Over twenty-five years experience in Project/Construction Management in an Engineering Procurement and Construction Management environment, specializing in Project Controls, Planning and Scheduling. Project Controls background includes EP, EPC and EPCM both for new installations and fast tracked plant maintenance outages. Responsibilities have encompassed all Project Phases: Proposal Development, Engineering, Procurement, and Construction through Start-up. Hands on working knowledge of WBS coding structure, cost/schedule variance analysis, earned values, Project Trend & Contract Change Notice. Project complexity has included detailed, resource loaded CPM schedules comprising of several thousand activities, with multiple project/contract interfaces and project value in excess of $500 million. A team player with strong interpersonal skills and have had extensive dealings with the client and all levels of management. Strong computer skills including Excel, Access, Word, advanced knowledge of Project Management Software: Primavera's P3, Suretrak, MS Project and Timeline.
EXPERIENCE
SHAW STONE & WEBSTER
Castle Peak Generating Station, Hong Kong
Senior Construction Scheduler – Emissions Control Retrofit Jan. 05 – present
- Develop an overall integrated Master Schedule for the Emission Control Project U# 1 – 4
- Monitor and weekly progress up-dating of Master Schedule
- Integrate the sub-contractors schedule into overall Master Schedule
- Perform "What If" schedule scenario's to analysis decision or change impacts
- Review sub-contractors schedules for logic and contract compliance
- Identify schedule deviations and potential risks for corrective action
ALSTOM POWER
Santee Power - Cross Generating Station, South Carolina
Senior Construction Scheduler - 640 MW Coal Fire Generating Station Dec. 03 - Present
- Develop an overall Construction Schedule for unit #3 & 4 boiler island
- Integrate the sub-contractors schedule into overall construction schedule
- Integrate the commissioning schedule into overall construction schedule
- Review sub-contractors construction schedule for logic and contract compliance
- Analyze performance indicators and identify deviations and potential risks
- Support the Site Manager in risk mitigation
PEARSON CONSULTING INC
Brighton Beach Power Project, Windsor
Construction Scheduling Supervisor - 580 MW (GE7A Frame) CC Power Plant Mar. 03 - Dec
- Develop an overall Master Construction Schedule for a two on one combined cycle power project
- Integration of the main sub-contractor schedules into master construction/commissioning schedule
- Support the commissioning team in schedule development and its integration into the overall master construction/commissioning schedule
- Review of the sub-contractors construction schedule for logic and contract compliance
- Review weekly sub-contractors up-dated schedule and identify deviations and potential risks
- Analyze performance indicators and identify trends that will have negative impacts on the schedule
- Support the Site Manager in risk mitigation and claim reviews.
AMEC ENGINEERING & CONSTRUCTION, OAKVILLE
Lead Planner - Power Group
Project Services Manager - 75 MW Combine Cycle Power Plant Nov., 00 - Mar 03
Lead Planner - Three Gas Compressor Stations (Bolivia) Aug., 02 - Jan 03
Project Services Manager - Continuous Emissions Monitoring (OPG) Mar., 02 - Mar 03
- Establish Engineering Work Breakdown Structure (EWBS) and Engineering Packages (EWP)
- Develop a detailed, resource loaded, integrated Engineering/ Procurement Schedules
- Maintain project schedule
- Analyze performance indicators, identify deviations and potential risks
- Support Project Manager in risk mitigation.
- Develop and maintain overall Project Cost Report, cost to date, Earned Values, Cost/Schedule Variances
- Review of sub-contractors schedule for compliance with overall project schedule
- Maintain Project Trend & Contract Change Notice procedure
- Support of Proposal Development
ALSTOM POWER
Formosa Heavy Industries, Taiwan
Construction Project Planner - 2 x 150MW Pet Coke Fired, CFB Mar 00 - Oct 00
Commissioning Scheduler - 2 x 600MW Coal Fired, Gen. Station Sept 99 - Mar.00
Construction Scheduler - 2 x 600MW Coal Fired, Gen. Station Feb 98 - Sept 99
- Developed detailed CPM construction schedules for Units # 1 & 2 CFB boiler islands.
- Resource loaded and baseline schedules for performance analysis
- Maintained project schedules, analyzed performance indicators and identify deviations and potential risks
- Supported the Site Manager in development of a mitigation strategy.
- Developed detailed Combined Structural Steel and Component Erection Plan/Schedule
- Developed and maintained Project Control Curves and Reports
- Established Project delivery requirements to maintain overall Project Milestones
- Prepare Weekly & Monthly Progress Reports
- Prepared weekly discipline look ahead schedules
- Provide training and support to the client's designates in usage of Primavera's P3 software and Project Controls techniques.
- Developed the overall plant start up schedule
- Maintained and up-dated Commissioning Schedule on a weekly basis
AGRA MONENCO
HRDC, Scarborough, Ont,
Cost/Schedule Analyst March, 1994 - Feb., 1998
- Provided in-house Project Management Services to the Federal Government's Income Security Programs on their Business/Systems Redesign Project.
- Worked with the clients Project Team to develop their Schedule and Project Execution Plan.
- Identified the Crown's contractual obligations and Liquidated Damages risk and supported the development and implementation of Mitigation Plans.
- Developed project budgets and controls.
- Developed a resource loading spreadsheet for workload vs. manpower analysis.
AGRA MONENCO
NB Power, Belledune, N.B.
Senior Planner - N.B. 1 x 400MW Generating Station July, 1991 - June, 1993
- Managed the Boiler, Scrubber, Precipitator, H.P. Piping, Coal Handling and the Main Electrical contract schedules for compliance with the Project Schedule.
- Review contractor's schedules for the reflection and accuracy of contractual and interface dates.
- Co-ordinated contractor's terminal releases to maintain project and contractual milestones.
- Developed and maintained system schedules for commissioning turnover.
- Identify potential schedule conflicts and risks to the Contract Manager.
- Develop monthly project report and progress curves.
- Developed a site manpower tracking and reporting system.
ABB COMBUSTION ENGINEERING
Head Office - Ottawa, Ont.
Supervisor, Construction Planning and Field Administration Jan., 1985 - June, 1991
- Managed Construction Planning /Scheduling for all grass roots and major maintenance Projects.
- Developed project schedules, cost and progress reports, cash flow projections.
- Analyzed project performances and identified risks and trends to the Project Management.
- Provided support in developing mitigation strategy to minimize cost and schedule impacts.
- Co-ordinated problem resolution with other project team members to minimize impact on field activities.
- Mark up of engineering drawings for installation access, leave-out steel requirements and field weld locations.
- Responsible for the requisitioning and delivery of field material and replacement parts.
- Provided in-house support to the client in the development of their project schedules.
- Staff development.
- Departmental representative at the Senior Management Project Review Meetings
- Construction representative and departmental co-ordinator for the Total Quality Management Program (TQM).
ABB COMBUSTION ENGINEERING
NS Power Corp., Lingan N.S.
Q. A. Program Supervisor - 2x 150 MW Coal Fired Boilers May, 1982 - Dec., 1984
- Implemented and controlled the Construction Quality Assurance Program for the installation of two (2) coal fired steam generators, in accordance with ASME and CSA.
ABB COMBUSTION ENGINEERING
Petrosar Chemicals - Sarnia, Ont.
Quality Assurance Program & Field Supervisor May, 1982 - Sept., 1982
- Implemented and controlled the Construction Quality Assurance Program for the installation of M.U. steam generator at a petrochemical expansion, in accordance with ASME and CSA.
- Assisted the construction manager in co-ordinating day-to-day construction activities.
ABB COMBUSTION ENGINEERING
Kimberly Clark of Canada - Terrace Bay, Ont.
Field Planner/Construction Co-ordinator Feb., 1980 - May, 1982
- Developed on-site schedules for a major recovery boiler rebuild & systems up-grade.
- Expedited the receipt of material in accordance with construction requirements
- Co-ordinated field issues and problem resolution with the appropriate areas (engineering, manufacturing).
ABB COMBUSTION ENGINEERING
Head Office - Ottawa, Ont.
Project Planner/Scheduler Sept., 1977 - Jan., 1982
- Developed overall project plans/schedules for engineering, manufacturing and procurement.
- Expedited project requirements and identify deviations to the Project Manager for resolution.
SKILLS: Primavera's P3, Suretrak, MS Project, Timeline, Quiknet, MS Excel, Quattro Pro, Lotus 1-2-3, MS Word, WordPerfect, MS PowerPoint, MS Access, Harvard Graphics,
Internet/Intranet Web Browsers, Windows 3.1/95/98/XP, DOS, Quality Assurance Programs, Matrix Management, TQM, Interpret Engineering Drawings
EDUCATION:
St. Lawrence College Diploma - Business Administration, 1974
SECURITY CLEARANCE: SECRET
Projects List
Location: Project Office
- Kirklareli - Turkey - Two (2) LM 2500 (25MW) Gas Turbine
- New Brunswick Power - St. Rose - Two (2) GT-11 (82 MW) Gas Turbines
- Alberta Power - Forestburg - Unit # 5 - 375 MW Coal Fired Power Plant
- Alberta Power - Sheerness - Units # 1 & 2 - 375 MW Coal Fired Power Plant
- Alberta Power - Keephills - Units # 3 & 4 - 375 MW Coal Fired Power Plant
- Edmonton Power - Genesee - Units # 1 & 2 - 400 MW Coal Fired Power Plant
- Nova Scotia Power - Lingan - Units # 1 & 2 - 150 MW Coal Fired Steam Generator
- Mae Moh - Thailand - 4 Units - 300 MW Coal Fired Power Plant
- Nova Scotia Power - Pt. Tupper - 150 MW Conversion from Oil to Coal Fired Power Plant
- New Brunswick Power - Chatham - 30 MW Fluidized Bed
- Champion Forest Products - Chemical Recovery Boiler
- Domtar - Red Rock, Ont. - Chemical Recovery Boiler
- Malaysia - Chemical Recovery & Bark Burning Power Boiler
- Repap Pulp and Paper Plant - New Brunswick - Chemical Recovery Boiler
- Polysar - Sarnia - MU Power Boiler
- Domtar - Windsor, Que. - Chemical Recovery & Bark Burning Power Boiler
- Paper Dryer, Black Liquor Evaporator System,
Location: Field Office
- China Light & Power- Hong Kong - Castle Peak GS - Units # 1 to 4 - 640 MW Coal SG
- Santee Cooper Power – Cross, South Carolina – 640 MW Coal Fired Steam Generator
- Brighton Beach Power - Windsor, Ont. - 580 MW Combine Cycle w/ GE7A Frame GT's
- Bolivia – Santa Cruz - Three Gas Compressor Stations
- Nova Scotia Power - Lingan - Units # 3 & 4 - 150 MW Coal Fired Steam Generator
- New Brunswick Power - Belledune - Unit # 1 - 400 MW Coal Fired Steam Generator
- New Brunswick Power - Belledune - Unit # 1- Precipitator, H.P. Piping, FGD, Main Electrical
- FHI - Mai Liao - Taiwan - Units # 1 & 2 - 150 MW CFB Power Plant
- FHI - Mai Liao - Taiwan - Units # 4 & 5 - 600 MW Coal Fired Power Plant
- Kimberly Clark - Terrace Bay, Ont. - Chemical Recovery Boiler Rebuild
- Petrosar - Sarnia - MU Power Boiler