EXPERIENCE
Feb 2005- Till Date C
airn Energy PLC, Edinburgh, UK

Group Projects Engineer
Group Technical Engineering & Operations Department
Cairn Energy PLC (Head office)
Edinburgh, Scotland, UNITED KINGDOM

Responsibilities:
* Prepare, Review Field Development Plan for Company developing assets.
* Deal with respective JV's of various operating assets and organize Technical Committee meetings.
* Prepare development cost estimates and budget.
* Responsible for project conceptualization & Front end Engineering & of Developing Assets.
* Responsible for Detailed Engineering of Development Project.
* Responsible for Development Project Implementation, Management, Construction & Commissioning.
* Review assets annual budget for board approval.
* Responsible for Technical Integrity of operating assets of company in India and Bangladesh.

Projects:
* Rajasthan Field Development in India. Involved in Field development Plan preparation and Front End Engineering being carried out by MEG Worley in Calgary Canada. ( Total Estimated Development cost of Phase-I is approximately $ 1.2 Billion)
* Rajasthan Southern Field Development (Rageshwari & Saraswati) on Fast track basis- First Oil by Q3 2006.
* Heading the Technical Integrity Audit of Sangu Gas Filed in Bangladesh.
* De-bottlenecking of Ravva Oil & Gas Field to sustain the production plateau of 50,000 BOPD.

March 2004-Jan 2005
Cairn Energy India Pty Limited

Sr. Manager-Projects
Water Injection Pilot Project ($ 10 million)
Rajasthan Block- RJ-ON-90/1. INDIA

Job Description: Responsible for Project conceptualization, Front End Engineering, Detailed Engineering, Managing Installation Contract, Tender specification & document preparation, Installation Contracts review, evaluation and award, Review of design documents generated by consultants, Tender evaluation, Project management, preparation of monthly report for management, Conduct progress review meetings and manage project management team.

Main Projects Component:
- Water well drilling, completion& Testing
- Completion of Deep Wells as Injectors and Observation Wells
- Development of Surface Water Injection Facility
- Injectivity & Interference Study

Objectives of Project:
- To establish the Injectivity and conductivity of Fatehgarh reservoir with an objective of pressure maintenance across the Mangala/NA fields
- Establish surface facilities design parameters, and injection water quality and compatibility with formation water.
- Deepwater Thumbli aquifer deliverability studies with respect to sustained water production requirements, once the production starts
- Study the Interference/effect on shallow fresh water aquifer with respect to water production from deepwater aquifer.
- To collect uncontaminated water sample from Thumbli and Fatehgarh aquifers through deep wells.

October 2002- March 2004
Cairn Energy India Pty Limited

Manager-Projects
Gauri Gas Field Development ($ 31 million),
Suvali, Surat, India.

Job Description: Responsible for Project conceptualization, Front End Engineering, Managing Detailed Engineering, Managing EPIC Contract, Tender specification & document preparation, Review of design documents generated by consultants, Engineering, Tender evaluation, Project management, preparation of monthly report for management, Conduct progress review meetings and manage project management team.

Main Projects Component:
- 4 legged Jacket
- Top Side with Gas processing facility, Pedestal Crane, Helideck, Scrapper receiver/ Launcher
- 5.2 Km 12" Sub-sea Pipeline
- Onshore Gas Processing and Compression Facility.

JACKET Fabrication & Installation: The Jacket fabrication and installation was done in fast track to facilitate the drilling as the rig was already in the field.

Gauri-A 4 legged Jacket was constructed at Nippon Steel between Jan to March 2003. The steel was free issued to Nippon Steel by Cairn Energy. The detail design was carried out by JBTI Bangalore under Cairn contract. Steel for Jacket were located in UK, Dubai and Singapore and shipped to Nippon Steel Batam Indonesia in Time. Jacket transportation engineering carried by Asian Energy Singapore. The Jacket Transported by Britoil Singapore. The Jacket was installed in 7 days by Sea Way Heavy Lifting, Netherlands under my direct supervision.

Pipeline Engineering, Procurement & Installation: Pipeline Engineering is carried out by Aker Kvaerner E&C, Singapore. The line pipe material is procured from M/s Tenaris, Tamsa, Veracruz Mexico directly by CEIL to cut down the cost. The line pipe material transported to Ras-Al-Khaimah for corrosion and weight coating. The coating processes for 5500 m of line pipe were completed in week's time and it was delivered in Gauri Field in first week of Jan 2004. The pipe lay was completed in 7 days by HHI using HD-2500 Derrick cum lay barge.

TOPSIDE Fabrication, Installation & Commissioning: Topside engineering, procurement and fabrication were completed in record time of 8 months and 1 week at Lamprell Dubai. It sailed out of Dubai 20 Feb 2004. The Installation and commissioning of topside completed in 2 weeks. The first Gas achieved on 19 March 2004. The Hook-up & commissioning was completed in record of 10 days.

October 2001-September 2002
Cairn Energy India Pty Limited

Construction Manager
Lakshmi Gas Field Development ($ 78 million),
Suvali, Surat, India.

Job Description: Posted at Work Site to Supervise the Job carried out by M/s Clough Offshore Division, Australia.
Overall responsibility to supervise the job carried out by a Contractor to complete the project safely and timely. Responsibilities included to organise daily review meetings, monthly meetings, implementation of HSE aspects, follow up & interact with Contractor on day today basis, provide technical clarifications to contractors TQ's, deal with local regulatory authorities etc.

Responsible for construction & installation of:
* Installation & Commissioning of 4 Km of 24" pipeline for Gas and 4 " for Treated Water disposal.
* Installation of Onshore gas processing and compression facility which included;
a) Terminal area b) Slug catcher c) Gas-Gas exchanger d) TEG regeneration package e) Dew Point Compression Unit f) LT separator g) Metering Skid, Gas Chromatograph and flow computers h) Gas Compressors i) Loading Gantry j) Tank Farm for condensate storage.
k) All associated Civil& Structural Works including piling, Heavy Foundations, Pipe racks, Compressor house, Control Room, Fire water reservoir and pump house etc.
l) All associated piping, electrical and instrumentation works.

Dec 2000 – September 2001
Cairn Energy India Pty Limited

Construction Superintendent
Ravva Satellite Gas Field Development ($ 40 million),
Ravva Terminal, Surasaniyanam, Andhra Pradesh, India.

Job Description: Posted at Work Site to Supervise the Job carried out by M/s Clough Offshore Division, Australia.
Overall responsibility to supervise the job carried out by a Contractor to complete the project safely and timely. Responsibilities included to organise daily review meetings, monthly meetings, implementation of HSE aspects, follow up & interact with Contractor on day today basis, provide technical clarifications to contractors TQ's, deal with local regulatory authorities etc.

Responsible for construction & installation of:
* Jacket & Piling for RH Platform
* Tripod, 4-slot gas platform with minimum facilities like Helideck, Pedestal Crane, Production manifold, separators.
* Installation of 20 Km of sub sea infield pipelines & risers for Gas and Water Injection Pipeline.
* Installation of Onshore gas processing and compression facility which included;
m) Terminal area n) Slug catcher o) Gas-Gas exchanger p) MEG regeneration package q) Dew Point Compression Unit r) LT separator s) Metering Skid, Gas Chromatograph and flow computers t) Gas Compressors u) All associated Civil& Structural Works including piling, Heavy Foundations, Pipe racks, Compressor house, Control Room etc.
v) All associated piping, electrical and instrumentation works.
w) Onshore pipeline and its hydro testing.

June 1997 – Nov 2000
Cairn Energy India Pty Limited, Chennai

Principal Projects Engineer

Job Description:

Responsible for Project conceptualization, Tender specification & document preparation, Review of design documents generated by consultants, Engineering, Tender evaluation, Project management, preparation of monthly report for management.

Following projects handled during above duration:

- Effluent Treatment Plant- EPIC Contract ($ 1.5 million)
- Produced Water Handling Project ($ 250K)
- Gas Turbine Generator – 2 X 2.5 MW- Construction and Installation of Civil, Mechanical, piping and E&I components ($ 200K)
- Helipad Construction for Offshore Operations ($ 175K)

- Construction of Crude Oil Storage Tank- Floating Roof, 79 m diameter.-EPIC Contract o Cathodic Protection for Crude Oil Storage Tanks.
- Engineering of Civil components for Water Injection Upgrade project, Third Stage Gas recovery, Associated Gas Compressor.
- Construction of doghouses on offshore platforms.
- Blasting & Painting of offshore Platforms, o Mechanical Instrument Workshop.
- Sewerage System for Ravva Oil & Gas Terminal & Living Quarters.
- Minor & Major Buildings.
- Public Water Supply Scheme and Canal re-alignment work for local community.
- Construction of Roads - 100 Km-Local Community Development

Apr' 1996 - May 1997
Cairn Energy India Pty Limited
Senior Projects Engineer

Supervised construction of onshore crude oil process facility executed by Hyundai Heavy Industries Ltd., South Korea worth of US $ 100 million.

The project consisted of:
* Construction of 3 Nos. of crude oil storage tanks(65 mts. dia)
* Heavy machine foundations
* 9000 nos. of pre-cast concrete & stone column piles
* Control room
* API Separator
* Cross country pipelines.
Offshore construction:
* Hydro testing of sub-sea pipelines

Aug 1995 - Mar 1996
Punj Lloyd Limited, New Delhi

Sr. Engineer
Job Description:
Ravva Oil & Gas Field Development Project
Punj Lloyd Ltd. was awarded onshore civil construction job.

Overall supervision of following works:
* Cross Country Pipeline
* Stone Column Piling
* Pre-cast Concrete Pile
* Pile Caps/ Heavy Machine Foundations
* Construction of Tank Farm

Dec 1992 – Jul 1995
WAPCOS(Govt. of India), New Delhi

Assistant Project Engineer

Responsible for following:
* Designed Sewerage Network for Nashik & Jalgaon city.
* Feasibility Report for Godavari Action Plan for Ministry of Environment and Forest.

Jan 1992 – Dec 1992
Vij Constructions, New Delhi

Project Engineer
Job Description:

In-charge for Re-construction of Imperial Hotel. A time bound project worth of $1 million.

Sep 1988 - Jan 1992
Chawla Techno Construct Ltd, New Delhi
Engineer
Job Description:
* Turnkey Construction of Chancery Building for Royal Nepalese Embassy at New Delhi, India.
* Construction of 5 Star Super deluxe Hotel Rajputana Palace Sheraton Hotel for Sheraton Group at Jaipur, India.

EDUCATION - Technical 1984 –1988
Civil Engineering

Graduate in Civil Engineering (First Class with Honours) in 1988
From Thapar Institute of Engineering & Technology (Deemed University), Patiala, Punjab, India.

TRAINING/ COURSES
1. "Basic Petroleum Engineering Technology" from OGCI-PETROSKILLS at HOUSTON, USA (2004).
2. "Project Management" from Singapore Institute of Management at Singapore (2000).
3. "Human Relations Skills & Technique" from Singapore Institute of Management at Singapore (2000)
4. "Managing Projects Well" from Singapore Institute of Management at Singapore (1998)
5. "Oil Spill Containment" Workshop from AMOSC, Australia(1996)
6. "Survival at Sea" course from AMET, Madras
7. 'Oil Spill Containment' Workshop from EARL & OSRL Global Alliance (Singapore) at Pattaya Thailand (2001)
8. "Offshore Pipeline Design & Construction" workshop from IBC at Kuala Lumpur (Malaysia) (2001)

View contact information...
«« previous resume next resume »»
Search Results (Resumes 2151 to 2200 of 3118)Go to Search Parameters...
Brief Description
I have a three years experience as an auto electrician and heavy equipment mechanic for Trident Transport Company in Abu Dhabi. I am looking for same kind of job in Abu Dhabi or in Europe, like Netherlands, Belgium or Germany.
I have extensive experience in various disciplines associated with electronics. For the past two and a half years I have been employed on a semi-submersible drilling rig. In this position I worked with various PLC controls, level controls, Seimens Step5 and Step7 control trees.
Logistics, Procurement and Materials Manager (Supply chain)
A solid background in project controls, project coordination, project scheduling, and records management with over twelve years combined experience in these areas.
Procurement Manager with over 15years Multidisciplinary experience, providing Managerial, Engineering, Information Technology for onshore/offshore rigs and office operations in Procurement, Warehousing and Logistics.
I am working as a Mechanical/HSE Engineer in ADCOP (Abu Dhabi Crude Oil Pipe line Project) in Abu Dhabi, UAE. I have also got the training in Oil and Gas processing Plant for three months and also worked as a maintenance and sales engineer in SATAKE Corporation, JAPAN Pvt. Ltd.
A project management and business development professional with extensive experience in bid management through to contractual completion. An impressive record in winning new business, and managing and completing projects on time and under budget.
Mechanical Engineering Diploma holder with BGAS Painting Inspector Grade 2 Certification, working in Saudi Arabia-(Saudi Aramco contractor) as a Painting Inspector in pipeline construction field (Gas Wells, Manifolds, Trunk lines, GOSP & Gas Plants, etc).
An experienced security professional with 24 years of strong corporate security and law enforcement qualifications who has demonstrated a high level of success in a variety of significant and highly critical assignments in a fast paced environment. Also has an impressive track record of hands-on exp
I am a mining engineer and also has a masters degree in urban and regional planning.
QUALFIED FITTER, EXPERIENCE ON DOSERS, CATERPILLARS, HITACHI LAODERS, REPARI AND INSTALL HOWDEN, EAGEL, SAMURI, MONO AND SAMSON WATER PUMPS, REPAIRED AND MAINTAINED LOCOMOTIVES AT TRANSNET.
Summary An enthusiastic, Postgraduate Civil engineer with 2 years and 2 months of experience in the design, Engineering and Construction of Industrial, infrastructure and Multi storied Buildings, Eager to learn new technologies
recent chemical engineering graduate with 2 years of work experiences including R&D and industrial experiences. Experiences in pilot plant operations, bench tests, process engineer
I am a self-motivated, determined and organized individual who strives to perform any task to the best of my abilities. I have a strong background in 2D and 3D drafting, design and modelling and am capable of producing accurate and high quality drawings in a fast paced environment.
He has more than 25 years of experience; from his current work in hydrogeological and hydrochemical assessment, environmental monitoring, and capacity building. He has managed many projects as well as acted as team leader on various project components.
NEBOSH Certificate availabe. About 9-10 years practical experience in construction, operation, maintenance as HSE Advisor and Coordinator.
Construction HSE Manager with 18 years of experience encompassing the areas of Safety Adviser through to Corporate HSE Manager. Formerly a Senior ranking Fire Officer (nine years experience). Five year apprenticeship served as a mech. engineer. Degreed engineer with both off-shore and on-shore exp.
Qc inspector mechanical or Welding inspector
Mechanical Engineer with over 7 years experience in QA/QC of mechanical construction activities, Welding, Painting, NDT, Insulation, Implementing QA/QC procedures, Auditing
I'm a Site Engineer with 3+years of Exp as a Site Engineer, Roads at KMC Constructions Ltd. , India.
Software Developer .NET, Java SQL
To be associated with a professional organization, which will provide an opportunity for the growth of my career and grant scope, to utilize my knowledge and skills towards the success and growth of the organization.
I have an overall experience of 17 years out of which 11 years in Oil & Gas Development Projects. Presently I am working as Group Project Engineer in a Major British Exploration & Production Company in Edinburgh UK. Following are my current responsibilities:
Contracts Manager
Entry level geologist, mining, environmental science
geology, geotechnical, geological engineering, geology and environment, hydrogeology, prospection and groundwater abstraction, geohazards, geological mapping, interpretation of seismic reflection profiles, stratigrafic, sedimentology. Very experience in topography, cartography, mapping and autocad
All kinds of Fault finding in the Tower crane & Hoist from electrical department
Extensive Autodesk AutoCAD and Autodesk Inventor Professional Experience
• Extensive experience managing Document Control deparments within Engineering, Construction and Petrochemical Industries.
Project Management / Production Control
B.E.(ECE) in College of Engineering, Guindy, Anna University, Chennai having experiences in working in Integrated Systems Laboratory (Anna Univ) on various projects and interested in taking up a career in Analog VLSI Design
Site Construction Manager Oil and gas Industry. Over 20 years experience. Process plants, facilities and pipelines.
Project control engineer with experience in planning and cost engineerig fields.
A self-directed, high organized individual who is able to easily identify and achieve priorities. Significant broad based experience in the areas of facilities planning, production, engineering, maintenance, environmental, staffing, and safety. Excellent communication and technical report writing
Marine Engineering, Risk Assessment, Lloyds Surveyor, Project Management FPSO Projects worldwide
Extensive and progressively responsible hands-on management experience.
Currently employed as the primary Electrical Engineer. Engaged with improving safety, training, documentation, and implemeting preventive maintenance goals.
Seeking an opportunity in the oil and gas industry to develop and utilize expertise in electrical/electronics, control, instrumentation and/or automation as a new entry or trainee engineer.
•Nebosh International certificate in Occupational Health and Safety , Membership Examaination of The Institution of Fire Engineers UK., Fire Officer course from National Fire Service College Nagpur India
Welding Engineer
I graduated in July 2006 with a BE Honours Degree in Manufacturing Engineering. I have over two years’ experience as a Process/Project engineer in a multinational company. I have completed courses on DOE & PDA and Project Management. Proficiency with Microsoft Word, Excel, PowerPoint, AutoCAD,etc
BE,MBA graduage having 13+ years experience in Sales & Marketing of Engineering, Flow Control & Instrumentation Process Products
i have complited a MSc degree from pune univeristy,worked as a geologist in geotechnical field,wel known to GPS ( Trimble Geoexplorer 3 )
A proactive leader with extensive reliability centered maintenance management and hands-on experience in the repair, overhaul and troubleshooting of mobile equipment, initiate change and reengineering of quality improvement processes while maintaining a positive, safe and productive environment.
With more than ten (10) years of extensive experience and knowledge in Pipe stress calculation and support design of oil & gas, petrochemical, refinery, chemical, LNG, LPG, onshore, nuclear power plant and subsea piping projects.
M.Sc. Environmental Engineering and B.Sc. Civil Engineering holder seeking more experience. Although I do not have long working experience, I assure you that I am a keen learner and will work hard for the department if I am selected.
Over 20 Years experience in International and Domestic assignments in the Electrical and Instrumentation Fields. Assignments internation-ally have been in Project/Construction management, Supervision, QA/QC and commissioning. Project experience is diverse and in-cludes mining and extraction/ recov
In-service / shutdown inspection of most of the static equipments in a plant, such as pipe works, pressure vessels, hydrogen crackers, reactor vessels, storage tanks, reformer tubes, risers, topside structures, well head parts, valves, etc. , Inspection of all plant construction related activities
Supervision, planning, scheduling, coordination, maintenance (prevantive & breakdown), budgeting/forecasting, optimum inventory management, resource development & deployment, utilities etc.
Engineering graduate experienced in installation ,pre-commisiioning ,commissioning
First   1   2   3   4   5   6   7   8   9   10   11   12   13   14   15   16   17   18   19   20   21   22   23   24   25   26   27   28   29   30   31   32   33   34   35   36   37   38   39   40   41   42   43   [ 44 ]   45   46   47   48   49   50   Next   Last
Seach Parameters

Change search parameters...
CATEGORIES: Engineering/Technicians;
INDUSTRIES: Construction;
Change search parameters...
Keywords: (e.g. mining engineer)Find results with:
Save this search parameters...
Post job with this search parameters...
Frequently Asked Questions
What's the most effective way to perform a search?
Go to Advanced Search
1. Select 'Industries', 'Categories', 'Education', and 'Experience' fields. Click 'Search' and look through results.
2. Enter one or two of the most important keywords. Click 'Search' and look through results.
3. To search within results add more keywords.

How can I find resumes that contain specific exact phrase?
To search for an exact phrase, just put quotation marks around two or more words, for example "mining engineer". Use this feature to narrow your results or to find words that can be typed differently, for example AutoCAD "Auto CAD".

More Frequenly Asked Questions...
Employer's Center


» Employers Home
» Feedback
» Help

» Post Jobs
» Edit/Delete Jobs
» Search Resumes
» Resumes By Email

» My Account
» Log In

» Log Out
 
©1999-2009 Misco Jobs. All rights reserved.  Contact: support@miscojobs.com