33 years with Fluor Corporation:

Over (33) years Mechanical & Civil Exp in QA/QC & Construction Management from $65. Million to $3.2. billion Projects; Including nuclear piping; documentation verification; system verification; hydrostatic & pneumatic testing of code & non-code piping systems; various types of inspection & testing of code & non-code piping systems; welding, piping & structural; pipe fabrication and installation; working knowledge of ASME Sections I & IX, ASME B31.1 & B31.3, ASME Sec.V, ASME SEC.VIII and AWS D1.1. Along with API – 653, & 650
Develop & Writing QA/QC Programs, Site Procedures Manuals, Project Execution Plans & Welding Plans for Projects.
Review/Approve Contractors QA/QC Programs & Welding Programs.
Civil Experience Include Concrete Testing & Soil Compaction Testing and Asphalt Testing.

TRAINING & CERTIFICATIONS:
Level II RT Film Interpretation
Level II Liquid Penetrant
Level II UT Thickness
Level II B31 Visual Inspector
Prolog Management System
Computer Knowledge- Microsoft word, Excel & PowerPoint

FLUOR MIDEAST LIMITED
AUG-2006 to Nov-2007
SITE QA/QC MANAGER
RASGAS
LNG PROJECT
RAS LAFFAN, QATAR
PROJECT COST: 3. 2 Billion

Assigned to the RasGas Project as a Site Quality Manager.
Responsible for writing and implementing a QA/QC & Engineering plan for Mechanical, Civil and Electrical for the Fluor self perform work.
The project Consisted of NewCondensate Storage Tanks, New LNG Storage Tanks, & Piping for Both and New 20,000 sq. ft Control Room and Sub Stations.
Responsible for Review of Contractors QA/QC Programs and Personnel for Approval, Monitoring of Contractors Compliance to RASGAS Specifications and Procedures.
Managing Between 15 to 30 Multi-discipline Fluor inspectors through out the Project. Conducted Scheduled Audits on contractors Quality Plans, ITP's and Method Statements for performance and compliance to Industry standards and client requirements, Monitored Daily inspection Activities along with Training to Multi disciplined inspectors as necessary.
Filled in for the Site Manager when he was away on R&R and Company Business.

FLUOR POWER SERVICES
MAY-2005 TO PRESENT
QA/QC MANAGER
PROGRESS ENERGY
FGD PROJECT
ROXBORO,N.C.

Establish and Supervise an Engineering & Quality Program for a $350. Million FGD Project.
Responsible for Writing and Implementing a QA/QC & Engineering Plan for Mechanical, Civil, and Electrical for the Fluor Self Perform Work. Reviewed Sub- Contractors QA/QC Plans for Acceptance
For Mechanical, Electrical, and Civil work for the project. Scheduled all NDE Activies for Mechanical, Civil and Electrical Testing. Conduct Quality Audits for Compliance to Project and Fluor Requirements.
Conduct Training, Qualification and Certification of Field Personnel, Review all Site and Shop Drawings
For Correct Specifications for the Project with the Fluor Engineers for acceptance or rejection, and issue comments back to sub-contractors for Resubmittal to Fluor for Acceptance. Further Responsibilties include the Supervision of Fluor Inspection Personnel, and Conducting routine inspections and surveillance of construction work activities as required to achieve contract Quality Requirements PER: ASME: B31.1, ACI-301, AWSD1.1, and ASME SEC: IX

FLUOR DANIEL
APRIL-2005 to MAY-2005
QA/QC MANAGER
PROGRESS ENERGY
SUTTON PLANT
WILMINGTON, N.C.

Perform Quality surveillance & visual inspections for the 1 month outage of the #3 Boiler tube replacements for code compliance. Duties included Managing 24 welders and 24 pipe fitters for the day and night shift. Scheduling and monitoring of all work activities and visual inspection of 209 tube welds, weld mapping and scheduling all NDE act ivies and final sign off of R-1 reports with the Authorized Inspector.

FLUOR ARABIA LTD.
DEC-2004 to APRIL - 2005
QA/QC MANAGER
YANPET-DBN-1 PROJECT
YANBU, SAUDI ARABIA

Construction Management Project:
Responsible for Management of the QA/QC Program for the YEP-DBN-1 De-Bottlenecking outage.
Reviewed the QA/QC plans for Acceptance for all contractors involved in the outage, from WPS's & PQR'S for welding to inspection & test plans for Mechanical, Electrical, and Civil activities.
Responsible for the implementation of the ASME Quality Program including welding and NDE activities.
Further responsibilities included the Supervision of Fluor inspection personnel, and conducting routine inspections and surveillance of construction work activities as required to achieve contract Quality requirements.

FLUOR FEDERAL SERVICES
JULY-2004 to DECEMBER- 2004
QA/QC & SAFETY MANAGER..
CETAC II MANAS AIR BASE
TEMPORARY CANTONMENT PROJECT
BISHKEK, KYRGYZSTAN

Construction Management Project:
Establish a Quality Control & Safety Program for (USACE) and (USAF) for a Permanent housing project for APP:1,000 Military personal, Review Contractors QA/QC plans for Mechanical, Civil and Electrical for Acceptance. Review All Site and Shop drawing and USACE Specifications for the project with the Fluor Engineers in Greenville,S.C. for acceptance or rejection, and issue comments back to Sub Contractors for resubmittal to Fluor for acceptance.
DATA entry in PROLOG of all Submittal items from sub contractors, Materials, Drawings, Specifications Equipment, Concrete Mix Designs, Asphalt Mix Designs, Low Voltage & High Voltage Designs and ECT. Once the Submittals are accepted by Myself and Fluor Engineers they are then submitted through PROLOG to United States Army Core of Engineers for Approval.

FLUOR /FEDERAL SERVICES
FEB-2004 TO MAY-2004 MGR.
QA/QC MGR.
OPERATION IRAQI FREEDOM
CAMP COOKE/TAJI, IRAQ

Construction Management Project
Duties included, Site Engineering MGR. & QA/QC MGR. and Contract Manager for 5 Major contractors for the 2,451 units of permanent housing for the U.S. ARMY in IRAQ. Review and accept contractors QA/QC plans for Mechanical and Civil work for the project. Testing Activities Per: British and ASTM standards for Asphalt and Sieve Analysis of Aggregates for base coarse material and CBR testing prior to Asphalt placement.
Mechanical activities PER: ASME & British standards for all plumbing and under ground piping installations. Reviewed all contractors daily reports and testing actives PER: FLUOR Specifications for the project, Issued some NCR'S where needed to contractors, submitted weekly reports back to Greenville, S.C. for review on each weeks progress. Total contract for the 5 contractors was over $100.million

FLUOR/FEDERAL SERVICES
OCTOBER-2003 –DECEMBER-2003
QUALITY ENGINEER
OPERATION IRAQI FREEDOM

Construction Management Project
Traveled to 5 Middle East countries and 3 East Europe countries to visit 15 different contractors for a $100 million dollar project for the USAF in IRAQ for 2,451 units of permanent housing for 10,000 military personal in several different sites in IRAG. The Purpose of the visit was to look at the contractors on FLUORS bid list to verifey their specifications for building of the housing verses U.S. specifications and for a over all QUALITY ASSURENCE look at fabrication of these Contractors Facilities and return to GREENVILLE, S.C. in December to review the bids verses my visit to all of these contractors and award the contracts to 5 of the contractors.

FLUOR/FEDERAL SERVICES
NOVEMBER 2002 – OCT-2003:
QA/QC & SITE ENGINEERING MGR.
OPERATION ENDURING FREEDOM
OPERATION IRAQI FREEDOM
THUMRAIT, AIR BASE, OMAN

Construction Management Project:
Establish and Supervise a Engineering & Quality program for the (USAF) for a (2,080ft) x (980ft) concrete parking ramp for USAF's B-1 Bombers and a (14,000ft) x (100ft) Asphalt parallel taxi way to the exiting OMANTI airport runway. The project consisted of ASTM & BRITISH STANDARDS. The Concrete parking ramp was a combination of both ASTM & British standards for 5,500-psi concrete. Direct magament of three contractors, OMAN GULF, L.L.C. Thumrait Oman, Asphalt plant and Aggregates for both concrete and asphalt & base coarse materials. READYMIX ABU DHABI, ABU DHABI,U.A.E. for the concrete plant operation, reviewed and accepted their mix designs for each operation & QA/QC plans for testing and sampling of aggregates on a daily and weekly basis for compliance to site specifications for ASTM, BRITISH STANDARDS. Third party material testing: TARMAC ALAWI, L.L.C. Muscat Oman, reviewed & accepted their QA/QC plan, scheduled all testing of Concrete, Asphalt, Sub-base, & base coarse material PER: ASTM & BRITISH STANDARDS. Testing activies, Sieve analysis of aggregates, Slump testing of concrete, air-entrainment, compressive strength of concrete cylinders & beams.
Asphalt: Daily extraction method, for bitumen content, voids in mix, specific gravity, and sieve analysis of aggregate after extraction & field (CBR) testing. Contracts manager for 3 Civil contractors total contract award for 3 contractors was $67.million

DUKE/FLUOR DANIEL
FEBRUARY 2002-NOVEMBER 2002
QUALITY ENGINEER
DEMING ENERGY FACILITY, DEMING, NEW MEXIC0

Construction Management Project:
Established and Supervised a Quality Assurance program and record keeping system for a 450 MW: CO –Generation Facility to meet the requirments of ISO 9000 in the following areas civil, mechanical, piping and welding. Reviewed all site work packages and generated weld instructions to sub- contractors to ensure code and site compliance as this was a construction management project. Contract Manager over two major contractors for Project mechanical & electrical total of two contractors was $247. Million.

DUKE/FLUOR DANIEL
March 2001 – FEBRUARY 2002
Quality Engineer Construction Manager
Urquhart Repowering Project, Beech Island, South Carolina

Generated all ASME weld travelers required for ASME Section I work for 450 MW Co-Generation Facility. Contacted and scheduled weekly visits with Site (AI). Performed daily weld inspections and assisted craft and engineering in technical areas related to HRSG'S and welding. Assisted other inspectors in daily activities related to high energy piping (PWHT, XRAY, Pre-Heat, etc.) Monitored sub-contractors to ensure a quality product was given to SCE&G at job completion, Tank Fabricator, Painters, and Insulators. Witnessed Hydrostatic testing of piping systems. Night Shift Construction Manager /supervised all activities for Piping, Electrical, Civil., and sub-contractors for 6 months.
Performed shop visits to local pipe fabrication shops when required to ensure quality and schedules were being met.

DUKE/FLUOR DANIEL
April 2000 – February 2001
Quality Engineer/Nightshift Construction MGR.
Odessa -Ector Power Project, Odessa, Texas

Responsible for NDE and welding activities for new 1,000MW co-generation facility. Establish and supervise a quality control program meeting ANSI B31.1, B31.3 and AWS.D1.1 requirements. Review and identify site-welding requirements to ensure code compliance. Schedule work on all NDE sub-contractors. Ensure appropriate ASME code certification of all sub-contractors. Monitor Duke/Fluor Daniel and all sub-contractors for weld rejections and appropriate corrective actions to maintain an acceptable rejection rate. System walk down and punch out to ensure systems are complete and fabricated per P&ID and current drawings.
Construction Manager/Quality Engineer Nightshift for 6 months Supervised Duke Fluor Daniel and All Sub Contracrors for Mechanical, Electrical & Civil Activities for the Project.

FLUOR DANIEL
October 1999 – December 1999
Quality Engineer
Proctor & Gamble, Jackson, Missouri

Perform visual welding inspections of piping systems for compliance to applicable codes and job specifications. Coordinate activities of NDE sub-contractors. Weld map systems to assure necessary NDE is completed prior to hydro testing and clear packages for hydro testing.

FLUOR DANIEL
June 1999 – October 1999
MECHANICAL ENGINEER/Quality Engineer II
S.K. Corporation, Ulsan, Korea

Perform quality surveillance and monitoring of construction work for code compliance. The work included inspection of piping, welding, structural steel, mechanical and vendor's shops. Reviewed radiographic film for compliance to applicable codes. This was a construction management job.

FLUOR DANIEL
March 1998 – May 1998
QUALITY ENGINEER II
Union Carbide, Taft, Louisiana

Responsible for QA/QC NDE and welding activities for new Olefins Modification Project. Activities include welder qualification testing of all Fluor Daniel and sub-contractors per ASME Section IX & B31.3 and AWS D1.1 welding specifications. Review all sub-contractors welding procedures for approval. Schedule NDE contractors for RT, PT and UT inspection, per ASME B31.3 compliance. Review site welding requirements to ensure code compliance to B31.3 and AWS D1.1. Preparation of Quality documentation and daily activities reports. Monitor Fluor Daniel and sub-contractors work force for weld rejections and appropriate corrective actions to maintain an acceptable rejection rate.

FLUOR DANIEL
December 1997 – March 1998
QUALITY ENGINEER II
Wellman Plastics, Inc., Bay St. Louis, Missouri

Responsible for all welding and mechanical inspections related to Fluor Daniel and sub-contractors for Wellman Project. Other activities and responsibilities included pre-hydro walk downs and acceptance as per ASME B31.1. Final P&ID walk down of piping systems and punch listing prior to turnover to Wellman. Also review for approval welding procedures for sub-contractors and off site vendors.

FLUOR DANIEL
January 1997 – September 1997
MECHANICAL ENGINEER/QUALITY COORDINATOR
EQUATE Petrochemical Complex, Ahmadi, Kuwait

Lead inspector responsible for coordinating and overseeing all inspections and activities of 19 Fluor Daniel Inspectors. Witnessed all hydrostatic, pneumatic and flushing inspections. Review test reports to ensure accuracy and address any discrepancies before final turnover to EQUATE. System walk down and punch out to ensure all lines are complete and fabricated per P&ID and isometric drawings. Daily field inspections and observations of all ongoing mechanical work.

FLUOR DANIEL
August 1996 – December 1996
QUALITY ENGINEER II
Shell Chemical, Norco, Louisiana

Quality supervisor on night shift. Review site welding requirements to ensure code compliance to B31.1, B31.3 and AWS D1.1.a. Performed visual and NDE inspections on piping components for F-140 furnace & debottlenecking shutdown. Monitor Fluor Daniel work force for weld rejections and appropriate corrective actions to maintain an acceptable rejection rate. Supervise over weld tracking program on night shift. Worked hands-on with engineers on all problem areas and weld test shop supervisor.

FLUOR DANIEL
April 1996 – May 1996
QUALITY ENGINEER II
Rohm & Haas Chemical, Deer Park, Texas

Weld test shop supervisor on night shift, performed visual & NDE testing PT and UT on all project piping during shutdown. Inspections of all mechanical work for shutdown and pre-shutdown work. Scheduled all NDE work for sub-contractors. Review site welding requirements to ensure code compliance to B31.1.

FLUOR DANIEL
May 1995 – May 1996
QA/QC Manager
Chevron USA, El Segundo, California

Quality Manager in charge of a 48MW Co-generation facility. Establish and supervise a quality control program meeting ANSI B31.1, ANSI B31.3 and AWS D1.1 requirements. Review and identify site-welding requirements to ensure code compliance. Schedules work for all NDE sub-contractors. Worked with project management and client to resolve and correct problem areas. Ensure appropriate ASME code certification of all sub-contractor welders. Monitor Fluor Daniel and General Electric work force for weld rejections and appropriate corrective actions to maintain an acceptable rejection rate. Solely responsible for all civil and mechanical quality compliance.

FLUOR DANIEL
1994 – 1995
QA/QC MANAGER
Unocal, Wilmington, California

Establish and supervise a quality control program meeting ANSI B31.1, B31.3 and AWS D1.1 requirements. Review and identify site-welding requirements to ensure code compliance. Schedule work for all NDE sub-contractors; work with project management and client to resolve problem areas. Ensure appropriate ASME code certification of all sub-contractor welders. Monitor Fluor Daniel work force for weld rejections and appropriate corrective actions to maintain an acceptable rejection rate.

View contact information...
«« previous resume next resume »»
Search Results (Resumes 1801 to 1850 of 2820)Go to Search Parameters...
Brief Description
A Mechanical Engineer and an MBA with years of progressive experience in in commissioning, procurement and project engineering of power plant renovation & modernization contracts
Mechanical Engineer with over 7 years experience in QA/QC of mechanical construction activities, Welding, Painting, NDT, Insulation, Implementing QA/QC procedures, Auditing
Maintenance Manager Engineer Middle East Experience, Looking for work in UAE
Project Management, Oil & Gas Industry, Civil Costing, Planing and Estimation
My experience includes the Superintendent level managing maintenance crews for a nickle smelter. I have a trades background of 25 years which includes millwright; welding and machinist. I am currently working for a large Nickel Project overseas and have extensive experience with RCM.
I have an overall experience of 17 years out of which 11 years in Oil & Gas Development Projects. Presently I am working as Group Project Engineer in a Major British Exploration & Production Company in Edinburgh UK. Following are my current responsibilities:
Handling key customers like Saudi Aramco, Sabic Affiliates, Saudi Electricity Company, Saline Water Conversion Corporation, etc in the western region of Saudi Arabia related to Sealing Solutions.
I have 25 years of multi disciplined, design, engineering, and project management experience with very strong automation skills. I am highly experienced with specialize, automated process equipment systems for Oil & Gas, Petrol Chemical, Power Generation, Semiconductor,Pharmaceutical,Water & Waste
BS in Mechanical Engineering from India, 36 years of Petrochemical industrial Experience in NDT & Vibration analyses field.
To obtain a Full Time position as an Electrical/ Hardware Engineer.
• Extensive experience managing Document Control deparments within Engineering, Construction and Petrochemical Industries.
Site Construction Manager Oil and gas Industry. Over 20 years experience. Process plants, facilities and pipelines.
Project control engineer with experience in planning and cost engineerig fields.
A self-directed, high organized individual who is able to easily identify and achieve priorities. Significant broad based experience in the areas of facilities planning, production, engineering, maintenance, environmental, staffing, and safety. Excellent communication and technical report writing
I have worked in the Petrochem/Oil and Gas industry for 20 years. Vast knowledge of all support qualifications, document control, purchasing, expediting and subcontracts work.
Expertise in Project Engineering, Cadd Management & related fields.
Fully experienced HSE Coordinator,Supervisor,Advisor comfortable in Oil&Gas,Construction and Military environments
ELECTRICAL ENGINEER
Marine Engineering, Risk Assessment, Lloyds Surveyor, Project Management FPSO Projects worldwide
Lead construction engineer (structural, methods, lifting, marine)
Currently employed as the primary Electrical Engineer. Engaged with improving safety, training, documentation, and implemeting preventive maintenance goals.
•Nebosh International certificate in Occupational Health and Safety , Membership Examaination of The Institution of Fire Engineers UK., Fire Officer course from National Fire Service College Nagpur India
i have complited a MSc degree from pune univeristy,worked as a geologist in geotechnical field,wel known to GPS ( Trimble Geoexplorer 3 )
A proactive leader with extensive reliability centered maintenance management and hands-on experience in the repair, overhaul and troubleshooting of mobile equipment, initiate change and reengineering of quality improvement processes while maintaining a positive, safe and productive environment.
Telecom Transmission Engineering, Computer and Electronics
With more than ten (10) years of extensive experience and knowledge in Pipe stress calculation and support design of oil & gas, petrochemical, refinery, chemical, LNG, LPG, onshore, nuclear power plant and subsea piping projects.
M.Sc. Environmental Engineering and B.Sc. Civil Engineering holder seeking more experience. Although I do not have long working experience, I assure you that I am a keen learner and will work hard for the department if I am selected.
In-service / shutdown inspection of most of the static equipments in a plant, such as pipe works, pressure vessels, hydrogen crackers, reactor vessels, storage tanks, reformer tubes, risers, topside structures, well head parts, valves, etc. , Inspection of all plant construction related activities
Supervision, planning, scheduling, coordination, maintenance (prevantive & breakdown), budgeting/forecasting, optimum inventory management, resource development & deployment, utilities etc.
Electrical Engineer, Six Sigma, Lean, Manufacturing
33 years Mechanical & Civil Exp in QA/QC & Construction Management form$65.Million to $3.2 Million Projects. EXP. All Codes , ASME, B31.1 B31.3 AWS, , NBIC, ASME Sec.V, ASME Sec.VIII API-650 &653. Develope & writing QA/QC Programs, Site procedures Manuals, Project exection plans & Welding plans
Over 25 years Quality Management Supervision experience in the Oil & Gas and Heavy Engineering construction.
More than 20 years E&I experience of Maintenance & Commissioning within the Oil & Gas Industry. Enjoy working as part of a team but I can also operate independently when required. Self-motivated, resourceful, adapt quickly to new working environments, easily integrate into multi-cultural operations
Planning / Project Controls Manager , PMP certification, Primavera 3.1 / 6 professional user, Civil Engineer, Cost Control and Claims experience
Project Manager/Construction Supervisor/Contracts Manager/Claims Manager/Cost Engineer/Construction Manager/Site Supervisor/Civil Engineer/Quantity Surveyor etc.,
Buyer, Purchasing Agent, 38 Yrs. Material Handling and Purchasing Experience
Project management, commercial management quantity surveying
Automation/Electrical/Instrumentation/Supervisor
Seven years experience in quality control and quality assurance, welding inspection, Nondestructive tests (RT, UT, PT& MT),destructive tests (tensile,bend,hardness, macroscopic, impact, corrosion,...), in the fields of (Pressure Vessels,Boilers,piping, steel structure , tanks & Pipelines) at gas &
Excellent experience, coupled with a strong quantitative and analytical background, makes me an excellent candidate
Quantity surveyor, estimation and land surveying works
Rotating Equipment Repair and Refurbishment of Rotors and other Internals of Compressors, Steam Turbines, Gas Turbines and Screw compressors. Over 10 years with OEM worshop as Works Manager of Service shop and Head of Technical Services. An ASME Authorized Global Training Instructor.
Geologist with good expertise in planning, follow-up and reporting of geotechnical and geophysical site-/soil-investigations.
To contribute strong background in project management, civil engineering, contracts and along with unique drive for excellence and success to your firm in a Planning & Control Engineer position.
Civil engineer having knowlegde and working exposure of AutoCad 2000 and Staad 2004
Construction Project Manager, Property Development Manager
Electrical and Instrumentation Technician/Engineer with significant experience in Construction, HUC and Maintenance in the Petrochemical and Oil & Gas Industries at Technician or Engineer levels for companies with several large development projects ongoing at once.
Self-motivated Draftsman proficient in AutoCAD and manual drafting with 750 hours of theory and 750 hours of hands on experience. Eager to contribute time and effort to benefit a respectable company. Responsible, hardworking and dependable.
Engineering/Operations professional with sixteen (16) years of experience managing multi-disciplined projects.
having 5 years experence by using cad tools such as proe catia associated with automotive\offhighway industries
First   1   2   3   4   5   6   7   8   9   10   11   12   13   14   15   16   17   18   19   20   21   22   23   24   25   26   27   28   29   30   31   32   33   34   35   36   [ 37 ]   38   39   40   41   42   43   44   45   46   47   48   49   50   Next   Last
Seach Parameters

Change search parameters...
CATEGORIES: Engineering/Technicians;
INDUSTRIES: Construction;
Change search parameters...
Keywords: (e.g. mining engineer)Find results with:
Save this search parameters...
Post job with this search parameters...
Frequently Asked Questions
What's the most effective way to perform a search?
Go to Advanced Search
1. Select 'Industries', 'Categories', 'Education', and 'Experience' fields. Click 'Search' and look through results.
2. Enter one or two of the most important keywords. Click 'Search' and look through results.
3. To search within results add more keywords.

How can I find resumes that contain specific exact phrase?
To search for an exact phrase, just put quotation marks around two or more words, for example "mining engineer". Use this feature to narrow your results or to find words that can be typed differently, for example AutoCAD "Auto CAD".

More Frequenly Asked Questions...
Employer's Center


» Employers Home
» Feedback
» Help

» Post Jobs
» Edit/Delete Jobs
» Search Resumes
» Resumes By Email

» My Account
» Log In

» Log Out
 
©1999-2008 Misco Jobs. All rights reserved.  Contact: support@miscojobs.com