DATE OF BIRTH: 21 MAY 1954
NATIONALITY: Romanian
STATUS: Married, one child
LANGUAGES: Romanian-Mother, English-Speak and write, Italian-Speak,
French-Read
EDUCATION: Romanian University of Galati
QUALIFICATION: Electro-Mechanical Engineering Faculty
TRAINING:
- Electrical mounting, testing and commissioning of electrical equipment
(circuit breakers, VT, CT, power transformers) for High/Medium/Low Voltage
- Setting of relays
- Calibration of instruments
(pressure transmitter, flow transmitter, temperature transmitter)
COMPUTER PROFICIENCY: WINDOWS, Excel, Word,
WORK EXPERIENCE:
Sept.2000 up to present:
Company NUCLEARMONTAJ ELECTRICAL CONTROL & INSTRUMENTATION, Bucharest, Romania
As General Manager
Examples of a few electrical projects:
* Spent Fuel Storage of Cernavoda Nuclear Power Plant
* Thermo Electrical Power Plant Turnu Severin, Romania (Turbo Generator – 60 MVA)
* Civil building construction
May. 1999 to June 2000: Company SNAMPROGETTI S.P.A - Italy
For Project Ruwais Refinery Expansion –United Arab Emirates.
As electrical coordinator engineer
The project consists of 8 major electrical substations and 3 Emergency Diesel Generators.
I was involved in my job activities as follow:
* For engineering solutions at site,
* For testing and commissioning of DC System, with vendor specialist from GUTOR factory
* For testing and commissioning 3 Diesel Generators, together with specialist vendor
* For pre-commissioning activities for MV (33Kv, 11Kv, 3.3Kv) and LV switchboard along with ABB SACE and S&I together with the specialists vendor
* For pre-commissioning and commissioning for various electrical equipments and motors (11Kv, 3.3Kv and LV)
* For installation and pre-commissioning Cathode Protection system of tanks, fire water pipes and miscellaneous pipes work
Dec 1996 to oct 1998: Company SNAMPROGETTI S.P.A - Italy
For Project BANDAR ABBAS Refinery - NIOC -Iran.
As supervisor
(Telecommunication, Fire fighting and cathode protection systems)
Dec. 1995 to April 1996: Company FOCHI PETROCHEMICAL COMPANY - Italy
For Project Qapco LDPE-2 Expansion Umm Said, Qatar
As instrumentation supervisor
(Mounting cable trays, instruments hook-up and as-built plans)
April 1995 to Dec. 1995: Company FOCHI PETROCHEMICAL COMPANY - Italy
For Project Qapco Utilities Expansion Umm Said, Qatar
As instrumentation supervisor coordinator
(Mounting cable trays, instruments hook-up and loop checks)
June 1994 to Dec. 1994: Company FOCHI PETROCHEMICAL COMPANY - Italy
For Project PVC Petrochemical Complex Bandar Imam, Iran
As electrical & instrumentation supervisor coordinator
(Mounting cable trays, instruments hook-up, pulling and terminal cables, pneumatic adjustment valves, metrology and loop checks)
Jan. 1994 to May 1994: Company FOCHI BUINI GRANDI COMPANY - Italy
For Project Kuwait - Safat Desalination No.3
As electrical supervisor
(Cable tray, pulling and terminal connection of cable)
Feb. 1993 to Jan 1994: Company ENERGOMONTAJ – Bucharest, Romania
For Project Candu Nuclear Power Plant of Cernavoda, Romania
As manager for department electrical construction
(Electrical mounting: transformers, panels, lighting, bus bars, cable trays, and pulling and terminal cables).
April 1989 to Feb. 1993: Company ENERGOMONTAJ – Bucharest, Romania
For Project Candu Nuclear Power Plant of Cernavoda, Romania
As electrical engineer for pre-commissioning
(All tests for transformers of 60MVA / 440MVA, cables, electrical motors, bus bars 6.3KV, 10KV, 24KV)
Oct. 1987 to Mar. 1989: Company ENERGOMONTAJ – Bucharest, Romania
For Project Thermo Electrical Power Plant of Galati, Romania
As electrical control & instrumentation engineer
(Loop checks, metrology instrumentations at the combustible housekeeping of natural gas and fuel oil, and at the boiler 400 tons steam per hour)
May 1987 to Oct. 1989: Company ENERGOMONTAJ – Bucharest, Romania
For Project Thermo Electrical Power Plant of Halânga, Romania
As electrical engineer for pre-commissioning
(Loop checks, metrology, protective relays setting at the turbine protection, electro-filters and at the combustible housekeeping of natural gas, fuel oil and coal)
July 1985 to May 1987: Company ENERGOMONTAJ – Bucharest, Romania
For Project Thermo Electrical Power Plant of Halânga, Romania
As electrical engineer for pre-commissioning
(Loop checks, hi-pot tests, protective relay setting, and electrical insulation resistance at the substations of 110 KV, 6KV and 0.4KV)
July 1984 to July 1985: Company ENERGOMONTAJ – Bucharest, Romania
For Project Thermo Electrical Power Plant of Galati, Romania
As electrical control & instrumentation specialist
(Pre-commissioning, loop checks of boiler automation and adjustment of motorized valves of 400 tons/hours boiler capacity)
April 1982 to July 1984: Company ENERGOMONTAJ – Bucharest, Romania
For Project Thermo Electrical Power Plant of Galati, Romania
As electrical/instrumentation specialist
(Turbo generator of 100MVA, instruments hook-up, cable trays boxes, pulling and terminating cables)
Sept. 1980 to Mar. 1982: Company ENERGOMONTAJ – Bucharest, Romania
For Project Thermo Electrical Power Plant of Galati, Romania
As electrical specialist
(Mounting and pre-commissioning of Power Station Erection (0.4 KV and 6.3KV).