Projects Exposure &Experience
* PETROCHENICAL PROJCET 02Years
* COMBINED CYCLE POWER PLANT 04 Years
* EFFLUENT TREATMENT PLANT 01Year
* COMMERCIAL & RESIDENTIAL BUILDINGS 03Years
* PUMPING STATION & PIPELINE 02Year
Career Work Summary
* Analyzing, Planning & Execution for Scope of work area assigned.
* To ensure satisfactory execution and consolidation of on site construction activities on time, within budget and according to specification.
* Involvement in Coordination, Implement, Updating of Method statements, QA & QC Plans & Construction Schedule.
* Manage and administer daily reports to ensure effective performance of all manpower and machinery resources involved in construction
* Raising material requisition, Inspection of material procurement as per the specifications. Ensure compliance with the stated quality requirements of the project.
* Maintain close liaison and good relationship with other subcontractor's personnel.
* Supervise subcontract work..
* Liaison with client representative and attend meetings as per demand of the job.
Personal Data
Nationality: Indian
Marital Status: Married
UAE Driving License: 377107 / A
Qualification: B.Tech (Civil) – Nagarjuna University.
Experience in Brief:
1) TECHNIP-COFLEXIP July 00-Till Date Abu Dhabi, UAE
INVOLVED IN FOLLOWING PROJECT:
Project: Sulfur Recovery Unit
Owner: Saudi Aramco Consultant: Technip Contractor: Technip Project value: 80 million Suadi Riyal Period & Place: July03Till Date. Riyadh, KSA
Civil Engineer
* In charge for execution civil works Amine Treating Units, Sour Water strippers & Sulfur Recovery units.
* Answering the clarification requests, issuing Site design modifications.
* Coordinating with client & subcontractor.
2) Al Jaber Energy Services (AJES) Feb 00 – June' Abu Dhabi, UAE
INVOLVED IN FOLLOWING PROJECTS:
a) Project: 180 MIGD Water Transmission System From Qidfa water & Power Plant to Al-Ain.
Owner: UOG Offsets, Consultant: Fitchner. Contractor: TechnipGmbh/Al-Jaber. Project value: 1.6 Billion UAE Durham's Period & Place: Jan 02- Till Date. Fujairah, UAE.
Senior Engineer
* In charge for execution of civil works Pumping Station—Booster, Main Pump, Electrical Buildings, Valve Pits, Instrument Pits, Surge Vessel, Compressor Foundation, Tanks & Underground Services.
* Excavation for the cross-country pipes.
b) Project: 600 KTA Boruge Petrochemical Project
Owner: Borouge Consultant & Main contractor: Bechtel. Contractor: AJES.
Project Value: 600 Million U.A.E Dhirams. Period & Place: Feb 00 - Dec 01 Abu Dhabi, U.A.E.
Senior Engineer
* In charge for execution of all civil works involved in utilities of the project. — Sea Water Basin, Plate Exchanger, Compressor Foundation, Fire Water Tank Foundation Equipment Foundations and Pipe Supports (20,000 cum)
* Excavation & backfilling for Underground services like Fire Water Line, Cold Water Line, Potable Water line, Sea Water Line, Oily Water Line accidentally oily line Electrical Trenches (20,000 cum).
* Paving 30,000 sqm & Roads - 5 kms
2) Delta Mechcons (I) Ltd Jul 96 – Jan 00 Maharastra, India.
INVOLVED IN FOLLOWING PROJECTS:
a) Project: 2x260 BPL Thermal Power Plant
Owner: BPl India Ltd. Consultant: Tata consultant. Contractor: Thoshiba, Japan.
Project Value: US $ 95 Million. Period & Place: May 99-Jan 00 Andhrapradesh, India.
Senior Engineer
* Executed civil works related Area Leveling (167 hectares) Excavation 6 lakh cum, Back filling 4 lakh cum.
* Planning & controlling movement of the equipment.
* Assigning the targets for the Junior Engineers & Foremen.
b) Project: 316 MW Thaweelah Combined Cycle Power Plant
Owner: ADEWA. Consultant: Fitchner Contractor: Bechtel Hitachi Zosen.
Project Value: US $ 81 Million Period & Place: Jun 98-Apr 99. Abu Dhabi, UAE
Senior Engineer
* In charge for civil works: Foundation for Gas & Steam Turbine, Compressor, Generator, Bypass & Main stack, Cable Trench, Pipe Supports, Underground Services Paving & Roads. (6000 cum)
* Planning & controlling the movement of the equipment.
c) Project: 172 MW Vijjeswaram Combined Cycle Power Plant.
Owner: A.P.S.E.B. Consultant: Tata Contractor: Sumitomo Corp. Japan
Project Value: IRS 430 Million. Period & Place: Jul 96 - May 98 Andhrapradesh, India.
Senior Engineer
* In charge for execution of civil works massive foundations like Compressor Generator, Turbine, Stack, Steam Turbine Foundations, Equipment Foundation, Pipe Supports, Underground Services, Paving & Roads.
* Planning & controlling movement of the equipment & work force.
3) Global Environment Engineering Ltd (GENL) Oct 95 -Jun 96 Maharastra, India.
Project: Effluent Water Treatment Plant.
Owner: Maharastra Distrillies. Consultant: GENL. Contractor: GENL.
Project Value: IRS 2 Million.
Resident Engineer
* Execution of civil works - Clarifier Tank, Lagoon, Sludge Drying Beds, Pipe Supports & Underground Services (3000 cum)
* Coordination with Sub-contractors.
4) Essar Project Ltd May 94 – Sep 95 Gujarat, India.
Project: 500MW Combined Cycle Power Plant.
Owner: Essar power ltd. Consultant: Tata consultant. Contractor: Essar projects ltd.
Project Value: IRS 350 Million.
Site Engineer
* Executed Foundations for Turbine, Bypass & Main stacks, HRSG, NGL Tank, Pipe Supports, Cable Trenches, Power House Building, & Control Building.
5) Pawan Builders Aug 91–Apr 94 Andhrapradesh, India.
Project: Multistoried Buildings.
Project Value: IRS.10Million.
. Site Engineer.
* Executed one Commercial Building and three Apartments. (1.5 lakh sft)
* Coordination with Architect, Contractors and Sub-contractors.