Oil & Gas and Marine (Onshore & Offshore).
I have been working extensively with M/s. Saudi Wiemer & Trachte Ltd., Riyadh for ten (10) years in their Tendering & Procurement Dept. The company has given me an experience and a clear edge over my professional peers.
21 years EPC experience Reading and Interpreting Contract Drawings, Defining Project Scope, Creation of EPS/OBS/WBS, Performing Detailed Quantity Surveys, Cost Estimating, Identifying Resource Requirements, CPM Scheduling, Cost/Resource Management & Implementation of ANSI/EIA-748-A EVMS Guidelines.
Hardworking, Driven Individual
Government Contracts Financial Executive
Seeking business development position with multinational organization involved with turnkey type projects where my background of over 16 years progressive oil and gas industry experience will provide value creation to grow business.
A senior professional with 22+ years of rich experience in Project Management, Inventory Management, Operations Management, Documentation Management; presently associated with Voltas Ltd, Qatar; seeks senior level opportunity preferably in on shore - off-shore oil/gas projects.
Experienced financial analyst with over 15 years of domestic and international integrated oil and gas company experience covering a broad spectrum of activity. Proven expertise in the areas of Finance, Accounting, Project Management, Materials Management, Systems implementations (SAP/R3).
Professional engineer with wide ranging international experience in project, engineering, reliability, business development, sales and commissioning of refinery.
I am Professional Logistician (CITT), Certified Purchaser and Journeyman, H/D-Partsman (automotive and mining equipment-including underground) and Warehouseman.
Possess excellent interpersonal skills and organization skills;• Able to adapt and work within a dynamic environment;,Willing to work under pressure
Project cost control / scheduling
Over 26 years experience of Gological Explorations for various minerals in Government Sector. Now seeking for an upward change.
Facilities Management, Procurement Specialist, Proficient in MicroSoft Office Suite
Account Management - International Department
A Senior Financial, Systems and Accounting Manager with significant experience in the development, creation and management of accounting and reporting systems gained both internationally and domestically. Have worked in the United States and the United Kingdom for Citibank, Xerox, Yale, Louis Dreyf
Supervisor / Foreman / Project Manager
Broad experience of water and sewage treatment plants, gas turbine stations, oil pipelines, commercial and industrial building, housing, earthworks, rail and general civil, mechanical and electrical works in UK, Africa and Asia. Project and Site Management in a variety of challenging locations.
Financial accountant - 12 years experience - oil & gas
Mechanical engineer (4 yrs degree) with appx 15 yrs exp in Contract & Project management. LOOKING FOR CHANGE IN MIDDLE-EAST, CANADA OR INDIA (AVAILABLE FOR IMMEDIATE START)
Seeking a Management position where my considerable experience and knowledge of Construction civil estimating and project management that can be fully utilized to help drive employer profit margins and complete contracts on time.
Accomplished Head of Finance & Administration with 11 years of experience and a history of reducing costs, effectively managing financial operations, and optimizing efficiency and productivity. Demonstrated expertise in accounting and GAAP, SAP, strategic planning, and cross functional collaboration
accounting administration
10 years of experiences at administration, academic and operation line
An experience individual with excellent knowledge of Freight handling / Exports Management with the objective of achieving organizational goals and making it a strong profit center, seeks an opportunity in managerial capacity.
Project Manager, QA/QC Wireless Telecommunications
B.Sc. in computer science and 13 years of experience in IT / Accounts / Trainer / Graphic Designer
Outside Plant Technian, Bell System Trained, College Degree, AVAYA ACS PBX READY, copper/fiber palnt install/test/termination, Cat 5 and 6 as well as paging, cameras and home theater seeks contract/fulltime work in Middle East or almost anywhere in the world..
Human Resources professional with over 15 years experience. Areas of expertise include benefits administration, employee relations, payroll, reporting, records management and project management. Responsible, detail oriented with strong organizational, analytical, problem solving, communication, an
Free!
Multi tasked in the construction filed. SAP 4.6, Lotus Notes, Act, JD Edwards, Microsoft, Access, Material handler, Tool-Room, A/P & A/R, Procurment, Human Rescources duties
Very experienced in Logistics, Procurement, Warehousing, Material Control.
I always see to it that my work is based on strong leadership and proper documentation.
Mining Engineer with surface, underground, contracting, industrial minerals, metal mining, hard rock mining, block caving, narrow vein, cut & fill, dragline, international, process, frontline shift supervisory, mine planning, & permitting experience
Licensed professional civil engineer. Have worked mostly in construction as either an owner or an owner's representative. Enjoy doing field work and would like to work in a foreign country.
GIS analyst , GIS Developer , GIS Trainer SDE administrator , GIS Data manager
A leader with extensive experience in demanding work environments and a proven ability to prioritize business needs, then implement creative solutions. Consistently demonstrates a passion to exceed organizational goals by improving customer satisfaction, improving quality and reducing cost.
Systems Engineer - Project Planning & Control Specialist. Oil & Gas / HVAC / Construction
Project Manager (Electrical, Alarm Applications, Construction,Safety)
Manager / Supervisory position in the field of Administration, Personnel, Finance Accounting, Business
Procurement, Materials and Logistics Manager (SCM): 20 years international experience in gas & oil and energy projects.
I have over 19 years of experience working in the Petroleum Pipeline Industry doing a variety of roles. Until very recently, I have been on a special assignment as a “Lead Project Inspector” on a new Pipeline Delivery Facility, but also have other additional managerial & supervisory responsibilities
DOCUMENT CONTROLLER
Safety/Env (HSE) post sought (Will also accept Quality related positions) Reliable/Flexible/Language proficient - Willing to work worldwide, available from May 2008
1
2
3
4
5
[ 6 ]
7
8
9
10
11
12
13
Seach Parameters
Change search parameters...
CATEGORIES:
Administration;
INDUSTRIES:
Construction;
Change search parameters...
Keywords:
(e.g. mining engineer)
Find results with:
ANY of the words
ALL of the words
WITHOUT the words
Save this search parameters...
Post job with this search parameters...
Frequently Asked Questions
What's the most effective way to perform a search?
Go to
Advanced Search
1. Select 'Industries', 'Categories', 'Education', and 'Experience' fields. Click 'Search' and look through results.
2. Enter one or two of the most important keywords. Click 'Search' and look through results.
3. To search within results add more keywords.
How can I find resumes that contain specific exact phrase?
To search for an exact phrase, just put quotation marks around two or more words, for example "mining engineer". Use this feature to narrow your results or to find words that can be typed differently, for example AutoCAD "Auto CAD".
More Frequenly Asked Questions...
Employer's Center
»
Employers Home
»
Feedback
»
Help
»
Post Jobs
»
Edit/Delete Jobs
»
Search Resumes
»
Resumes By Email
»
My Account
»
Log In
»
Log Out
©1999-2008 Misco Jobs. All rights reserved. Contact:
support@miscojobs.com